Plumbing
Sanitary building sewer: the lateral from building to main
Set the slope so it scours, bed it so it never bellies, put the cleanouts where you can rod it, and connect to the main the way the sewer authority demands.
Direct answer
A building sewer is the buried gravity pipe carrying sanitary waste from the building drain, starting 30 in outside the wall, to the public sewer main or a septic tank. Slope it 1/4 in per ft up to 2 in and 1/8 in per ft on 3 in and larger; the plumbing code and the local sewer authority govern it.
Key takeaways
- A building sewer is the buried gravity pipe from the building drain (starting 30 in outside the wall under the IPC) to the public main or septic tank.
- Minimum slope is 1/4 in per ft up to 2 in, 1/8 in per ft on 3 in and larger, and 1/16 in per ft at 8 in and up; hold the grade uniform.
- Minimum slope targets about 2 ft per second scour velocity; too flat silts in and too steep strands solids on the pipe wall.
- Any building sewer carrying a water closet is 3 in minimum; PVC SDR-35 to ASTM D3034 is the default buried gravity lateral.
- Place cleanouts at the building-sewer junction, not more than 100 ft apart, and at direction changes over 45 degrees; install a backwater valve where a fixture rim sits below the upstream manhole cover.
The building sewer, and what it actually is
A building sewer is the buried gravity pipe that takes sanitary waste from the building and delivers it to the public sewer main or, where there is no main, to a septic system. It is the lateral. It starts where the building drain ends a short distance outside the wall and runs underground across the site to the point of connection. Everything inside the building, the stacks, the branches, the venting, belongs to the drain-waste-vent system covered in the DWV guide. The building sewer is the leg that lives in the dirt.
It does one thing, and it does it without a pump on most jobs: move waste downhill by gravity at a grade steep enough to keep the solids moving and shallow enough that the liquid does not run off and leave them behind. Get the grade right and it runs clean for decades. Get it wrong and you have built a horizontal holding tank that the owner will be rodding for the life of the building.
Two authorities govern this pipe, and people forget the second one. The plumbing code, some edition of the IPC or the UPC with local amendments, controls the slope, the sizing, the cleanouts, and the test. The local water and sewer authority controls the tap, the connection to their main, the materials they will accept at the property line, and who is allowed to make the cut. The authority's rule usually wins at the connection, even where it differs from the plumbing code. Confirm both before you trench. The trench itself answers to a third authority: OSHA excavation rules call for a protective system, sloping back the walls, shoring, or a trench box, once the trench reaches five feet deep, and a competent person has to inspect it before anyone enters.
Where the building drain ends and the building sewer begins
The handoff is a defined point, not a vague zone, and it matters because the rules change at the line. Under the IPC, the building drain extends 30 in beyond the exterior wall in developed length, and the building sewer begins there. The UPC draws the line differently, commonly measured a couple of feet outside the wall. Confirm the number against the adopted code, because it sets where the inside materials stop and the underground materials start.
That transition is also where you put the first cleanout. The code wants a cleanout near the junction of the building drain and the building sewer, brought up to finished grade or to the basement floor, so you have a place to rod the lateral from the building end. On most jobs this is the two-way cleanout in the yard a few feet off the foundation. It is the access point a drain cleaner will look for first, so make it findable and bring it to grade, not to a spot buried under future landscaping.
The DWV guide covers the building drain and everything upstream of this point. This guide picks it up here and follows the pipe to the main. Cross-reference the two so you are not sizing the same run twice or arguing about which code section owns the fitting at the wall.
What slope does a building sewer need?
A building sewer needs at least 1/4 in per ft of fall on pipe up to 2 in, and at least 1/8 in per ft on 3 in and larger, which is the size most sanitary laterals run. At 8 in and up the code allows as little as 1/16 in per ft. Those are minimums from the plumbing code table, and they are minimums for a reason: below them the flow slows down enough that solids settle out and the line plugs.
The grade is the heart of the whole job. Too flat and the line will not scour. The liquid creeps along, the solids drop, and you get a slow build that ends in a backup. Too steep is the mistake people do not expect: when the pipe is much steeper than the minimum, the water can run out from under the solids and leave them stranded on the pipe wall, the same plug from the opposite cause. The target is a uniform grade in the working range that carries everything together.
