ANVILFIELD Try FieldOS

Plumbing

Plumbing cleanout requirements and access field guide

Know what a cleanout is, where the code puts one, how big it has to be, and the clearance to actually rod the line.

CleanoutsDrain AccessIPCUPCPlumbing

Direct answer

A plumbing cleanout is a capped access fitting in a drain line that lets you run a rod or jet to clear a blockage without pulling a fixture or digging up pipe. The code requires them at the base of stacks, the building drain and sewer junction, sharp direction changes, and along the run, hedged to IPC or UPC.

On this pageWhat a cleanout is, and why every drain needs oneThe reason the code requires accessWhere are cleanouts required?The building drain and sewer cleanoutThe base-of-stack cleanoutCleanouts at changes of directionHow far apart should cleanouts be?How big does a cleanout have to be?How much clearance does a cleanout need?Which way the cleanout has to openFloor cleanoutsWall cleanoutsOutside and yard cleanoutsThe two-way cleanout at the property lineWhen a fixture can serve as the accessThe plug and the coverGrease interceptors and special accessHow drain cleaning uses the cleanoutWhy can't I find my cleanout?What the inspector checks on cleanoutsAdding a cleanout to an old systemCommercial, residential, and large-building accessWhat to documentCommon mistakesField checklistStandards and referencesUnits and terms

Key takeaways

  • A plumbing cleanout is a capped access fitting (tee or wye with removable plug) that lets a cable or jet clear a stoppage without pulling a fixture or digging.
  • Cleanouts are required at the base of each vertical stack, the building drain to sewer junction, each change of direction over 45 degrees, and along horizontal runs.
  • Under the IPC, horizontal drains and building sewers under 8 in need a cleanout every 100 ft of developed length; lines 8 in and larger use manholes.
  • Common IPC clearance is at least 18 in in front of cleanouts on pipe over 2 in and 12 in for pipe 2 in and smaller; this is the most violated cleanout rule.
  • Cleanout size matches the pipe up to 4 in under the IPC, and pipe larger than 4 in still uses a 4 in cleanout; verify all figures against the adopted code (IPC or UPC) and AHJ.

What a cleanout is, and why every drain needs one

A plumbing cleanout is a capped access fitting built into a drain line so you can get a cable or a jet hose into the pipe and clear a stoppage. It is a tee or a wye with a threaded or gasketed opening, sized to the pipe, sitting where a blockage is likely to form and where a drain machine can reach it. Pop the plug, feed the rod, clear the line, put the plug back. That is the whole job, and none of it is possible if the access fitting was never installed.

Think about what you do without one. The drain backs up, and the only way into the pipe is to pull a toilet, pull a trap under a sink, climb a roof to rod down a vent, or dig. Every one of those is slower, dirtier, and more likely to break something than threading a cable through a plug you can reach. The cleanout exists so the line can be cleaned over the life of the building, not just on the day it was installed.

That is the reason the code requires them, and it is a maintenance reason, not a flow reason. Drains carry grease, hair, scale, roots, and the stuff people flush that they should not. The pipe is going to clog eventually. The cleanout is the plan for when it does. Size and slope the drain right, covered in the DWV sizing and the building sewer guides, and you still need a way back into the pipe when it stops running.

The reason the code requires access

Drains run by gravity and they foul over time. The code answer to that is access at the spots where a stoppage forms and at intervals you can reach with a machine. A cleanout is not there to make the drain flow better when it is new. It is there for the day someone has to clean it.

The same logic shows up across the trade. You vent a drain so the trap seal holds, which is its own guide. You slope a building sewer so it scours itself. And you put cleanouts in so that when scour and venting are not enough and the line plugs anyway, there is a door into the pipe. The three pieces work together. The cleanout is the one that gets ignored until the line is already full, because it does nothing visible until that day.

