American Concrete Institute
ACI 305: hot-weather specifications, discharge temperature, and planning
ACI PRC-305-20 explains hot-weather concreting practices; ACI SPEC-305.1-14, reapproved 2020, provides contract requirements. The specification uses 95°F at discharge as the default maximum concrete temperature, with higher temperatures supported by field experience or preconstruction testing and accepted for the work. It also requires a preplacement conference at least 15 days before concrete construction. Separate that temperature acceptance decision from the surface-evaporation controls needed during placement.
Applies to
Producers, placement contractors, testing agencies, and specifiers use the two documents at different decision points. The hot-weather protection guide covers site controls. This reference identifies the submitted evidence, conference dates, measurement locations, and contract hierarchy needed to authorize those controls before loads arrive.
Include decorative work in that coordination when the finish changes the placement pace. The stamped concrete guide explains the finishing window, which the producer and placing crew need to understand when evaluating the proposed mixture.
Key topics
The conference has a 15-day lead time
ACI SPEC-305.1-14(20) calls for the hot-weather preplacement conference at least 15 days before concrete construction begins. Its submittal provisions call for the planned production, placement, finishing, curing, and protection procedures before that conference. Use the meeting to resolve decisions that affect orders and staffing. A morning-of-pour discussion cannot recover lead time for a missing cooling system or an unreviewed mixture.
Wind belongs at the surface being evaluated
ACI PRC-305-20 defines the wind input to its evaporation calculation as average wind speed measured 20 inches above the concrete surface. An airport observation or a rooftop sensor can describe a different exposure. Record the measuring location and height with the result, and reposition the instrument when the active placement moves behind a windbreak or into an exposed area.
A higher discharge temperature needs mixture evidence
ACI SPEC-305.1-14(20) uses a 95°F discharge-temperature ceiling unless a higher maximum is accepted with supporting field experience or preconstruction testing. ACI's cooling seminar and NAHB's hot-weather bulletin both identify that limit. Submit the proposed maximum with the actual constituent materials, proportions, and test evidence. The specification also calls for the cooling methods and their activation order in the plan. A chiller reservation alone does not qualify a proposed mixture above the default limit.
How it is used in the field
A first concrete placement on November 20 puts the specification's latest conference date on November 5. Submit the proposed procedures ahead of that meeting, including delivery interval, pour size, finishing labor, and curing resources. Resolve cooling capacity and mixture qualification there so the supplier can implement the accepted plan before the first affected batch.
Give each weather observation a time and location. Tie the concrete temperature to its load or sampling point, and distinguish a forecast from a measurement taken beside fresh concrete. That separation makes a later review useful: the reviewer can determine what the crew knew when it changed a placement rate or started a protection measure.
A producer proposes a 100°F maximum discharge temperature for a summer parking-lot placement. That is 5°F above the specification's default, so the preplacement submission needs the supporting mixture evidence and acceptance of that higher maximum. Record that decision separately from the on-site weather log; the accepted discharge temperature does not establish the wind exposure of the apron being finished.
After the pour, reconcile planned controls with the measures actually used. Capture any changed batching arrangement, added labor, delayed delivery, or revised curing start. Those observations provide a more useful starting point for the next placement than copying the previous plan without its field results.
Adoption
ACI 305-20 is a guide; ACI 305.1 is the reference specification. The latter requires an express contract statement that it governs when it is used alongside specified companion ACI construction specifications, including ACI 301. Resolve that relationship in the project documents so the weather plan has a clear contractual basis.
Municipal flatwork schedules also start in board agendas and capital plans; PorchRocket Bid Control tracks those early signals alongside public construction bids.
Frequently asked questions
Is a load below 95°F proof that evaporation controls are unnecessary?
No. The discharge-temperature criterion concerns acceptance of the fresh concrete. The evaporation assessment uses concrete temperature together with local air temperature, humidity, and wind exposure. Retain both records, with the approved response triggered by the site conditions.
Can last summer's mixture approval carry this summer's placement?
Check what the supporting experience actually covers: materials, proportions, expected temperatures, haul, and finishing conditions. Submit the applicable evidence and identify changes that need review before using the previous approval as the basis for new work.
Sources checked
- ACI: PRC-305-20 hot-weather guide
- ACI 305-20 public preview: wind measurement definition
- ACI: SPEC-305.1-14, reapproved 2020
- ACI 305.1 public preview: submittals and preplacement conference
- ACI Committee 305: current publications
- ACI 2018 cooling seminar: ACI 305.1-14 maximum concrete temperature at discharge
- NAHB: Hot Weather Concrete, 95°F discharge limit and supporting test-data exception