How much colocation power is usable after a failure?

Reconcile contracted rack kW with surviving electrical capacity, cooling, power caps and dated failover evidence.

Colocation powerFailover capacityBuyer diligenceGPU infrastructure

Direct answer

For two independent 208 V, 30 A single-phase rack feeds serving a fully transferable load, Anvilfield estimates a continuous electrical ceiling of 4.74 kW after either feed fails at a 0.95 power factor, using Schneider Electric's standard-rated breaker guidance, revised October 2024. The two feeds do not provide 9.48 kW of failure-protected capacity. Your usable allocation is the lowest supported contractual, surviving electrical, cooling or enforced-control limit that also meets the agreed interruption and outage-duration conditions. In the worked allocation below, cooling lowers the usable load to 4.00 kW.

On this pageHow much contracted power remains usable after a failure?Where is colocation power measured?Do A/B feeds, N+1 or a Tier label prove failover capacity?Which deratings belong in the capacity register?How do you calculate the failure-capacity worksheet?What evidence proves contracted rack failover?Does usable power also support cooling and GPU performance?How fresh must capacity and test evidence be?Claim-to-evidence matrix: what is supported?Worked example: two 30 A feeds are not 9.48 kW of protected loadHow much time and money does buyer evidence review take?Buyer evidence request checklistSources, methodology and how to cite this page
Need to run this in the field?

Open the related tool for the calculation, checklist, or packet.

How much contracted power remains usable after a failure?

Buy continuous IT kW at a named delivery point, in a named hall, under named failure conditions. Separate capacity available for sale, capacity reserved for your organization, energized capacity ready for use and future capacity awaiting construction. A delivery date belongs beside each allocation, not beside a campus-wide MW announcement.

Four quantities determine the purchase: installed equipment rating, operating electrical limit, contractual entitlement and evidence-supported allocation. A signed entitlement does not enlarge a feeder, and a successful test does not reserve capacity for a new tenant.

Read what “contracted kW” purchases. It can describe a continuous ceiling, a minimum monthly billing commitment or an average demand measure. Establish whether A/B pricing buys one protected load or two separately rated circuits, then put surviving kW, permitted density, load shedding, cooling duties and evidence delivery in the technical schedule. Commercial remedies follow the agreement's actual terms.

Which load must keep running?

Specify uninterrupted electrical service, restored service, sustained cooling and application performance separately for each load class. Identify protected racks, interruptible racks, single-cord devices, transfer switches and enforced power caps. Record allowed interruption, restoration time, outage duration and initial battery/fuel state; each condition changes what the promised kW means.

Use the colocation fit-out guide for tenant/operator responsibilities and the grid-capacity evidence checklist for future utility dependencies. Reclaiming headroom belongs to stranded capacity and power utilization; this register establishes which buyer can use that headroom after the specified failure.

Where is colocation power measured?

Measure at the contractual delivery point and trace every upstream constraint to that boundary. A utility meter includes facility services; rack inlets measure the tenant load. Record both boundaries when billing and delivery differ, using the power distribution chain and rack PDU distribution guide to identify the intervening equipment.

Real power in kW describes consumption; apparent power in kVA and conductor current constrain equipment; kWh records accumulated energy. Capture voltage, power factor, phase configuration and each conductor's current. Sum synchronized A/B readings for rack consumption, then calculate the surviving capacity of each feed separately.

The Green Grid's undated PUE glossary defines PUE as total data center energy divided by ICT equipment energy. Annual PUE cannot establish instantaneous rack failure capacity: downstream measurements and scenario-specific auxiliaries and losses determine that allowance. See PUE and energy efficiency for the energy boundary. [S7]

Table 1. Meter demarcation register
PointQuantityBoundaryEvidence to requestDecision
Utility revenue meterSite kW and kWhIT plus facility servicesMeter ID, utility service record, interval exportEstablish site supply, then trace the tenant path
Generator output buskW, kVA, current, frequencyLoads carried during outageDuty rating, site derates, auxiliaries and outage traceAllocate IT only after non-IT load and losses
UPS outputkW, kVA, per-phase currentCritical bus; verify any non-IT loadsOne-line, module state, bypass state, battery recordApply surviving configuration and downstream limits
Floor PDU or buswaykW and current by phaseMultiple customers or rowsTap map, breaker settings, reservation ledgerDeduct other allocations once at this shared boundary
Rack A and B inletskW, voltage, current, PF per feedTenant delivery point in this worksheetSynchronized A/B export and upstream circuit IDsMeasure consumption across both; calculate either-feed loss separately
Server telemetryDevice input or component estimateConfirm whether PSU input or GPU-onlyMetric definition and time-aligned workload logCorroborate workload; do not substitute GPU-only watts for rack metering

Request instrument ID, CT/PT ratios, accuracy specification, calibration or verification record, time zone and aggregation period. Keep interval averages, captured maxima and event waveforms distinct: an average can conceal an overload or interruption.

Resolve conflicting meter readings by aligning boundaries, clocks, transformer ratios and averaging windows before attributing the difference to losses. Carry stated uncertainty and an agreed acceptance rule into a close pass/fail decision. The CDU capacity uncertainty worksheet applies that discipline to thermal measurements; this buyer register sets no universal meter accuracy class.

Do A/B feeds, N+1 or a Tier label prove failover capacity?