A drain with no cleanout is a drain you can only clear by destruction. The next person owns that, usually a service plumber standing in a flooded mechanical room at 2 a.m. looking for an opening that the original crew never put in. That is the failure the code is trying to prevent.

Where are cleanouts required?

Cleanouts are required at the predictable trouble spots of the drainage system: at or near the base of every vertical stack, at the junction where the building drain meets the building sewer, at each change of direction greater than 45 degrees, at intervals along long horizontal runs, near the building exit, and at the upper end of horizontal branches where the code calls for it. The exact list and the wording belong to the adopted code, IPC or UPC, and any local amendments, so confirm against the edition the jurisdiction enforces.

Read the locations as a pattern, not a memorized list. Cleanouts go where solids settle and where a cable would otherwise have to make a turn it cannot make. The base of a stack is where everything that fell down the pipe lands. A sharp bend is where a cable hangs up. A long flat run is where you run out of cable reach. The junction to the sewer is the last reachable point before the line leaves your control.

The two siblings to this point are sized elsewhere. The base-of-stack and direction-change rules ride along with DWV layout, and the building drain and sewer junction cleanout is part of the building sewer install. Both get their own section below, because both are where inspectors look first and where the field most often comes up short.

The building drain and sewer cleanout

The most important cleanout in the building is the one where the building drain leaves and becomes the building sewer. The code requires a cleanout serving that junction, typically at the junction itself or within about 10 ft of developed length upstream of it under the IPC. This is the main cleanout, sometimes called the exit cleanout or house cleanout, and it is the access point for the whole horizontal main and the line heading out to the street.

Put it where a service plumber can actually use it. A main cleanout brought up to grade just inside or just outside the wall, with room to set a drain machine in front of it, is worth more than a code-compliant fitting buried behind a stack of stored material in a back corner. The line that backs up most often is the main, and this is the opening that clears it.

Out at the property line, many jurisdictions and sewer authorities require a two-way cleanout where the building sewer approaches the public main. That fitting lets a plumber rod back toward the building or out toward the city main from one opening, which matters when the question is whose side of the line the blockage is on. The building sewer guide covers the lateral and the tap; the cleanout at that point is the access that proves which side owns the stoppage.

The base-of-stack cleanout

A cleanout is required at or near the base of each vertical waste or soil stack. The bottom of a stack is where everything that drops down the pipe arrives with momentum and then has to turn horizontal, so it is a natural collection point for solids and a natural place for a stoppage to build. The base cleanout gives you a straight or near-straight shot up into the stack and down into the horizontal that carries it away.

Place it so the cable can actually go both ways from the fitting, or at least up the stack, which is the usual direction of trouble. A base cleanout jammed against a wall, or oriented so the cable fights the fitting, technically exists and practically does not. The point is access into the stack, and the geometry of the fitting decides whether you get it.

On a multi-story building each stack gets its base cleanout, and on a tall stack the code may call for additional access up the height of the run. Confirm the spacing and the additional-cleanout rules against the adopted code, because the requirements for tall stacks and for offsets in a stack carry their own provisions.

Cleanouts at changes of direction

Cleanouts are required at each change of direction greater than 45 degrees in the building drain, the building sewer, and horizontal waste or soil lines. A sharp bend is exactly where a drain cable hangs up, because the cable wants to go straight and the pipe makes it turn. Put an opening at the turn and you can feed the cable into the bend from a fitting instead of fighting it from 40 ft away.

The code gives relief when bends stack up close together. Under the IPC, where more than one change of direction occurs in a run, only one cleanout is commonly required for each 40 ft of developed length, so you are not forced to put a fitting at every elbow in a tight jog. Read the exact allowance in the adopted code, because the developed-length number and the way multiple fittings are counted are code-specific.

The judgment call is which bends matter. A long-sweep change that a cable rides through easily is different from a hard quarter bend that stops a cable cold. The code sets the 45-degree trigger; the field sense is to give yourself access at the turns a machine cannot push through, which are the ones that will actually need rodding.

