ASTM International
ASTM C172: sample size, sampling clocks and placement equipment
ASTM C172/C172M-25 governs collection of representative fresh concrete, including a minimum 1-cubic-foot sample when making strength specimens, as explained by NRMCA. It addresses mixer and delivery equipment, composite sampling and wet-sieving. Testing frequency and concrete acceptance limits come from the project testing program. A sampling plan must also distinguish the deadline to start molding from the time molding ends, and identify a collection method when the specified location is beyond a pump or conveyor.
Applies to
Testing agencies, concrete producers and inspectors use C172 when the project invokes it for acceptance sampling. NRMCA identifies ACI 318, ACI 301 and ASTM C94 as documents that call for this sampling practice. On the slump-test assignment, assign both the sampling location and a container large enough for the complete fresh-test and strength-specimen program.
Key topics
How much concrete is needed for strength specimens?
MnDOT's 2021 concrete inspector workshop identifies 1 cubic foot as the minimum C172 sample for strength testing, approximately 145 pounds of normalweight concrete. NRMCA's materials FAQ likewise specifies at least 1 cubic foot when strength specimens are made, while allowing smaller samples for slump and air tests alone. Select the collection container and handling arrangement for that complete sample rather than the volume of one cylinder mold.
Does the 15-minute limit mean finish molding?
NRMCA's materials FAQ places the strength-molding start within 15 minutes after obtaining the sample; it does not make that interval a deadline to finish every cylinder. Its fresh-test start limit is 5 minutes after the last composite portion. With the last portion collected at 8:04 a.m., start slump, temperature and air testing by 8:09 and begin specimen molding by 8:19. Record molding completion separately because C31's initial-curing transfer clock starts there.
Which loads are selected for testing?
ASTM C172/C172M-25 leaves selection of specific test batches outside its sampling procedures and recommends random sampling for overall specification compliance. A sample collected correctly from a conveniently selected truck does not establish that the required batch-selection plan was followed. Put the selection rule and responsible party in the inspection plan before dispatch begins; distinguish scheduled acceptance samples from additional diagnostic samples.
Does C172 cover the end of a concrete pump?
NRMCA's materials FAQ states that C172 does not provide sampling procedures for pumps, conveyors or crane-and-bucket placement equipment. Where a specification calls for sampling after that equipment, establish the collection procedure and location explicitly. Identify paired upstream and downstream observations as separate sampling events. Merely writing 'C172, point of placement' leaves the equipment-specific collection method unresolved.
When wet-sieving belongs in the testing plan
The publisher includes removal of oversized aggregate by wet-sieving within C172/C172M-25. The companion test method determines when that preparation is required. Provide the designated sieve and identify the fraction tested in the report. Treat wet-sieving as a planned preparation step, with enough collected material remaining for every required test and specimen, rather than discovering the equipment shortage after sampling.
How it is used in the field
Six 4 by 8 inch cylinders consume about 0.35 cubic foot of concrete: 6 × pi × 2² × 8 / 1,728. That is only the molded volume. The fresh-test apparatus and material handling need additional concrete, and collecting just enough to fill those molds would still fall below the cited 1-cubic-foot strength-sampling minimum. Plan the sample around the full test assignment.
For a delivery feeding both a pump and a direct chute placement, mark each sampling point on the pour plan. Associate the downstream sample with its equipment path and the concrete location it represents. This prevents a later strength report from appearing to cover a placement route that was never sampled. A change in delivery arrangement during the pour also calls for a change in the sampling record.
Edition history
ASTM lists the 2025 practice as active, following the 2017 edition. Keep the sampling practice identified separately from the editions of the individual test methods in the laboratory method register.
Frequently asked questions
Does C172 prescribe a test for every truck?
No. The practice describes sampling, while the project testing program determines frequency and batch selection. Retain the selection rule with the sample register so the number of reports can be reconciled with the required coverage.
Is a mixer-uniformity sample the same as an acceptance composite?
Not necessarily. ASTM identifies mixer-efficiency and consistency-uniformity testing as cases with specific sampling exceptions. Record the purpose before applying a collection arrangement intended for one of those investigations to routine acceptance work.