ASTM International
ASTM C476: specifying and verifying masonry grout
Masonry grout ordered to ASTM C476 needs a complete designation: fine or coarse, conventional or self-consolidating, and the permitted basis for qualification. ASTM International’s C476-23 allows conventional grout to be specified by proportions or strength, while self-consolidating grout uses strength requirements. That distinction determines what belongs in the submittal and which fresh-property and strength records the inspector expects.
Applies to
Masonry designers choose the specified grout; suppliers document its constituents and qualification; masons and testing agencies carry that designation through delivery and sampling. C476 is the material specification within the wall package. Placement heights, reinforcement clearances and construction inspection belong to the masonry construction requirements identified by the project.
Key topics
Proportion compliance and strength compliance need different evidence
A proportion-based submittal identifies the constituent materials and their controlled batching proportions. A strength-based submittal identifies the specified compressive strength and supporting tests. ASTM C476-23 permits both routes for conventional grout but only the strength route for self-consolidating grout. Write the selected route into the order so a supplier’s proportion sheet is not mistaken for strength qualification. Fine and coarse describe aggregate selection; they do not select the acceptance route. The CMU execution guide applies the approved material at the pre-grout hold point.
Self-consolidating grout needs spread and stability results
CMHA TEK 09-02B describes a self-consolidating grout slump-flow range of 24 to 30 in and a Visual Stability Index no greater than 1 under ASTM C1611. Record both observations. A wide spread alone can conceal an unstable mixture with aggregate separation or a surrounding mortar halo. CMHA’s guidance also calls for the specified compressive strength or 2,000 psi, whichever is greater, at 28 days using C1019 specimens. These are SCG qualification measures, separate from the conventional-grout slump discussion in the masonry guide.
Which molds produce a usable masonry-grout strength result?
ASTM C1019-26 specifies masonry-unit molds with absorption and moisture characteristics matching the construction, so the specimen loses excess water in a way closer to grout in the wall. CMHA TEK 18-08B explains why ordinary nonabsorptive cubes or concrete-cylinder molds distort that comparison. Its mold for a wall containing both concrete and clay units uses both materials. Identify the mold units and their condition on the laboratory request; recording only specimen dimensions misses the water-removal mechanism that makes this a masonry-grout test.
How it is used in the field
Resolve a submittal marked only “coarse grout, 3,000 psi” by identifying its conventional or self-consolidating classification, strength age, test method and approved constituent package. For SCG, the receiving record also needs slump flow and stability. A 27 in spread falls within CMHA’s stated range, but a VSI of 2 exceeds its stability criterion even when the strength requirement is 3,000 psi. Passing one property does not replace the missing or failed property.
For conventional grout, CMHA TEK 18-08B calls for a bulk sample of at least 0.5 ft³, with the first and last portions collected no more than 15 minutes apart. Its sequence starts slump testing within 5 minutes of the final portion and specimen preparation within 15 minutes. At a final collection time of 10:00, those starts are due by 10:05 and 10:15. Arrange the sampling station and matching masonry molds before discharge so those separate clocks can be met.
Close the grout package with the approved classification, qualification evidence, fresh tests and specimen history. Link each strength result to its placement and preserve any nonconformance disposition. The masonry construction guide places those material records alongside reinforcement and assembly-strength verification.
Frequently asked questions
Can grout cut from a wall be compared directly with molded specimens?
ASTM C1019-26 says results from grout specimens taken from a wall should not be compared with results obtained by its molding method. Extraction and specimen geometry create a different test basis. Label wall samples separately from C1019 quality-control specimens instead of putting both into one strength trend.
Can a conventional grout mix become SCG by adding a water reducer?
A changed mixture needs SCG qualification and acceptance records. A product added at the mixer does not establish the required flow, stability or compressive performance.