Uniform is the word that does the work. A line that averages 1/4 in per ft but does it as a roller coaster, steep here and flat there, behaves like its flattest spot, not its average. Set the grade with a laser or a transit and a grade rod, hold it across every joint, and check it before backfill. The 3 in minimum size applies to any building sewer carrying a water closet.
| Pipe size | Minimum slope (plumbing code) | Drop over 100 ft |
|---|---|---|
| 1-1/4 to 2 in | 1/4 in per ft | 25 in |
| 3 in | 1/8 in per ft | 12.5 in |
| 4 in | 1/8 in per ft | 12.5 in |
| 6 in | 1/8 in per ft | 12.5 in |
| 8 in and larger | 1/16 in per ft | 6.25 in |
Scour velocity: why the minimum slope is what it is
The slope numbers are not arbitrary. They exist to hold a minimum flow velocity of about 2 ft per second, the scour velocity, the speed at which moving water keeps solids in suspension instead of letting them settle and stick. Drop below it and the line stops cleaning itself. The 1/8 in per ft on a 4 in pipe is the grade that gets a partially full line up to roughly that speed.
This is why a flatter run is a false economy. People shave the grade to save depth at the connection, the line tests fine empty, and the trouble shows up a year later as a recurring backup that gets blamed on the homeowner flushing wipes. Often it is the grade. A line that never reaches scour velocity accumulates a little every day until it does not pass.
Half-full flow matters here too. A building sewer rarely runs full; it runs partly full most of the day. The velocity the design cares about is the velocity at real, partial flow, which is why the code ties the minimum slope to pipe size rather than letting you average it out. The smaller the pipe at a given slope, the easier it is to hold velocity, which is part of why oversizing a lateral can hurt: a too-large pipe at low flow runs shallow and slow and silts in.
How is a building sewer sized?
A building sewer is sized by drainage fixture units and slope, off the plumbing code table for building drains and sewers, the same DFU currency the DWV guide uses for the interior drains. You total the fixture units the lateral carries, pick a slope, and read the smallest pipe that the table allows to carry that load at that grade. Slope and capacity are linked: a steeper grade lets a given pipe carry more DFU, a flatter grade less.
The numbers move with the code, so verify them against the adopted edition, but the shape is stable. A 4 in building sewer at 1/8 in per ft carries a large residential and light commercial load, into the low hundreds of DFU in the common tables, which is why 4 in is the default lateral for a house and many small commercial buildings. Step up to 6 in when the fixture count, a food service load, or the authority's rule calls for it.
Two field cautions. First, the minimum size for any building sewer carrying a water closet is 3 in, so you never run a toilet to a 2 in lateral no matter what the DFU math suggests. Second, bigger is not automatically better. A lateral sized well past the load runs shallow and slow at normal flow and silts in, the same scour problem from the other direction. Size it to the load and the slope, not to the largest pipe on the truck.
| Building sewer size | Slope | Approx. max DFU (verify to code edition) |
|---|---|---|
| 3 in | 1/4 in per ft | ~42 DFU |
| 4 in | 1/8 in per ft | ~180 DFU |
| 4 in | 1/4 in per ft | ~216 DFU |
| 6 in | 1/8 in per ft | ~700 DFU |
Pipe materials: SDR-35, schedule 40, cast iron, ductile
The common building sewer pipe is PVC SDR-35 to ASTM D3034, the green or white gasketed sewer pipe made for buried gravity flow outside the building. It joins with a bell-and-spigot gasket, not solvent cement, so the joints flex a little with the ground and seat fast. Its wall is thinner relative to diameter than schedule 40 because it is rated as a buried gravity pipe, not a pressure or in-building pipe. It is not approved inside buildings or for venting.
Schedule 40 PVC DWV, the heavier-wall solvent-welded pipe, shows up at the transition near the building and wherever the local code or the depth-and-load condition calls for a heavier wall. Cast iron is still specified under roads, under structures, where fire-resistive construction or sound rating drives it, and where an owner or authority wants the durability. Ductile iron earns its place under heavy traffic, at shallow cover under a drive, and on large-diameter site mains. The authority's accepted-materials list at the property line can be narrower than the plumbing code, so check it.
