ASTM C143: valid slump results, sample purpose and acceptance
A C143 slump result can be measured correctly and still be unsuitable for acceptance because the sample was collected for another purpose. ASTM C143/C143M-26b supplies the measurement method, while sampling and purchase requirements establish the decision it supports. FDOT's FM 5-501 early sample, for example, is 0.5 cubic foot and is restricted to quality control. Identify that purpose, any aggregate removal and the specified acceptance criterion before using the reported inches to accept a load.
Applies to
Field testers perform the measurement, ready-mix producers use it for consistency control, and inspectors compare acceptance results with the specified requirement. The slump-test field guide explains filling, rodding and lifting. The standard reference adds the sample classification and material-scope checks that determine how the result can be used.
Key topics
When aggregate must be removed before the test
ASTM C143/C143M-26b applies directly to concrete with coarse aggregate up to 1.5 inches [37.5 mm]; larger aggregate requires testing the fraction passing that sieve after preparation under C172/C172M. Record that preparation in the result. The tested fraction is different from the complete mixture, so a report that omits wet-sieving has hidden a material detail needed when comparing field and laboratory observations.
An early quality-control sample has a different job
FDOT's August 2017 FM 5-501 specifies a 0.5-cubic-foot early sample taken after 2 to 6 cubic feet have discharged from the batch. That procedure references C143 for measuring slump, but explicitly limits the sample to quality control rather than acceptance for pay. The measurement method and the authority of the sample are separate decisions. Label an early result before it enters the same database as the acceptance results.
Are the half-inch and nine-inch limits rejection limits?
ASTM C143/C143M-26b flags slumps below 0.5 inch or above about 9 inches as possible plasticity or cohesion problems affecting the test's significance. Those observations belong to method applicability, rather than the purchaser's allowable slump interval. A 9.25-inch observation should retain its measured value and description of the concrete's behavior; clipping it to 9 inches in software hides the very condition the method asks the reviewer to interpret.
How it is used in the field
A delivery record contains an early FM 5-501 sample collected after 4 cubic feet discharged, followed by a later composite acceptance sample. Preserve both results with their purpose, collection time and any intervening adjustment. If the early result is 7.25 inches and the later result is 6.75 inches, averaging them to 7 inches would invent a result that represents neither sampling event. Compare each observation only with the decision it was collected to support.
For a mixture containing 2-inch aggregate, arrange the 1.5-inch wet-sieving step referenced by C143 before delivery, then identify the original aggregate size and the fraction tested on the report. Do not compare that result with an unsieved trial observation as though the specimens were identical. The mixture guide supplies the original aggregate selection; this testing preparation does not change that approved mixture.
NRMCA CIP 41 treats a C94 preliminary sample and the C172 composite acceptance sample as separate sampling events. FM 5-501 also has its own early-sample discharge window and quality-control purpose. Keep the named sampling procedure beside the result instead of transferring one procedure's early-sample volume or discharge point into another. The ready-mix receiving guide covers the delivery handoff, including adjustments between those events.
An acceptance record should carry the actual slump requirement, including whether it is nominal or maximum, separately from the method designation. A failed acceptance test also needs its check-test result and the reason for the disposition, rather than an overwritten first reading. NRMCA CIP 41 describes check testing on a separate sample before rejection after a nonconforming acceptance result. Keep the original and check result linked so an early quality-control adjustment is not mistaken for that rejection check.
Edition history
ASTM identifies C143/C143M-26b as active, updated August 6, 2026, and lists the earlier 2026, 2026a and 2020 versions separately. The suffix belongs in the laboratory's controlled method list. Updating that list also calls for reviewing worksheets and training references that still identify an older edition.
Frequently asked questions
Can a quality-control slump be reported as an acceptance slump?
Only the specified acceptance sampling and testing program establishes an acceptance result. FDOT FM 5-501 expressly classifies its early sample as quality control, despite using C143 for the measurement itself.
Are metric and inch-pound procedure values interchangeable?
ASTM C143/C143M-26b requires each unit system to be used independently because their stated values are not necessarily exact equivalents. Identify the working system before preparing the report or checking a tolerance.
Does a collapsed conventional mix become SCC?
The mixture designation and approved test plan establish whether SCC testing applies. A collapsed specimen from a conventional load requires investigation of that load and its C143 test behavior. It does not acquire an approved SCC mixture qualification merely because it spreads on the plate.