ASTM C173: volumetric air readings, foam and invalid tests

ASTM C173/C173M-26 measures fresh-concrete air by releasing it through agitation in a water-filled volumetric meter. The method works with dense or porous aggregates because it excludes air inside the aggregate particles. A valid result requires a stable liquid level, controlled foam, a sealed meter and complete release of concrete from the bowl. Apply the alcohol correction and calibrated-water additions, then report at the method's quarter-percentage-point precision.

Current edition: ASTM C173/C173M-26 (2026)
Updated

Official publisher page

Applies to

Field technicians use C173 where the aggregate or testing specification calls for volumetric measurement. Producers and inspectors need the observations that establish a valid reading. Air targets in the concrete mix guide become useful acceptance criteria only after the liquid reading and its adjustments have been established.

Key topics

How much foam makes the air test invalid?

ASTM C173/C173M-26 invalidates a test when foam above the liquid exceeds the equivalent of 2 percentage points on the air scale. The same edition prohibits adding alcohol after the initial filling to the zero mark to suppress that foam. Restart with an appropriate initial alcohol quantity. A stable-looking top of foam is not the liquid meniscus and cannot rescue the original test.

A stable level needs a timed observation

Humboldt's H-2796A manual, revision 1022, allows no more than 0.25 percentage point of liquid-level movement over 2 minutes and rejects stabilization taking longer than 6 minutes. After another 1-minute rolling, compare the new reading with the first. A change above 0.25 point requires another confirmation cycle; a further change above 0.25 point invalidates the test. This sequence catches air still trapped in the concrete after an apparently settled first reading.

Alcohol correction is separate from water added to the neck

Humboldt's H-2796A manual subtracts an alcohol correction and adds the percentage represented by calibrated water cups when the air exceeds the readable scale. Its correction data are for 70% isopropyl alcohol and the specified meter geometry. Record concentration, quantity and calibrated additions. An unspecified bottle of alcohol and an unrecorded cup count leave the calculation impossible to reconstruct.

How it is used in the field

A final neck reading of 7.0%, less the H-2796A manual's 0.3-point correction for 3 pints of 70% alcohol, calculates to 6.7% before rounding. CCRL's concrete proficiency instructions require C173 air results to the nearest 0.25%, so report 6.75%. Keep 7.0, 0.3 and 6.7 on the worksheet as the reading, correction and unrounded calculation. Include any calibrated-water addition before rounding the result.

Humboldt also rejects a leaking meter and a test that leaves undisturbed, tightly packed concrete in the bowl after emptying. Record either observation as an invalid test with its reason, then retain the replacement test under its own identifier. Those failures are apparatus or sample-release problems; changing the mix's air-entraining dose does not correct them.

ASTM explains that fresh and hardened air contents can differ because of handling, consolidation and the stability of the air system. A valid volumetric number establishes total fresh air at the sampled stage. It does not supply a hardened spacing factor. The air-entrainment guide develops that durability distinction; preserve the sampling stage with the volumetric result.

Frequently asked questions

Can the foam height be subtracted from the reading?

No. Foam above the permitted amount is a restart criterion in C173/C173M-26, not a correction term. The calculation uses a valid liquid reading and the applicable alcohol and calibrated-water adjustments.

Does a low volumetric reading prove the delivered concrete is deficient?

First establish that the test remained sealed, the liquid stabilized and the concrete released completely. Compare a valid result with the specified air requirement. Preserve an invalid test as an invalid observation rather than an acceptance result.