ASTM C94: ready-mix purchase requirements, yield and delivery records
Ready-mix acceptance under ASTM C94 starts with what the purchaser ordered and what the producer delivered. ASTM International’s C94/C94M-26d covers freshly mixed concrete, including material, production and delivery requirements. It expressly leaves placement, consolidation, curing and protection after delivery outside its scope. Use the order and delivery evidence to settle supply questions, then use the construction specification for the work after discharge.
Applies to
Purchasers, concrete producers, inspectors and testing agencies use C94 when ordering and documenting ready-mixed concrete. ASTM states that the purchaser’s requirements govern when the order differs from the specification. Put acceptance properties, sampling responsibilities and delivery conditions in that order so the producer and inspector work from the same requirements.
Key topics
A short pour is not a measured delivery shortage
NRMCA CIP 8 determines batch yield from total batch mass divided by the average fresh density measured on representative samples from three different delivery vehicles under ASTM C138. Preserve the three density results and their average on the worksheet. Empty forms measure remaining placement demand; they do not measure fresh volume delivered. This separates a supply discrepancy from extra thickness, displaced forms or material used elsewhere, while the ordering guide handles takeoff and truck scheduling.
Check a yield worksheet before blaming the last truck
NRMCA CIP 8 publishes a batch totaling 32,220 lb with measured density of 151.0 lb/ft³: 32,220 divided by 151.0 and then by 27 gives about 7.90 yd³. Keep the mass, density and calculated volume visible rather than replacing the worksheet with the ordered nominal volume. In a project yield investigation, use the required representative density determinations. A comparison also needs records of returns, washout and concrete placed outside the original takeoff, because those quantities can explain why the formed area is still short.
Separate discharge limits from the finishing schedule
NRMCA’s March 2026 specification guide recommends an agreed setting-time window when uniform finishing is the objective, distinguishing that window from a delivery cutoff. It explains that C94’s former 90-minute default has been removed and that purchaser and producer set time or truck-revolution discharge limits. Put the agreed delivery limit on the receiving record and retain the trial’s setting-time evidence separately. A load can meet a delivery cutoff while its finishing behavior still differs from the preceding load.
How it is used in the field
NRMCA’s 2026 specification guide identifies truck discharge as the acceptance-sampling location for verifying the supplied concrete under C94. When the construction specification calls for point-of-placement properties, establish the delivery requirements and record both sampling locations explicitly. Pumping can change air content and slump. A result labeled only “site sample” cannot establish whether the reported property describes the supplied load or the concrete after conveyance. Agree on this distinction at the pre-placement meeting.
A quantity review should show the arithmetic in the same units throughout. For the CIP 8 batch above, dividing pounds by pounds per cubic foot gives cubic feet; the final division by 27 converts to cubic yards. Omitting that step produces a quantity 27 times too large. Preserve the original tickets and density sheets so another reviewer can reproduce the calculation.
Do not turn a successful fresh-property check into acceptance of the finished structure. C94’s delivery scope ends before several construction operations that control the final result. Link the received load to the placement record and the strength-cylinder record, then record curing and protection through the applicable construction workflow.
Edition history
ASTM lists C94/C94M-26d as active, updated October 22, 2026. Keep the complete suffix on the order and compliance documentation; “C94-26” does not identify this later 2026 revision.
Contractors following public apron and loading-area replacements use PorchRocket Bid Control to track agency bids and the capital plans that precede them.
Frequently asked questions
Does C94 cover a volumetric concrete mixer?
ASTM’s public C94 scope directs volumetric batching and continuous mixing to C685/C685M. Identify the production system in the supply specification instead of applying a truck-batch assumption to every mixer.
Can a stricter project requirement override C94?
Yes. C94 expressly gives the purchaser’s differing order requirements precedence. State the requirement in the purchase documents so its acceptance consequence is established before delivery.