ANVILFIELD Try FieldOS

ASTM International

ASTM C1611: slump-flow evidence for SCC mix qualification

ASTM C1611/C1611M-21 provides the unconfined slump-flow measurement used in SCC qualification and production. Acceptance still needs the purchaser's limits: Caltrans' 2025 specification requires at least 20 inches of production slump flow, within 3 inches of the approved target, and VSI no greater than 1. Its trial batch also needs T50 of 2 to 7 seconds. Keep trial and production criteria in separate fields so an optional ASTM observation is applied where the contract actually requires it.

Current edition: ASTM C1611/C1611M-21 (2021)
Updated

Official publisher page

Applies to

SCC producers, precasters, field technicians and specifying engineers use C1611 during mixture trials and production. ASTM limits the method's stated aggregate applicability to coarse aggregate up to 25 mm [1 inch]. The self-consolidating concrete guide explains the spread, T50 and VSI observations; this page follows those observations into qualification documents and agency acceptance decisions.

Key topics

Optional ASTM observations can become contract requirements

ASTM C1611/C1611M-21 places its relative-viscosity and visual-stability procedures in nonmandatory Appendix X1. A purchaser can nevertheless require those observations and specify their limits. The report should identify both authorities: C1611 for the measurement method and the agency or project specification for the acceptance criterion. Otherwise 'ASTM compliant' leaves the reviewer unable to tell whether the supplier performed only a spread measurement or the full requested test set.

Caltrans trial batches need more than a large spread

Caltrans' 2025 Standard Specifications, section 90-5.01D(2)(c), require an SCC trial-batch slump flow of at least 20 inches, T50 of 2 to 7 seconds and VSI no greater than 1. These are three of its qualification criteria, alongside separate passing-ability, segregation, bleeding and strength checks. The agency also requires the trial to use the production materials, proportions, equipment, procedures and batch size. A small laboratory batch alone does not satisfy that production-equivalence requirement.

Apply the minimum flow and the approved target together

Caltrans' 2025 section 90-5.02 requires at least 20 inches of slump flow, no more than 3 inches of deviation from the approved mix-design flow, and VSI no greater than 1. A 26-inch target therefore yields a flow interval of 23 to 29 inches; a 22-inch target yields 20 to 25 inches. A 24-inch spread with VSI 2 falls inside either flow interval but fails the agency's independent stability criterion. Keep all three production checks on the acceptance sheet.

How it is used in the field

A trial batch with a 22-inch spread, T50 of 1.6 seconds and VSI 1 passes the cited Caltrans spread and visual-stability criteria but misses the trial's minimum flow time. Mark each observation separately on the qualification sheet. Calling the overall result a 'passing slump flow' would conceal the failed criterion and invite production with an unqualified mixture.

At the handoff from trial approval to production, transfer the approved mixture revision and target flow to the field sheet. Keep the trial's timed-flow qualification in the mix file and record the production observations required for that placement. A later mixture revision needs its own approval link; copying a previous sheet's 'qualified' status does not establish that the delivered proportions, materials or batch size match the approved trial.

Caltrans' 2025 field quality-control provisions require slump flow and VSI at the start of SCC placement and whenever a cylinder set is prepared. Associate each result with the placement and sample identifiers. When several trucks feed one element, a test result without that association cannot establish which material reached a particular part of the form.

For congestion, keep the separate passing-ability result beside the unconfined spread. Caltrans' 2025 trial table limits the difference between J-ring flow and slump flow to 2 inches under ASTM C1621. A 26-inch unconfined spread and 23-inch J-ring spread differ by 3 inches, so that trial misses the passing-ability criterion despite its generous unconfined flow. The SCC placement guide explains the obstruction mechanisms behind that difference.

Adoption

Caltrans' 2025 Standard Specifications explicitly invoke C1611 in section 90-5 for SCC trial batches and field quality control. Its submittals include the mix design, placement procedures and trial report, plus mock-up details and results when a mock-up is specified. Link those to the concrete QA record rather than accepting a spread-only laboratory sheet as the complete qualification package.

Frequently asked questions

What happens when the proposed production batch size changes?

Flag the change in the qualification record. Caltrans' cited trial-batch provision requires the production batch size, so an earlier trial with a different size does not document that required equivalence.

Is every T50 outside 2 to 7 seconds an ASTM failure?

That interval is the cited Caltrans trial-batch requirement. C1611 supplies the test framework; the governing purchaser's specification establishes the required range and when it applies.

Can the accepted mix-design spread replace the field measurement?

The target is the reference for the field comparison. Record the delivered mixture's measured spread and apply both the target tolerance and any independent minimum or maximum in the contract.

Sources checked

Field guides that apply ASTM C1611

Browse all codes and standards