How far apart should cleanouts be?

Horizontal drainage piping inside the building and building sewers smaller than 8 in are commonly required to have cleanouts at intervals of not more than 100 ft of developed length under the IPC. The number comes from how far a drain machine can reasonably push a cable and still have the power to cut through a stoppage. Past about 100 ft the cable loses the stiffness and torque to do real work, so the code keeps openings within reach of each other.

Larger lines change the rule. Building sewers 8 in and larger are typically served by manholes rather than plug cleanouts, with the manhole spacing set by the code, commonly not more than a few hundred feet apart and within a set distance of the junction. Confirm the manhole spacing and the size threshold against the adopted edition, because the large-diameter provisions read differently from the under-8-in cleanout rule.

Spacing is also a UPC-versus-IPC point. The two model codes count developed length and set intervals with their own language, and a jurisdiction may amend either. Do not carry one code's number onto a job governed by the other. The 100 ft figure is the common IPC interval for the usual sizes, not a universal constant.

Location or conditionCommon requirement (verify adopted code)
Base of each vertical stackCleanout at or near the base
Building drain to sewer junctionCleanout at junction or within ~10 ft upstream
Change of direction over 45 degreesCleanout at the change
Horizontal run, pipe under 8 inCleanout every 100 ft of developed length
Building sewer 8 in and largerManholes per code spacing, not plug cleanouts
Property line / building exitTwo-way cleanout where the authority requires it

How big does a cleanout have to be?

A cleanout is sized to the pipe it serves, up to a limit. Under the IPC the cleanout is the same nominal size as the pipe up to 4 in, and for piping larger than 4 in the cleanout need not be larger than 4 in. A 2 in line gets a 2 in cleanout, a 3 in line gets a 3 in, a 4 in line gets a 4 in, and a 6 in or 8 in main also gets a 4 in cleanout, because a 4 in opening is large enough to pass the cable and the cutting heads a drain machine carries.

The reason for full-size up to 4 in is simple: a cleanout smaller than the pipe necks down the opening and a cable or jet hose may not pass a cutter through it, or may not be able to work the full bore of the line. Undersizing the cleanout to save a fitting or to fit a tight space defeats the purpose. The opening has to admit the tool that cleans the pipe.

Confirm the exact sizing language and the 4 in cap against the adopted code, since the UPC and the IPC state it with their own wording and a local amendment can change it. The principle holds across both: match the pipe up to a ceiling, because the cleanout is only useful if the cleaning tool fits through it.

How much clearance does a cleanout need?

A cleanout is required to be accessible, with working clearance in front of the opening to remove the plug and feed a cable straight into the pipe. The common IPC figures are not less than 18 in of clearance in front of cleanouts on piping larger than 2 in, and not less than 12 in for piping 2 in and smaller, measured from and perpendicular to the face of the opening. Larger lines call for more; verify the exact dimensions against the adopted code, because they vary by pipe size and edition.

This is the most violated cleanout requirement in the trade, by a wide margin. A cleanout that meets every location and sizing rule is worthless if a wall, a duct, a water heater, or a slab of stored inventory sits 6 in off the opening. The cable has to go in straight, and the drain machine needs room to sit and turn. No clearance means no rodding, which means you are back to pulling fixtures.

More than that, the code requires cleanouts to be accessible at all, which means not concealed. Required cleanouts are generally barred from concealed locations: inside plenums, buried in finished walls or floor-ceiling assemblies, below grade, or in crawl spaces too low to work in, commonly a minimum crawl height in front of the cleanout. Where piping is concealed in a finished wall or ceiling, the cleanout has to be reachable through an access door or cover plate sized to pull the plug and insert the cleaning equipment. Confirm the concealment rules and the crawl-space height against the adopted edition.

When you set a cleanout, picture the service plumber and the machine, not just the fitting on the drawing. If a person cannot stand a drum machine in front of it and feed a cable, the clearance is wrong even if the tape measure says it passed.

