ANSI Z223.1 and NFPA 54: 2027 fuel gas changes and project scope

ANSI Z223.1 and NFPA 54 are two designations for the same jointly developed National Fuel Gas Code. NFPA identifies 2027 as its current edition. It covers building fuel-gas piping and appliance installation, including air supply, inspection, testing, purging, and venting. The new edition adds hydrogen-blend provisions and changes to regulator testing, unpurged-pipe removal, and combustion-air calculations. The permit's adopted edition still establishes the project's code basis.

Current edition: NFPA 54/ANSI Z223.1, National Fuel Gas Code, 2027 edition (2027)
Updated

Official publisher page

Applies to

Gas piping designers, licensed installers, HVAC contractors, facility managers, utilities, and inspectors use the code across residential, commercial, and industrial installations. AGA serves as secretariat to ASC Z223; the joint committee develops the document with NFPA's fuel-gas committee.

An equipment replacement can retain the pipe route while changing the fuel, combustion-air calculation, or regulator arrangements. Identify those changed inputs on the natural gas piping schedule before carrying forward the previous installation's approvals.

Key topics

Hydrogen blending changes the fuel description on the design basis

NFPA's 2027 summary puts natural-gas blends at or below 20 percent hydrogen by volume within the piping provisions without additional piping considerations for that blend. A fuel analysis reporting 20 percent hydrogen reaches that boundary; a 25 percent blend exceeds it. These percentages describe composition by volume, not the fraction of delivered heat. Submit the fuel analysis with the appliance's approved fuel information so the piping decision and equipment decision use the same fuel description.

Removing unpurged piping requires a qualified agency

NFPA identifies a new 2027 requirement for a qualified agency to remove unpurged gas piping. Identify that removal scope in renovation documents, including the responsible agency and the system boundary. A demolition allowance that merely calls for removing abandoned pipe leaves the gas condition and assigned responsibility unresolved. Keep the removal authorization distinct from the new installation's inspection and startup record.

Regulator testing needs a designed means of access

NFPA's 2027 summary identifies a new requirement to provide a means of testing line pressure regulators. Put that requirement into the regulator and piping coordination before concealment. The installed arrangement must support the required testing; an approved regulator catalog sheet alone does not show that the completed piping provides it. Coordinate the service access and test provisions with the accepted equipment layout.

The 2027 combustion-air method drops the fan-assisted equation

NFPA says the 2027 known-air-infiltration-rate method removes the separate equation for fan-assisted appliances. Revalidate stored calculation sheets when the project uses the new edition, including spreadsheets that choose a formula from appliance type. The connected equipment schedule and the governing air-supply calculation must remain coordinated. The water-heater venting guide explains why an equipment replacement also changes the shared air and venting questions.

How it is used in the field

Use one code-basis line on the permit drawings: National Fuel Gas Code, NFPA 54/ANSI Z223.1, the adopted edition, and the applicable amendments. AGA's committee description establishes the joint designation. Reconcile any different year in the equipment specification before issuing the installation package.

At a building renovation, separate retained piping, new piping, removed piping, pressure regulation, appliance connections, combustion air, and venting on the scope drawing. This exposes the handoffs between the gas installer, demolition contractor, equipment supplier, and inspection authority before those boundaries are hidden in a single gas-work allowance.

A replacement schedule contains two furnaces and one atmospheric water heater. List each appliance's input and combustion-air source on the calculation sheet. For a project using 2027, the retired fan-assisted equation must not remain hidden in a spreadsheet branch selected by appliance type. Record the revised formula and equipment schedule together so the inspection record can reproduce the accepted air-supply calculation.

Close the installation with the approved piping revision, required test records, regulator information, appliance fuel documentation, and the air-and-venting basis. The propane system guide explains the separate storage and supply interface with NFPA 58. Keep that supply scope identifiable rather than applying a downstream building-piping reference to the entire storage installation.

Edition history

As of November 5, 2026, NFPA's document listing identifies 2027 as current and links its 2027 reading access. AGA's committee page still labels 2024 current and records that edition's ANSI approval on November 1, 2023. Use NFPA's current publication listing to identify the latest edition and the jurisdiction's adoption record to identify the edition governing the permit.

Adoption

Jurisdictions adopt fuel-gas requirements through their governing codes and amendments; the IFGC is another model-code pathway used in building work. State the permit basis before changing a calculation or inspection form. NFPA's current-edition listing does not by itself revise an adopted 2024 or earlier project requirement.

Frequently asked questions

Are ANSI Z223.1 and NFPA 54 different fuel gas codes?

AGA identifies them as the same jointly developed National Fuel Gas Code. Match the edition and amendments when reconciling the two designations in a contract.

Does the 20 percent hydrogen piping provision approve every appliance?

NFPA's summary addresses the fuel-gas piping provisions. The appliance's recognized fuel and manufacturer's instructions remain separate equipment requirements, so the fuel description must reach the appliance review as well.