ASTM C31: cylinder curing temperatures, transfer and transport
ASTM C31/C31M-26b governs field-made concrete cylinders and beams through molding, initial curing, transport and laboratory curing. Acceptance specimens need controlled temperature and moisture, with a tighter initial temperature range for specified strengths of 6,000 psi or more. Field-cured specimens serve a different assignment tied to the structure. Label the curing purpose before molding, prepare the storage enclosure, and schedule laboratory delivery against both the final-set transport restriction and the limit measured from casting.
Applies to
Field technicians, contractors and receiving laboratories each control part of the specimen's history. Give the fresh-test record and the cylinder set the same sample identifier, then assign responsibility for the enclosure, temperature log and collection. ASTM's published C31 scope identifies standard curing for acceptance, mixture verification and quality control, and field curing for decisions about the structure.
Key topics
Which mixtures need a different specimen practice?
ASTM C31/C31M-26b excludes lightweight insulating concrete and controlled low-strength material, directing those applications to C495/C495M and D4832/D4832M respectively. It also identifies C1856/C1856M for making and curing ultra-high-performance concrete specimens. Classify the material before assigning the routine cylinder procedure. Structural lightweight concrete and lightweight insulating concrete are different testing assignments despite sharing the word lightweight.
Which initial-curing temperature applies at 6,000 psi?
NRMCA's materials FAQ states 60°F to 80°F for ordinary initial curing and 68°F to 78°F when specified compressive strength is at least 6,000 psi. Use specified strength, not the producer's higher mixture target, to select the band. NRMCA also requires moisture protection and records of the enclosure's minimum and maximum temperatures. A 6,000 psi set stored at 79°F exceeds its band even though that temperature would fit the ordinary range.
The curing environment must be ready when molding ends
NRMCA’s materials FAQ calls for specimens to enter the initial curing environment within 15 minutes after molding. That clock starts when molding ends, not at the truck’s batch time or the beginning of sample collection. An insulated box ordered after the cylinders are cast is already a failed handoff plan. Assign the storage location and verify its operation before testing begins.
Eight hours, four hours and 48 hours measure different events
NRMCA CIP 34 delays cylinder transport until at least 8 hours after final set, limits the site-to-laboratory trip to 4 hours, and requires delivery within 48 hours of casting. The current materials FAQ also states the 48-hour delivery and 4-hour travel limits. Plan collection backward from laboratory receiving, including intermediate stops. Satisfying the minimum age for movement does not extend the deadline for leaving initial field storage.
What happens when the laboratory receives the set?
NRMCA's materials FAQ specifies a laboratory curing environment of 73.5°F ± 3.5°F with water continuously present on specimen surfaces. It allows a moist room or lime-saturated water for cylinders and requires water immersion for beams. The receiving assignment must identify the specimen shape and curing purpose before storage changes. A shared courier trip does not make field-cured, standard-cured and beam specimens interchangeable.
How it is used in the field
Molding of a cylinder set finishes at 6 a.m. Its initial-curing placement deadline under the cited NRMCA guidance is 6:15 a.m. If final set is established at 11 a.m., the cited earliest transport time is 7 p.m. A noon collection would be only 1 hour after final set. Record the applicable times rather than treating “the same day” as a transport authorization.
A set molded Friday at 6 a.m. reaches 48 hours on Sunday at 6 a.m. A Monday pickup cannot meet the cited standard-curing schedule, even with a short drive. Book weekend receiving or an earlier collection while preserving the final-set restriction. Include arrival time on the custody record so the laboratory can distinguish excessive time in initial storage from excessive time in transit.
At receiving, reconcile specimen identifiers and counts before separating the sets. Attach the enclosure's temperature extrema and moisture-protection record to the accession. A 70°F reading at pickup cannot establish that the enclosure stayed within limits overnight. Carry damage, missing observations and temperature excursions into the strength report so a later low result can be investigated against the actual curing history.
Use separate dispatch groups for standard-cured and field-cured assignments. The cold-weather guide explains their different decisions. The receiving laboratory needs the assigned purpose before it changes storage conditions; a courier’s common collection route does not turn both groups into the same curing assignment.
Edition history
ASTM identifies C31/C31M-26b, updated August 27, 2026, as active and lists 26a and 26 separately. The revision suffix belongs on the laboratory method register and the specimen assignment.
Frequently asked questions
Is eight hours counted from casting the cylinders?
The cited CIP 34 transport instruction counts from final set. Preserve the basis used to establish that time. Casting time and final set are different events, especially for retarded or cold mixtures.
Does C31-26b cover beam specimens too?
Yes. The practice includes field-made beam specimens as well as cylinders. Assign their curing and handling requirements explicitly instead of assuming that a cylinder pickup instruction completely defines the beam assignment.