Which way the cleanout has to open

A cleanout is installed to open in a way that lets you clean in the direction of flow, or at right angles to the pipe. The fitting is a tee or a wye oriented so the cable enters and runs down the line the way the water goes, not against it. Set it backward and the cable fights the flow path, fouls in the fitting, and you lose the access you paid for.

On a horizontal run the wye points downstream so the cable rides with the slope toward the stoppage. At the base of a stack the access lets you go up into the stack. The direction is part of what makes the fitting usable, which is why the code calls it out alongside the size and the location.

It is an easy thing to get wrong on a fast rough-in and an expensive thing to discover during a service call. A cleanout that opens the wrong way is a cleanout that has to be cut out and re-set, usually after someone has already wasted an hour trying to push a cable through it.

Floor cleanouts

A floor cleanout brings the access up flush with a finished floor, with a removable cover that sits level with the surface so it does not trip anyone or collect dirt. The body threads onto the riser off the drain, and the cover, often a round brass or nickel-bronze plate, can be set to match tile, terrazzo, or a coated slab. Mechanical rooms, restrooms, kitchens, and basements are where you see them.

The two field problems are finish and burial. On a remodel or a finish-out, the floor cleanout disappears under new carpet, new tile, or a topping slab, and the next plumber spends an hour with a probe looking for it. The fix is to bring the cover up to the new finish and keep it visible, or at minimum to document where it is. A flush cleanout the finish crew tiled over is a cleanout that no longer exists in any useful sense.

Set the height to the finished floor, not the rough slab, so the cover lands flush after the topping or the tile goes down. And keep the clearance in front of it clear of fixed equipment, because a floor cleanout under the front of a water heater is one you cannot use without moving the heater first.

Wall cleanouts

A wall cleanout brings the access out through a wall to a cover plate, used when the cleanout serves piping behind a finished wall or when a stack cleanout is easier to reach at chest height than down at the floor. The fitting sits behind the wall and a stainless or chrome cover plate, often a round plate with a center screw, gives access to the plug. Behind toilets and at the base of stacks in finished spaces is where you find them.

The cover plate has to give real access, not just hide the hole. The code expects the access door or plate to provide clearance to remove the plug and insert the cleaning equipment, so a tiny plate over a deep recess that you cannot get a wrench into does not meet the intent. Size the opening for the work.

The recurring failure is the plate that got painted, tiled, or drywalled over during a remodel. A wall cleanout sealed behind new finish is gone until someone cuts the wall open to find it. When you finish a space, keep the cover plates reachable and operable, and tell the owner where they are.

Outside and yard cleanouts

An exterior cleanout brings the access up to grade outside the building, on the building sewer or the lateral, capped at the surface so a service plumber can rod the line without going inside. It usually terminates in a cleanout box or a valve-style cover set flush with the ground, with the plug protected from dirt and traffic. For a service plumber, the yard cleanout is often the first thing they look for, because it clears the main without tracking through the building.

Grade and landscaping are where yard cleanouts get lost. Sod grows over them, mulch buries them, a flower bed or a new driveway covers them, and the cap that was at grade is now 4 in down under turf. The fix is to keep the cover at finished grade and to leave it findable, because a yard cleanout you cannot find when the main is backing up is the same as not having one.

Protect the cap from vehicle traffic and mower damage, and set the box so it does not fill with silt and lock the plug in place. The building sewer guide covers the lateral itself; the yard cleanout is the access that lets you rod it without a shovel.

The two-way cleanout at the property line

A two-way cleanout is a fitting that lets a cable run in both directions from one opening, back toward the building and out toward the main. It is the standard access at or near the property line where the building sewer meets the public system, and many sewer authorities require it there specifically so a plumber can rod either way from a single point.