Mind the joint type to the pipe. SDR-35 is gasketed; schedule 40 is solvent-welded; transitions between dissimilar materials need the proper listed coupling, not a rag and hope. The cheap mistake is a shielded no-hub band where the code wants a full-body transition coupling, or solvent cement on a gasketed bell. Match the joint to the pipe and the listing every time.
| Material | Standard / spec | Joint | Where it fits |
|---|---|---|---|
| PVC SDR-35 | ASTM D3034 | Gasketed bell and spigot | Default buried gravity lateral outside the building |
| PVC schedule 40 DWV | ASTM D2665 | Solvent weld | Transition near building, heavier-wall runs |
| Cast iron (hub or no-hub) | ASTM A74 / CISPI 301 | Gasket or no-hub band | Under structures, roads, fire-rated or sound-rated |
| Ductile iron | AWWA / ASTM | Push-on or mechanical joint | Heavy traffic, shallow cover, large site mains |
Bedding and the trench: support the whole pipe, not the bells
A building sewer fails as often from how it was bedded as from how it was sloped. The pipe wants continuous, uniform support along its entire length, sitting on a graded granular bed, with the same granular material worked up into the haunches to the springline so the bottom third is fully supported and braced against the sides. Clean crushed stone or pea gravel, a Class I bedding, is the usual material. The trench bottom gets trimmed smooth to the grade you set, free of rock, clods, and frozen lumps.
The two killers are point loading and the belly. A pipe resting on a single rock or a hard high spot carries the backfill load at that point instead of spreading it, and SDR-35 or cast iron will crack there under the cover and the traffic above. Bell holes matter for the same reason: on bell-and-spigot pipe you dig a relief at each hub so the pipe bears on the barrel, not on the bells, and the line is uniformly supported instead of teetering bell to bell.
The belly is the slope failure that hides in the bedding. Lay the pipe on soft, uncompacted, or uneven bedding and it settles unevenly after backfill, and a low spot forms that holds water and traps solids. The line tested fine the day you laid it. A year later it has a sag that no amount of rodding fixes. Compact the bedding, hold the grade across every joint, and do not lay pipe in a trench with water standing in the bottom. The grade you build is only as good as the bed it sits on.
Depth and cover: frost, traffic, and the slope that sets it
Depth on a sanitary lateral is driven by three things at once: enough cover to protect the pipe, enough depth to clear the frost line where freezing matters, and the depth the slope itself forces over the length of the run. The last one catches people. A long lateral at 1/8 in per ft drops over a foot every 100 ft, so by the time you reach a distant main the pipe is deep, wanted or not. You start at the building at the depth the building drain leaves, and the grade takes it down from there.
For cover, the common floor is around 12 in of cover where the ground does not freeze, deeper where it does, and the rule of thumb is to keep the pipe below the local frost depth so a partially full line at low flow cannot freeze. Sanitary lines are usually deep enough that frost is not the limit; the slope and the main's invert are. Under traffic the numbers go up: a trench that takes construction or vehicle loading commonly wants 3 ft of cover, more under heavy compaction equipment. Confirm the local frost depth and the cover requirement with the authority; they vary by climate and jurisdiction.
Where the slope would drive the lateral deeper than you can dig or deeper than the main sits, that is the signal that gravity alone will not reach, and you are into a pump. That decision is its own section.
Where do cleanouts go on a building sewer?
Cleanouts go where a drain cleaner needs to put a rod or a camera into the line, and the code is specific about it. The plumbing code wants a cleanout near the junction of the building drain and the building sewer, cleanouts spaced not more than 100 ft apart along the run, and a cleanout at each change of direction greater than 45 degrees. Many local sewer authorities add one more at or near the property line, at the edge of the public right of way, marking the boundary between what the owner maintains and what the utility maintains.
The 100 ft figure is the rodding reach. Sewer rods and cable machines have a practical range, and a cleanout every 100 ft means any point in the lateral can be reached from one end or the other. Where several bends stack up in a short run, the code lets one cleanout cover a run that turns through several fittings rather than demanding one at every elbow, with the allowance tied to the total degrees of bend the run accumulates rather than a fixed footage. Read the exact allowance in the adopted code.
