ASTM C270: mortar types, laboratory strengths and acceptance routes

Mortar compliance under ASTM C270-26 follows one of two routes: specified ingredient proportions or properties established with laboratory-prepared mortar. The routes are alternatives, and a field mortar strength is not a substitute for the laboratory property test. When neither route is specified, the proportion route governs unless the specifier accepts property data. Resolve that selection before batching so the submittal, inspection and test assignment all address the same requirement.

Current edition: ASTM C270-26 (2026)
Updated

Official publisher page

Applies to

Masonry specifiers choose the compliance route; suppliers and laboratories provide the corresponding evidence; inspectors verify the approved materials and batching. Mortar-type selection in the masonry construction guide leads to a second decision: which compliance route the laboratory and inspector will use to verify that particular mortar.

Key topics

Choose one compliance route before the submittal

ASTM C270-26 makes proportion compliance the default when the documents select neither route, unless property data are presented and accepted by the specifier. CMHA TEK 18-05B explains that the two routes are independent. Do not require a proportion-specified mortar to meet a borrowed property-table strength as an additional acceptance test. Identify the route explicitly on the approved mix record and inspection form.

Which strength belongs to Type M, S, N or O?

CMHA TEK 09-01A lists C270 laboratory property minima at 28 days of 2,500 psi for M, 1,800 psi for S, 750 psi for N and 350 psi for O. These are average strengths of laboratory-prepared mortar, not a site-cylinder rejection scale. Read the type together with the compliance route and specimen preparation. Type S on a bag does not authorize comparing a field cylinder with the 1,800 psi laboratory value.

Laboratory flow controls the property comparison

CMHA TEK 18-05B describes C270 property testing with laboratory mortar adjusted to 110% ± 5% flow. Its water content is controlled for that comparison, unlike field mortar adjusted for laying conditions and unit absorption. A report must identify laboratory preparation and conditioning before its strength is compared with the specified property requirement. The test specimen’s preparation is part of what the number means.

Water retention is a separate qualification property

CMHA TEK 18-05B identifies 75% as the minimum water retention for the C270 property specification, measured under ASTM C1506. It calculates retention from flow after suction divided by initial flow. This measures the mortar’s ability to retain mixing water under suction from the units. Strength evidence alone does not establish that water-retention requirement or the applicable air-content limit.

How it is used in the field

A laboratory reports initial flow of 110% and flow after suction of 88%. Water retention is 88 / 110 × 100 = 80%, above the cited 75% threshold. With the same initial flow and a post-suction value of 77%, retention is 70%, below it. These are water-retention comparisons; neither calculation establishes mortar compressive strength or the strength of the wall.

For a cement-lime Type N proportion batch, 1 volume of cement, 1 of hydrated lime and 6 of damp, loose sand fits the CMHA TEK 09-01A proportion limits. The sand is 3 times the combined binder volume: 6 / (1 + 1). Reuse the same gauge measure for each constituent and keep the approved binder combination on the batch sheet. This recipe applies to that cement-lime option, not to every bag labeled Type N.

A Type S laboratory qualification reports 28-day cube strengths of 1,750, 1,850 and 1,900 psi. Their average is 1,833 psi, above the CMHA-listed 1,800 psi minimum. One cube below that average-strength criterion does not alone fail this comparison. The laboratory still checks water retention and the applicable air limit. Put these results on the property-route submittal; a proportion-route inspection instead follows the approved constituent volumes.

ASTM C270-26 expressly excludes field-sampled mortar properties as acceptance or rejection criteria for the specification. Field evaluation belongs to the defined construction-testing program, commonly C780, with comparison to an appropriate baseline. Label a field report’s purpose before circulating it. Otherwise, a number intended to monitor production consistency is easily misread as a failed laboratory qualification.

Keep restoration compatibility as a separate design decision. The repointing guide explains matching the existing wall. A compliance route verifies the selected mortar; it does not establish that a stronger substitution suits historic masonry, or that a mortar result represents masonry assembly strength.

Frequently asked questions

Can a field mortar cylinder reject a C270 mix?

C270 does not authorize that comparison with its laboratory property criteria. Retain the construction test and review it under its assigned evaluation purpose, alongside the approved materials and batch records.

Does the laboratory mortar strength equal wall strength?

No. Mortar material qualification and masonry assembly strength verification are different submissions. Identify the assembly verification required by the masonry specification instead of assigning the mortar test result to the whole wall.