The value is in settling whose problem it is. When a main backs up, the question is whether the stoppage is on the owner's lateral or in the public main, and a two-way cleanout at the line lets you rod toward the house to clear the lateral and rod toward the street to check the connection. From one opening you find out which side owns the blockage, which is exactly the information a service call needs first.

Confirm the requirement with the local sewer authority, not just the plumbing code, because the property-line cleanout and the two-way fitting are often a utility or municipal requirement layered on top of the model code. The building sewer guide covers the connection to the main; the two-way cleanout is the access that lives at that boundary.

When a fixture can serve as the access

The code allows a removable fixture or trap to stand in for a cleanout in some cases. A fixture trap or a fixture with an integral trap that can be removed without disturbing the concealed piping is commonly accepted as an equivalent cleanout, and a removable P-trap with slip or ground-joint connections can serve as the cleanout for piping up to one size larger than the trap. A toilet that can be pulled is treated as access to the closet bend in many situations.

Useful, but read the allowance carefully and hedge it to the adopted code. The point is that the access has to be real: you have to be able to pull the fixture or the trap and feed a cable into the line without cutting into concealed pipe. A trap glued solid is not a removable trap, and a fixture you cannot get out without breaking tile is not access.

Lean on this allowance where it fits and the code permits, but do not use it as an excuse to skip a required cleanout where the code wants a dedicated one. The fitting that opens with a wrench beats the fixture you have to unbolt and reset every time the line needs rodding. Confirm what the adopted code accepts as fixture access before you count on it.

The plug and the cover

The plug is what seals the cleanout between uses, and it has to come out when you need it. Threaded plugs in brass or plastic, gasketed mechanical plugs, and expandable test plugs all show up, with the cover plate or access door over the top in finished spaces. The plug seals against sewer gas and keeps water in the pipe, so it is not optional, but it also has to be removable years later by someone who did not install it.

Do not overtighten a threaded plug and do not install it dry into a fitting it can seize in. A brass plug torqued hard into a cast-iron ferrule, or a plastic plug cranked down with a cheater, is a plug that shears or galls when the service plumber tries to back it out, and now the access is a demolition job. Pipe-thread sealant or anti-seize on the threads, snug not gorilla-tight, leaves a plug that comes out clean.

The painted-over and corroded plug is the field reality. A cleanout that has sat for fifteen years often has a plug seized, painted, or rusted into the fitting, and getting it out without cracking the fitting is half the service call. Set plugs so the next person can move them, and the cleanout stays a cleanout instead of becoming a casting you have to replace.

Grease interceptors and special access

Grease interceptors and the kitchen waste lines feeding them carry their own access requirements, because grease is the stoppage you are guaranteed to get in a commercial kitchen. The interceptor itself needs access for cleaning and pumping, and the waste lines on the grease side need cleanouts placed for the reality that they foul faster than sanitary lines. Treat the grease side as a system that will clog, and put the access where you will use it.

The line from the kitchen fixtures to the interceptor is the one that loads up with congealed fat, so the cleanouts on that run earn their keep more than almost any others in the building. A jetter, not just a cable, is often what clears a grease line, which means the access has to admit a jet hose and the clearance has to allow the jetter to work.

Confirm the interceptor sizing, the access, and the maintenance provisions against the adopted plumbing code and the local health and sewer authority, since grease interceptor rules often come from more than the plumbing code alone. The access principle is the same as any other drain, just more so: the grease line will plug, so plan the opening that clears it.

How drain cleaning uses the cleanout

The cleanout is the access the whole drain-cleaning trade runs on. A drum or sectional cable machine feeds a cable with a cutting head through the cleanout and into the line to chew through roots, grease, and scale. A water jetter feeds a high-pressure hose through the same opening to scour the pipe walls and flush the debris downstream. Neither works without an opening that admits the tool.