Bring every cleanout to grade and make it findable. A cleanout buried 8 in down under sod is a cleanout that gets jackhammered out of a driveway at 11 at night during a backup. On large sewers, 8 in and up, the code moves from cleanouts to manholes, spaced farther apart, because you are now into pipe a person works in rather than rods. The point does not change: build the access in now, where it is cheap, because the line will need it.
The tap: connecting to the public main
The connection to the public sewer belongs to the local sewer authority, and their rule governs, full stop. They specify how you tie in, who is allowed to make the cut, the permit, the inspection, and often the materials and the contractor's qualification. Do not assume the plumbing code controls here. The utility's standard detail does.
The tie-in itself is one of a few methods. The clean one is an existing wye or stub the utility left for the lateral when the main was laid, and you connect to it. Where there is no stub, you tap the live main, commonly with a saddle or an inserted wye fitting made for the main's material and size, cut and set under the utility's inspection so the tap is smooth, sealed, and aimed downstream so the lateral flow enters with the main flow, not against it. On larger systems the lateral may land in a manhole instead of the main barrel, channeled into the invert so it does not splash or build a shelf.
Two things go wrong here that the inspector watches for. A tap that protrudes into the main, a hammer tap punched without a proper saddle, snags rags and roots and becomes the choke point for the whole street. And a lateral that enters against the flow or at the wrong elevation backs up at the connection. Aim it downstream, set it to the utility's invert, and let them inspect it before you cover it. This is not the joint to backfill on a Friday and call in Monday.
When there is no main: connecting to a septic system
Where no public sewer is available, the building sewer runs to a septic tank instead of a main, and the rules shift to the health authority and the onsite wastewater code on top of the plumbing code. The lateral is the same gravity pipe at the same slope, but it terminates at the tank inlet, and the inlet has its own requirements: a tee or baffle, a watertight connection, and a tank set at a depth and elevation that the lateral grade can actually reach.
The grade discipline is identical and the stakes are the same. A lateral that bellies or runs flat into a septic tank plugs exactly the way it would into a main, except now the backup is into a building with no municipal system to blame. The tank is sized and sited by the soil and the loading, which is the health department's call, and the drainfield downstream of the tank is a separate design entirely. The plumber owns the lateral to the tank inlet; confirm where that responsibility line sits on the permit.
If the building's lowest fixtures sit below the tank inlet or the drainfield, gravity will not carry them, and you are into a pump or an effluent system, the same reach problem a deep main creates. Coordinate the tank elevation with the building drain elevation early, before the foundation is poured, because moving a tank is cheaper on paper than recutting a foundation penetration.
When do you need a backwater valve?
You need a backwater valve when a building's fixtures sit low enough that the public sewer could back up into them. The plumbing code draws the line at the manhole: where the flood level rim of a fixture is below the elevation of the cover of the next upstream manhole in the public sewer, that fixture has to be protected by a backwater valve. The logic is plain. If the street sewer surcharges and the water rises in that upstream manhole, it will find any opening below that level, and a basement floor drain below the manhole rim is exactly that opening.
The detail that trips people is the other half of the rule. Fixtures above the upstream manhole rim must not discharge through a backwater valve. You protect only the low fixtures, and you let the high fixtures drain freely past, because if the valve closes on a surcharge you still want the upper floors draining, and you do not want the whole building's flow throttled through one valve. So the valve goes on the branch serving the low fixtures, not on the whole building sewer, unless every fixture is below the line.
A backwater valve is a check valve for sewage: a flapper that opens for outgoing flow and snaps shut when flow tries to come back. It is also a maintenance item the owner inherits, because the flapper fouls with grease and debris and stops sealing. Put it in an accessible pit or chamber with a cleanout, not buried where nobody can service it. Confirm the elevation against the actual upstream manhole, not a guess. This is a hazard call, and a missed backwater valve is a flooded basement full of sewage, so verify the rim elevation, do not assume it.
Call 811 and locate before you dig
Before the trench, the utilities get located. Call 811, the one-call center, and have the existing lines marked, gas, electric, water, communications, and the existing sewer you may be connecting to. This is not paperwork. It is the step that keeps you from putting a backhoe tooth through a gas main on a sanitary job.
The locate also tells you what you are tying into and at what depth, which you need before you commit the lateral grade. Finding the main's invert by potholing at the connection, by hand or with a vacuum excavator, before you set the trench depth at the building, keeps you from trenching a beautiful 1/8 in per ft run that arrives 2 ft above or below where the main actually sits. Verify the connection elevation first, then set the grade to hit it.
