American Concrete Institute
ACI 308: curing phases, external protection, and application records
ACI PRC-308-26 is the May 2026 curing guide; ACI SPEC-308.1-23 is the separate external-curing reference specification. Their practical division is between selecting a curing system and specifying its execution. The guide distinguishes initial, intermediate, and final protection, while the specification supplies contract requirements. A usable pour plan assigns each interval to a crew and reconciles curing materials with the actual treated area.
Applies to
Finishers, curing crews, inspectors, and specifiers use these documents to assign area-by-area protection. Pair the curing methods guide with a placement grid identifying the finishing time, protection already in place, final method, and crew accepting responsibility for each bay.
The 2026 guide expands discussion of internal curing, elevated temperatures, monitoring, and moisture-sensitive flooring, while retaining external curing as its main scope. It does not fully address internally cured concrete. A mixture containing internal water still needs an identified surface-protection method under the selected external-curing specification.
Key topics
Protect the interval after the last finishing pass
ACI PRC-308-26 describes intermediate curing as continued initial protection after finishing is complete but before the final curing method is in place. Give that interval an owner on the pour plan. A crew moving to the next bay should identify which completed area still needs protection and who has accepted responsibility for it. The evaporation guide helps evaluate the exposure during that transfer.
Internal water does not replace surface curing
ACI SPEC-308.1-23 requires external curing methods even when internal or accelerated curing is used. Its scope does not cover every aspect of those additional curing processes. A mixture submittal describing prewetted lightweight aggregate therefore does not close the surface-curing item in the inspection plan. Identify the external method, its start condition, and the person responsible for maintaining it.
Check compound consumption against treated area
W. R. Meadows lists approximately 200 square feet per gallon for its 1100 curing compound, with coverage affected by texture, concrete condition, and climate. Use the selected product's own data to calculate planned consumption. Container counts become useful evidence when they are reconciled with the treated area and application conditions; they cannot establish uniform film coverage by themselves.
How it is used in the field
Divide the placement into identifiable curing areas and record the final-finishing time, interim protection, start of final curing, and subsequent interruptions for each area. A single end-of-shift entry saying that the slab was cured obscures the sequence on a long placement. Use the placement grid or stationing already on the drawings so the record can be matched to later observations.
W. R. Meadows' approximate 200-square-foot-per-gallon rate for 1100 compound yields 30 gallons for 6000 square feet. Using 20 gallons over that area instead works out to 300 square feet per gallon, 50 percent more area per gallon than the listed rate. Reconcile the applicator's area, container quantities, and equipment settings immediately. Map any missed or disturbed areas and restore protection under the accepted product and project instructions.
Retain the product identifier, batch number, delivered and remaining quantities, treated area, and applicator record together. Record a product change at its grid location and recalculate consumption using the replacement's data. A later flooring contractor then knows exactly which curing material occupies each area and which manufacturer's compatibility instructions apply.
Assign responsibility for disturbed protection. Saw cutting, access paths, and follow-on trades can interrupt a curing system after the first inspection. Document when a cover was moved or a treated surface was damaged, the area affected, and how protection was restored.
Edition history
ACI PRC-308-26 superseded the 2016 guide in May 2026. ACI SPEC-308.1-23 superseded the 2011 curing specification. The guide and specification follow separate revision cycles; the new guide does not rename the 2023 specification.
Adoption
ACI SPEC-308.1-23 says it is not to be used alongside ACI 301 or ACI 350.5 unless the contract explicitly makes 308.1 govern the curing work within its scope. Resolve that instruction when assembling the project specification, before competing curing provisions reach the crew.
Repeat paving territories change as industrial yards are added or altered; PorchRocket Asset Search monitors those visible assets and reports dated changes with owner-of-record information.
Frequently asked questions
Is 200 square feet per gallon an ACI application rate for every compound?
No. That approximate rate is W. R. Meadows' published coverage for 1100 compound, affected by surface texture, concrete condition, and climate. Use the selected product's instructions and test-area result for consumption planning. A manufacturer-specific coverage number cannot be transferred to another curing material.
What should be retained when the curing crew changes?
Transfer an area-by-area record showing the method in place, start time, interruptions, and remaining responsibilities. The incoming crew needs to know which surfaces still require attention before accepting the handoff.