The opening dictates the tool. A 4 in cleanout on the main takes a large machine with a heavy cable and a jet hose for a big line; a 2 in cleanout on a branch takes a smaller machine and a lighter cable. This is why cleanout size matters past the paperwork: a necked-down or undersized opening forces a smaller tool than the pipe needs, and a small tool may not clear a big stoppage. Match the access to the line and the cleaning gets done from the opening instead of from a pulled fixture.

Clearance is the other half. A jetter and a drum machine both need room to set up and feed line straight into the pipe, which is the same working clearance the code requires in front of the cleanout. The clearance rule is not bureaucratic. It is the space the cleaning equipment physically needs to do the work.

Why can't I find my cleanout?

If you cannot find a cleanout, it is usually because a finish or a landscape buried it, the original crew never installed one, or it exists somewhere with no clearance to use it. These are the common failures, and they all end the same way: a backed-up line and no clean way into the pipe.

The buried cleanout is the most common. A floor cleanout under new tile or carpet, a wall cleanout behind drywall or paint, a yard cleanout under sod, mulch, or a new slab. The fitting is there, the code passed years ago, and now it is invisible. A probe, a camera with a locator, or the as-built drawings find it; lacking those, you are guessing or opening finishes.

The missing cleanout is worse, because there is nothing to find. An older building, or a job where the cleanout requirements were skipped, leaves a drain with no designed access at all, and the only way in is a pulled fixture or a new cleanout cut into the line. The seized plug is the third case: the cleanout is right there, visible, and the plug is rusted, painted, or torqued solid so you cannot open it without cracking the fitting. All three are reasons you cannot clean the line, and all three trace back to how the cleanout was installed and maintained, not to the drain itself.

What the inspector checks on cleanouts

A plumbing inspector checks cleanouts for three things: are they where the code requires them, are they the right size, and are they accessible. The location and the size are on the rough-in. The accessibility is what gets checked again at finish, because that is where a code-compliant fitting gets buried or boxed in by other trades.

On the rough-in inspection the inspector walks the DWV and looks for the base-of-stack cleanouts, the change-of-direction cleanouts, the junction cleanout, and the spacing along the runs, sized to the pipe and opening the right way. On the final, the question is whether you can still get to them: clearance in front, no concealment behind finishes, cover plates and access doors reachable and operable. A cleanout that passed rough and got tiled over fails the intent even when nobody re-checks it.

Treat the inspector's cleanout list as your own pre-check. The permit and inspection process is its own subject, but on the cleanout side the questions are short and the same every time: required locations present, sized correctly, opening the right way, and reachable with clearance to rod. Walk that before the inspector does.

Adding a cleanout to an old system

Older buildings often have drains with too few cleanouts or none at all, and the fix is to cut one in. You add a cleanout by opening the line at a useful spot, installing a cleanout tee or wye and a fitting to a no-hub or compression coupling, and bringing the access out to a floor cover, a wall plate, or a yard box where a machine can reach it. The retrofit cleanout is one of the higher-value upgrades on an old system, because it converts a drain you can only clear by destruction into one you can rod.

Pick the spot for the next stoppage, not for the easiest cut. The main near the exit, the base of a stack, and a sharp bend in a long flat run are where a retrofit cleanout pays off, because those are where the line plugs. A cleanout cut in at a convenient but useless location is wasted work.

Match the new cleanout to the existing pipe material and size, and bring the opening up to a finished, reachable point. Confirm any permit requirement for the work, since cutting into a drainage system is often permitted work even on a repair. The goal is the same as new construction: a sized, accessible opening at the spot the line will actually need it.

Commercial, residential, and large-building access

The cleanout principles are the same across residential and commercial, but the scale and the stakes change. A house has a main cleanout, stack bases, and a yard or property-line cleanout, and a service plumber can usually clear any of it with a drum machine. A commercial building has more stacks, longer horizontal mains, grease lines, and runs that demand the 100 ft interval spacing and the larger access a jetter needs. The bigger the building, the more the cleanout layout has to be designed rather than assumed.