Private utilities on the site, the ones 811 does not mark because they are past the meter, are on you to locate. A site with existing buildings is full of abandoned and undocumented lines. Dig the connection carefully and assume the as-builts are wrong until you have eyes on the pipe.
When gravity will not reach: lift stations and ejectors
Gravity is the whole premise of a building sewer, and when the geometry breaks it, you pump. The trigger is elevation: fixtures below the main's invert, a basement below the sewer level, or a site so flat or so long that holding minimum slope would put the lateral deeper than the main or deeper than you can practically dig. When the grade cannot reach, gravity is out and a pump is in.
For a building or a basement below the sewer, that is a sewage ejector or a sump-and-ejector arrangement collecting the low fixtures in a sealed basin and pumping their discharge up to a point where gravity takes over into the lateral. That equipment, the basin, the pump, the vent, and the check valve, is its own design, covered where the sump and ejector work is detailed. For a site or a campus, it scales up to a lift station, a wet well with duplex pumps that lifts the collected sanitary flow over a high point to a gravity main beyond.
Two things to carry from here. Anything pumped needs a check valve so the lifted flow cannot drain back, and the pumped, pressurized leg is a force main, not a gravity sewer, sized and built to different rules than the lateral feeding the basin. Where the force main discharges back to gravity, the transition has to be detailed so it does not hammer or back-siphon. A pump is a maintenance liability and a power dependency the gravity line never had, so use gravity wherever the elevation allows and pump only where it does not.
How do you test a building sewer?
You test the building sewer for leaks before it is buried, because once the trench is backfilled, finding and fixing a leak means digging it back up. The plumbing code accepts a water test or an air test on the drainage piping. The water test fills the line and holds a head of water on it, commonly a 10 ft head, and you watch for the level to drop. The air test puts a low, measured air pressure on the capped line and watches the gauge for decay. Either way, it holds pressure or it fails.
On site sewers and utility-owned mains, the sewer authority usually dictates the test and the acceptance criteria, and it is often more than the plumbing code's leak test. Low-pressure air testing on the mains, and for plastic pipe a deflection test where a go/no-go mandrel is pulled through the line, commonly some weeks after backfill, to confirm the pipe has not been squashed out of round beyond a set limit, often around 5 percent. A camera, a CCTV run, is the acceptance step that finds bellies, sags, intruding taps, and debris that a pressure test cannot. Verify which tests the authority requires and when.
Get the inspector on the open trench. The whole reason to test before backfill is so the leak, the belly, or the bad joint is visible and reachable. An inspector signs off on the slope, the bedding, the cleanouts, and the connection while the pipe is exposed. Cover it first and you may be uncovering it. Schedule the inspection into the dig, not around it.
Large-site and data center sanitary
On a large site, a warehouse, a campus, a data center, the building sewer becomes a site sanitary system: multiple laterals, larger diameters, manholes instead of cleanouts on the big runs, and a network that has to be coordinated against the storm system, the water service, and everything else underground. The slope and scour rules do not change. The coordination is what gets hard.
Separation is the constant fight. Sanitary stays separate from storm, which has its own guide, and both have to clear the water service with the required separation, commonly 10 feet horizontally and, where they cross, 18 inches of vertical clearance with the water line above, so a sewer leak cannot contaminate potable water. Crossings get detailed, not improvised. On a data center the sanitary load is small relative to the building, mostly restrooms and mechanical drainage, but the site is large and the runs are long, so holding minimum slope over a long flat lateral and keeping it scouring is the real problem, not the fixture count.
Manholes take over from cleanouts on the larger pipe, set at the spacing the code and authority require, at junctions and changes of direction, channeled so flow runs through the invert cleanly. The bigger the system, the more the local authority's standard details govern, and the less you freelance. Build the access in, hold the grade, and keep the as-built accurate, because nobody is rodding a 10 in site main from a cleanout.
Keeping it running after turnover
The day the lateral passes inspection, the owner inherits a maintenance item, and how you built it decides how bad that job is. The cleanouts you brought to grade are what a drain cleaner uses to rod and camera the line. The cleanouts you buried are what costs the owner a service call just to find access. Build for the person who will be standing over this pipe at midnight in five years.
