ASTM C1064: fresh concrete temperature and thermometer records

ASTM C1064/C1064M-23 provides the fresh-concrete temperature measurement used on a delivery or placement record. MoDOT's field checklist calls for at least 3 inches of sensor immersion and a reading with the thermometer in the concrete after 2 to 5 minutes. Record that result against the specified limit at the same sampling location. C1064 supplies neither a hot-weather rejection temperature nor the embedded temperature history used to estimate strength.

Current edition: ASTM C1064/C1064M-23 (2023)
Updated

Official publisher page

Applies to

Concrete technicians use C1064 during delivery testing; inspectors and contractors use the resulting record to establish what was measured before placement. The receiving log needs both the measured temperature and the specified limit, with their units. A producer's batch temperature and a field discharge temperature describe different observations even when they belong to the same truck.

MoDOT's 2025 Concrete Field Proficiency Pack includes a C1064 performance checklist. That is a public example of an agency incorporating the method into technician qualification, rather than treating a thermometer reading as an informal observation. Its checklist revision is January 6, 2020; the current ASTM publication is the 2023 edition.

Key topics

What makes a thermometer reading auditable?

MoDOT's C1064 checklist requires thermometer verification annually. The verification date, instrument identifier and test result should form one traceable equipment record. Two probes that both display 89.0°F have matching resolution, but the displays alone establish neither calibration status nor agreement with a reference. When an instrument is replaced during a pour, start a new instrument identifier on subsequent results instead of assigning the old identifier to the replacement.

Probe contact and the measurement clock

MoDOT's published C1064 checklist calls for at least 3 inches of sensor immersion, gently closed concrete around the probe and a dwell of 2 to 5 minutes. FDOT's January 2014 C1064 checklist expressly requires reading the thermometer before removing it from the concrete. An operator who withdraws the probe to see the display has changed its surroundings before obtaining the result. Arrange the display and sample container so the reading is visible while the sensing portion remains immersed.

Why large aggregate changes temperature response

ASTM C1064/C1064M-23 identifies a heat-transfer delay of up to 20 minutes for concrete containing nominal maximum aggregate larger than 75 mm [3 inches]. The issue is heat exchange between aggregate and mortar, not permission to extend every routine field test. Identify this mixture characteristic in the testing plan before applying the ordinary timing checklist. A stable-looking mortar reading immediately after mixing can conceal a different aggregate temperature.

How it is used in the field

A load with a contract ceiling of 90°F is sampled at 08:12; the probe enters at 08:13 and reads 89°F at 08:16. Its 3-minute dwell meets the cited agency checklist, and its reading is below that contract ceiling. FDOT's checklist reports to the nearest 1°F or 0.5°C; retain the working unit system rather than treating a Fahrenheit report as a more precise converted Celsius result. Keep the sampling point, truck and instrument identifiers with those observations.

When a second reading is needed after transport through a pump or a delay, make another time-stamped observation. Do not average readings from different stages into a single acceptance temperature. ASTM's public significance statement expressly ties the result to the time of testing. A later measurement answers the later condition, while the first record remains evidence of the earlier one.

The hot-weather guide addresses cooling before delivery, while the cold-weather guide addresses protection after placement. For a pump-discharge retest, add another location and timestamp to the temperature record rather than replacing the chute result. Use the separate ambient-temperature input in the evaporation-rate calculation; the weather reading and the immersed concrete reading are different measured quantities.

Frequently asked questions

Can an infrared thermometer supply the C1064 reading?

An infrared spot reading describes the viewed surface. The agency C1064 checklist uses an immersed sensor with surrounding concrete and a timed dwell. Record a surface scan as a different observation; it does not supply that immersed measurement.

Where does the rejection temperature belong?

Put the specified minimum or maximum beside the result, with the document reference and sampling location. C1064 establishes the measurement method. The construction specification establishes the temperature criterion used to accept the delivery or authorize placement.