On large mains the access shifts from plug cleanouts to manholes once the pipe crosses the size threshold, commonly 8 in, with the manhole spacing set by the code. A facility with long buried mains across a site is laid out the way a small public sewer is, with manholes for access and rodding, not just threaded plugs. Confirm the size threshold and manhole spacing against the adopted edition.

Critical facilities make the access part of the design, not an afterthought. A data center, a hospital, or a large kitchen cannot take a drain down for a day to chase a stoppage, so the cleanout layout is planned for fast rodding and jetting with clearance designed in and the openings documented. On those jobs the access is a uptime question, and the cleanout that is sized right, placed right, and reachable is what lets the line get cleared without taking the building down with it.

What to document

A cleanout that nobody can locate is a cleanout that does not exist on the day the line backs up. The record is what saves the next service call, so document where every cleanout is, what it serves, and how to get to it. The as-built that marks the floor, wall, and yard cleanouts is worth more than any single fitting when the main plugs years later.

Capture the location of each cleanout, the line and size it serves, the type of access, whether it is floor, wall, or yard, the clearance in front of it, and any cleanout that ended up behind a finish so the owner knows it is there. On a retrofit, note what was added and why. The point is that a plumber arriving cold can find the access and clear the line without opening finishes or guessing.

Field to recordWhy it matters
Cleanout locationA buried or unmarked cleanout is unusable in an emergency
Line served and pipe sizeTells the next plumber what machine and cable to bring
Access type (floor, wall, yard, two-way)Sets how to reach the plug and feed the cable
Clearance in frontConfirms a drain machine can actually work there
Cleanouts behind finishesFlags the ones hidden under tile, paint, or sod
Retrofit additionsExplains a cleanout that is not on the original drawings

Common mistakes

  • No cleanout at a required location: missing the base of a stack, the building drain to sewer junction, or a change of direction over 45 degrees.
  • A code-compliant cleanout buried or covered: floor cleanout under tile or carpet, wall plate behind drywall or paint, yard cleanout under sod or a new slab.
  • No clearance in front to rod, so the fitting exists but a drain machine cannot work there.
  • A plug seized, painted over, or torqued solid so it cannot be removed without cracking the fitting.
  • An undersized cleanout that necks down the opening and will not pass the cable or jet hose the pipe needs.
  • A cleanout installed to open against the flow, so the cable fights the fitting instead of riding the line.
  • Counting a fixture or trap as access where the code wants a dedicated cleanout, or where the trap is not actually removable.

Field checklist

0 of 11 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

Standards and references

The cleanout rules live in the adopted plumbing code, which in most of the country is either the International Plumbing Code, IPC, or the Uniform Plumbing Code, UPC. The IPC handles cleanouts in its sanitary drainage chapter, with provisions for required locations, spacing, sizing, opening direction, clearance, and accessibility. The UPC covers the same ground with its own section numbers and its own wording, and the two do not always match. Confirm which code the jurisdiction has adopted before you cite a number.

The specifics this guide leans on, the 45-degree change-of-direction trigger, the 100 ft spacing for pipe under 8 in, the junction cleanout within about 10 ft upstream, full-size cleanouts up to 4 in, and the 18 in and 12 in clearance figures, are the common IPC values and are stated here as the typical case. Section numbers shift between code cycles and jurisdictions amend them, so verify the exact requirement against the adopted edition and any local amendments rather than carrying these figures onto a submittal as-is.

Cleanout fittings, plugs, and covers are made to product standards under bodies such as ASME and ASSE, and the listing on the fitting tells you what it is rated for. The property-line cleanout, the two-way fitting, and large-diameter manhole access are often driven by the local sewer or water authority on top of the model code. Cite the code that controls the point, name the standard that governs the fitting, and let the AHJ and the adopted edition settle anything the model code leaves to local choice.