Roots are the long-term enemy of a gravity lateral. Joints that weep, especially older or disturbed joints, draw roots that find the moisture and grow into the pipe until they net the flow and catch everything. A gasketed, properly seated SDR-35 line laid in good bedding resists it; a cracked, bellied, or root-prone line becomes an annual rodding contract. Bedding and joint quality you cannot see after backfill are exactly what determine this.
Grease is the other one, heavy on any food service or commercial kitchen lateral, and it has its own controls covered where grease interceptors are detailed. The short version for the lateral: where grease is in the waste stream, the code wants a steeper minimum slope on the piping upstream of the interceptor, commonly 1/4 in per ft regardless of pipe size, because grease congeals and needs the velocity to keep moving. Build the grease side steep, keep the interceptor accessible, and the lateral has a chance. Build it flat and it ropes shut.
What to document
A buried lateral that nobody recorded is a lateral the next crew has to find with a camera and a locator. The record is what lets the owner, the next plumber, and the inspector know what is in the ground and where. Capture it segment by segment, because a lateral is rarely one size and one slope end to end.
For each segment, record the size, the slope you built, the material and joint type, the cleanout and manhole locations with depths brought to a fixed reference, the connection detail at the main or tank, and the test results with the inspector's sign-off. Note the depths and the connection elevation, because the as-built is what tells someone three feet down where the pipe should be before they dig blind for it. If you put in a backwater valve or a pump, document its location, its access, and the elevation logic behind it.
| Field to record | Why it matters |
|---|---|
| Segment size and material | Sizing, sourcing, and the right coupling for a future repair |
| Slope built, per segment | Proves scour grade and finds the belly if one forms |
| Cleanout and manhole locations, depths | Where the next crew rods and cameras the line |
| Connection detail at main or tank | The utility's tie-in, for their records and the next tap |
| Backwater valve / pump location and elevation | Where the protection is and why it sits there |
| Test type, result, inspector sign-off | The proof it held before backfill |
Common mistakes
- Running the lateral too flat, below minimum slope, so it never reaches scour velocity and silts in.
- Running it too steep so the liquid outruns the solids and strands them on the pipe wall.
- Laying pipe on uneven or uncompacted bedding so it settles into a belly that holds water and traps solids.
- Point-loading the pipe on a rock or a hard high spot, or bearing on the bells, so it cracks under cover.
- Too few cleanouts, or cleanouts buried below grade where nobody can find or use them.
- Tapping the public main without the authority's permit, saddle, and inspection, or aiming the lateral against the flow.
- Skipping the backwater valve where fixtures sit below the upstream manhole rim, or installing one where it throttles the whole building.
- Oversizing the lateral so it runs shallow and slow at normal flow and silts in.
- Backfilling before the leak test, the inspection, and the locate of what you tied into.
Field checklist
Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.
Standards and references
The plumbing code, IPC or UPC depending on the jurisdiction with local amendments, is the framework for the building sewer: the slope table, the DFU sizing tables for building drains and sewers, the cleanout spacing, the backwater valve rule, and the leak test. The IPC and UPC do not agree on every number, including where the building drain ends and the sewer begins, so confirm which code and which edition the AHJ has adopted before sizing or laying anything off memory.
The local water and sewer authority governs the connection to the public main, the materials accepted at the property line, the tap method, the permit, and the acceptance test and criteria for the lateral and any utility-owned pipe. Where their rule and the plumbing code differ at the connection, the authority's standard detail controls. For onsite systems, the health department and the onsite wastewater rules govern the septic tank and the drainfield.
Pipe materials carry their own standards: ASTM D3034 for PVC SDR-35 sewer pipe, ASTM D2665 for schedule 40 PVC DWV, ASTM A74 and CISPI 301 for cast iron, and AWWA and ASTM specs for ductile iron. Acceptance testing on site sewers, low-pressure air and the deflection mandrel for plastic pipe, follows the authority's specification. And 811, the one-call locate, is the required step before any excavation. Cite the standard that controls the point, confirm the section against the adopted edition, and let the authority's detail override the rule of thumb at the connection.
Units, terms, and conversions
The building sewer goes by a few names and a few unit conventions, so the same pipe reads differently across a plan set, a utility detail, and a spec.
