ASTM F2200: Automated gate construction and slide-gate geometry

An automated vehicle gate needs safe physical construction as well as a suitable operator. ASTM F2200-24 addresses the gate itself: its configuration, openings, retention, and related construction hazards. Operator settings cannot repair unsafe geometry. Fabricators, installers, and owners use the specification when building or converting a gate, then coordinate it with the operator and entrapment-protection requirements of UL 325.

Current edition: ASTM F2200-24 (2024)
Updated

Official publisher page

Applies to

ASTM F2200-24 covers automated vehicular gates in Classes I through IV, including horizontal slide, horizontal swing, vertical lift, vertical pivot, overhead pivot, and horizontal bifold arrangements. Its scope expressly includes horizontal bifold gates even though older summaries omit them. ASTM also directs automated systems to comply with UL 325. ASTM current scope

Key topics

Screen the slide gate and the fence behind its runback

Nice/HySecurity's 2026 1500 LA manual specifies screening for Class I, II, and III slide gates to the lesser of the gate's top or 6 feet above grade, excluding a 2¼-inch sphere. A 4-foot gate therefore needs its full leaf height protected, without extending mesh above it. Include the fence overlapped by the open gate and the moving back frame. The manual lists Class IV separately; record the actual usage class instead of transferring a residential screening checklist to a guarded industrial installation. Nice/HySecurity gate-construction requirements, page 8

Roller guards and stops survive control failures

Nice/HySecurity's 2026 1500 LA manual requires guarding of exposed weight-bearing slide-gate rollers at 8 feet or less above grade, including the eight-foot boundary. It also requires physical stops for both travel limits and retains those safeguards for Class IV slide gates. DASMA's checklist separately identifies exposed pinch points. Keep the stops on the fabrication drawing and photograph guard coverage through the travel, since a roller hidden when closed can emerge as the leaf opens. A controller's programmed limit does not supply a mechanical stop. Nice/HySecurity hardware requirements, pages 8 and 9; DASMA pinch-point checklist

Retention and runback belong in the fabrication package

DASMA's construction checklist includes provisions to keep a gate from falling if supporting hardware fails. Specify the retaining arrangement as part of the gate assembly and coordinate it with posts, guides, hinges, and rollers. The operator connection is not a substitute for a documented retention detail. On an existing gate, identify alterations and missing fabrication information before adding powered movement; a motor installation exposes defects that were previously hidden by infrequent manual use. DASMA gate retention guidance

How it is used in the field

Dimension a retrofit survey at both end positions and through the travel between them. Mark the roadway, overlapped fence, nearby fixed objects, pedestrian route, and support hardware. Identify each dimension as a measured clearance or opening. Assign correction of the runback fence to a named scope so its screening is not omitted between the gate and fence contracts.

Split the submittal by responsibility. The fabricator documents leaf geometry, screening, guides, stops, and retention. The operator installer documents controls and protective devices. Use a shared site plan to locate interfaces, especially where the opening leaf passes beside a fence or structure supplied by another contractor.

During turnover, record the installed guards and stops with photographs taken through the gate's travel. Separately document operator and entrapment-device commissioning. Close each construction discrepancy with an as-built detail or photograph rather than treating successful push-button operation as proof that the physical gate complies.

Frequently asked questions

Does replacing an operator make an old gate compliant?

The new operator does not change the gate's openings, roller exposure, stops, or retention. Include those construction features in the replacement survey and correct them as part of the coordinated gate-system work.

Is the adjacent fence outside the gate contractor's review?

Not when the moving slide gate covers that fence area. Include it in the opening-protection review and assign any required screening work in the contract, even when a different trade originally installed the fence.

Does a short slide gate need a six-foot screen above it?

Nice/HySecurity's 2026 manual uses the lower of the gate top or six feet for its Class I, II, and III screening requirement. Screen the full applicable leaf height and the fence portion it covers; roller guarding has a separate eight-foot-inclusive height limit.