Units and terms

Cleanouts go by a few names and the access shows up across the drawings, the fittings, and the service ticket, so the same opening can read differently depending on who wrote it down.

A cleanout is abbreviated CO on plans. The main cleanout is also called the exit cleanout or house cleanout. Developed length is the length measured along the centerline of the pipe and fittings, which is how the code counts spacing, not straight-line distance. Pipe size is nominal diameter in inches. Rodding, snaking, and cabling all mean running a drain machine cable through the line; jetting means running a high-pressure water hose. The AHJ is the authority having jurisdiction, the local official who enforces the adopted code.

Cleanout (CO)
A capped access fitting in a drain line for running a cable or jet to clear a stoppage
Main / exit cleanout
The cleanout serving the building drain to sewer junction, the access to the whole main
Two-way cleanout
A fitting allowing a cable to run both toward the building and toward the sewer main
Developed length
Length measured along the centerline of pipe and fittings, used to set cleanout spacing
Rodding / jetting
Clearing a drain with a powered cable, or with a high-pressure water hose
AHJ
Authority having jurisdiction, the official who enforces the adopted plumbing code

Related tools

Grease-line access is a restaurant maintenance problem that starts with reaching the property owner; PorchRocket's Ground Control offers restaurant building lists with ownership available as an add-on.

Next step: Find drainage access projects

FAQ

What is a plumbing cleanout?

A plumbing cleanout is a capped access fitting in a drain line, a tee or wye with a removable plug, that lets you feed a cable or jet hose into the pipe to clear a stoppage. Without it, the only way into the line is to pull a fixture or dig up the pipe.

Where are cleanouts required?

Cleanouts are commonly required at the base of each vertical stack, the building drain to sewer junction, each change of direction over 45 degrees, at intervals along horizontal runs, and near the building exit. The exact locations belong to the adopted code, IPC or UPC, and any local amendments.

How far apart should cleanouts be?

Horizontal drains and building sewers under 8 in commonly need a cleanout every 100 ft of developed length under the IPC, because that is about how far a drain machine can push a cable. Larger sewers use manholes at code spacing. Verify the interval against the adopted code edition.

How much clearance does a cleanout need?

Common IPC clearance is not less than 18 in in front of cleanouts on pipe larger than 2 in, and 12 in for pipe 2 in and smaller, so a drain machine can feed a cable straight in. Larger lines need more. This clearance rule is the most violated cleanout requirement in the trade.

Why can't I find my cleanout?

Usually a finish or landscape buried it, the original crew never installed one, or it exists with no clearance to use it. A floor cleanout under tile, a wall plate behind drywall, or a yard cleanout under sod is the common case. A camera with a locator or the as-builts find the buried ones.

What size cleanout do I need?

A cleanout is sized to the pipe up to a cap. Under the IPC it matches the pipe nominal size up to 4 in, and pipe larger than 4 in still uses a 4 in cleanout, because that opening passes the cable and cutting heads. Undersizing the opening keeps the cleaning tool from fitting through it.

Can a toilet or trap count as a cleanout?

In some cases yes. The code commonly accepts a removable fixture or trap that comes out without disturbing concealed piping as an equivalent cleanout, and a pulled toilet as access to the closet bend. The access has to be real, and it does not replace a dedicated cleanout where the adopted code requires one.

What do I do if the cleanout plug is seized?

A plug rusted, painted, or torqued solid often has to be worked out with penetrating oil, heat, or a cheater bar, and sometimes the fitting cracks and gets replaced. Prevent it by setting plugs with anti-seize or thread sealant, snug not gorilla-tight, so the next plumber can open them years later.

Do commercial buildings need more cleanouts than houses?

Generally yes. Commercial buildings have more stacks, longer mains, grease lines, and runs that hit the 100 ft spacing rule, so the cleanout layout is designed rather than assumed. Large mains shift from plug cleanouts to manholes once the pipe crosses the size threshold, commonly 8 in. Confirm against the adopted code.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.