The building sewer is also called the sanitary lateral, the lateral, or the house connection. Slope is given as a fraction of an inch of fall per foot of run, 1/4 in per ft and 1/8 in per ft, or as a percent, where 1/8 in per ft is about 1 percent and 1/4 in per ft is about 2 percent. Velocity is in feet per second, with 2 ft per second the scour figure. Pipe size is the nominal diameter in inches. Load is in drainage fixture units, the same DFU currency the interior DWV system uses, carried out to the main.
- Building sewer / lateral
- The buried gravity pipe from the building drain to the public main or septic tank
- Building drain
- The lowest interior drainage piping, extending a short distance outside the wall where the sewer begins
- Slope / grade
- Fall per length, given as inches per foot or percent; 1/8 in per ft is about 1 percent
- Scour velocity
- About 2 ft per second, the flow speed that keeps solids in suspension so the line self-cleans
- DFU
- Drainage fixture unit, the load currency that sizes the sewer against the code table
- Backwater valve
- A check valve in the drainage line that closes against a backup from the public sewer
- Force main
- Pressurized pipe downstream of a pump or ejector, sized and built differently than a gravity sewer
FAQ
What is a building sewer?
A building sewer, also called the sanitary lateral, is the buried gravity pipe that carries waste from the building drain across the site to the public sewer main or a septic tank. It begins a short distance outside the wall. The owner typically maintains it to the property line, the utility beyond.
What slope does a building sewer need?
A building sewer needs at least 1/4 in per ft of fall on pipe up to 2 in and at least 1/8 in per ft on 3 in and larger, per the plumbing code table. Those minimums hold roughly 2 ft per second scour velocity. Keep the grade uniform; too flat silts in and too steep strands solids.
How is a building sewer sized?
Size a building sewer by total drainage fixture units and slope, off the plumbing code table for building drains and sewers. A 4 in lateral at 1/8 in per ft covers most houses and small commercial. Any sewer carrying a water closet is 3 in minimum. Verify the DFU numbers against the adopted code edition.
What pipe is used for a building sewer?
The common building sewer pipe is PVC SDR-35 to ASTM D3034, gasketed bell-and-spigot pipe made for buried gravity flow. Schedule 40 PVC, cast iron, and ductile iron are used at transitions, under structures and roads, and under heavy traffic. The local sewer authority's accepted-materials list at the property line can be narrower than the code.
Where do cleanouts go on a building sewer?
Cleanouts go near the building drain to building sewer junction, not more than 100 ft apart along the run, and at each change of direction greater than 45 degrees. Many authorities add one at the property line. Bring every cleanout to grade so it can be found and rodded. Larger sewers use manholes instead.
When do you need a backwater valve?
You need a backwater valve when a fixture's flood level rim sits below the cover elevation of the next upstream manhole in the public sewer, because a surcharge could back up into it. Protect only the low fixtures. Fixtures above that rim must not discharge through the valve. Verify the actual manhole rim elevation.
How deep should a building sewer be buried?
A building sewer is buried deep enough to protect the pipe, clear the local frost line, and meet the slope over its length, often 12 in of cover minimum where ground does not freeze and 3 ft or more under traffic. On long runs the slope drives depth more than cover does. Confirm frost depth and cover with the authority.
Does the building sewer share a trench with the water service?
Generally no, not without meeting the required separation. The plumbing code and health rules call for vertical and horizontal separation between the sanitary sewer and the potable water service so a sewer leak cannot contaminate water. Where they must cross, the crossing is detailed to maintain separation. Confirm the separation distances with the adopted code and authority.
How do you test a building sewer before backfill?
Test it with a water test, commonly a 10 ft head of water held on the line, or a low-pressure air test, watching for the pressure to hold. On site sewers, the authority may also require a deflection mandrel for plastic pipe and a camera run. Test and get the inspector on the open trench before you backfill.
What do I do if the building sewer fails its test or backs up?
If it fails a leak test, find and reseat or replace the bad joint while the trench is open. If it backs up after service, camera the line: a recurring backup is usually a belly from bad bedding, a flat grade below scour velocity, roots at a joint, or grease, not a one-time clog. Fix the cause, not the symptom.
People also ask
Codes cited in this guide
This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.