A/B labels identify feeds; the one-line establishes their dependencies. Trace common switchgear, UPS bypass, control power, cooling, fuel and distribution. Test A unavailable and B unavailable independently, then identify shared-component failures that neither directional feed test covers.

N is the capacity needed for the design load; N+1 adds one capacity component, while 2N provides two complete capacity systems. Neither label reserves tenant kW or proves that distribution, cooling and controls are independent. For interchangeable modules sharing a common load, sum the surviving derated ratings, then check their distribution limits.

Uptime Institute's April 2021 explanation defines Tier III by concurrent maintainability and Tier IV by fault tolerance. Obtain the exact award type and facility phase: design certification, constructed-facility verification and operational certification answer different questions. [S15]

Uptime's July 20, 2017 certification guidance explains why topology changes can affect previously certified outcomes. Match the award to the current built configuration and review subsequent changes, using Uptime Tier classification for the wider certification context. [S5]

How much normal loading leaves room for either feed to fail?

Under equal sharing, a fully transferable load at a 24 A surviving-feed ceiling draws 12 A per feed before failure. For two conventional 30 A circuits, Anvilfield estimates that as 40% of each breaker rating using Schneider's October 2024 continuous-application guidance. [S1]

Active/standby supplies, unequal sharing, changed PSU efficiency, inrush and phase imbalance alter the post-failure result. Obtain the actual transfer trace; a normal average cannot establish transient performance.

Which deratings belong in the capacity register?

Record each limiting asset's ID, rated value, operating condition, document revision, permissible value and verification date. Keep equipment derating, redundancy reservation and buyer growth allowance separate.

Schneider Electric FAQ FA104355, revised October 14, 2024, applies an 80% current ceiling to standard-rated continuous applications of three hours or more and allows up to 100% for qualifying 100% rated applications. Confirm the breaker, conductors, terminations and assembly installation conditions together. Apply the locally adopted code and equipment listing; the US manufacturer example does not establish a universal IEC circuit rule. [S1]

Schneider FAQ FA408273, modified January 5, 2026, gives a 320 A continuous limit for a standard-rated 600 A breaker set to 400 A. The as-left setting, rather than frame size, determines that calculation. [S2]

Table 2. Derating and scope comparison
Equipment/source editionConditionFilled valueBuyer action
Schneider standard-rated breaker, FA104355, 2024-10-14Continuous application, 3 hours or more30 A input × 0.80 = 24 AConfirm actual breaker, conductors and installed assembly
Schneider 100% rated application, same sourceListed equipment installed for that applicationUp to 100% of rating continuouslyObtain listing and installation evidence; do not apply another automatic 0.80 factor
Schneider FA408273, 2026-01-05600 A frame, 400 A setting, standard-rated320 A continuousObtain as-left settings, not just faceplate photo
Galaxy VS external-battery IEC UPS, 990-91141L-00145°C at UPS intake, otherwise rated conditions2.5% reduction per °C above 40°C; 87.5% at 45°CAnvilfield estimates 87.5 kW for a 100 kW selection [S13]
Galaxy VXL IEC UPS, 990-55333E-00145°C at UPS intake, otherwise rated conditionsPublished 40°C to 50°C operating band at 75% powerAnvilfield estimates 375 kW for a 500 kW selection [S14]
Galaxy VS, 990-91141L-0012,000 m elevation, temperature within non-derated bandAltitude factor 0.95Anvilfield estimates 95 kW for a 100 kW selection [S13]
Generator duty comparison, Cummins PowerHour, ISO 8528-1:2018 explanationEmergency standby versus data-centre ratingESP: up to 200 h/year; average over 24 h limited to 70% of ESP unless engine manufacturer agrees otherwise; DCP: unlimited hours under its defined serviceConfirm duty, load profile, fuel and operating permission; DCP and Cummins DCC are different ratings [S9]
Cummins DQLE / QSK78-G12, published PowerHour case studySame published generator model under different ratings2,500 kW ESP; 2,275 kW Cummins DCC; 2,000 kW ISO COPSelect the purchased duty sheet; this dated case demonstrates rating differences [S9, slides 49 to 50]

Apply the installed model's derating rule: extending the Galaxy VS temperature slope to VXL gives the wrong result. UPS intake and server inlet are separate thermal boundaries. Obtain OEM treatment of simultaneous temperature and altitude derates.

Cummins' PowerHour explanation of ISO 8528-1:2018 separates duty, annual operating hours and average-load restrictions. An average-load restriction is distinct from an instantaneous ceiling, and ISO DCP is distinct from Cummins DCC. Match the purchased duty sheet, site derates, fuel plan and operating permission to the promised outage duration.

How do you calculate the failure-capacity worksheet?

Anvilfield's buyer worksheet defines usable colocation capacity as the lowest supported contractual, surviving electrical, cooling or enforced-control allowance across normal operation and the required failure scenarios at one tenant boundary, with the agreed interruption and duration conditions met.

At each bottleneck, reconcile surviving capacity, other customers' commitments, non-IT loads, downstream losses and separately held reserves. Convert the remaining allowance to tenant IT kW before comparing it with another boundary. Keep demand and capacity on the same side of every loss conversion.

Anvilfield allocation method, 2026: U_s = max(0, min(C_s, E_s, H_s, P_s)); U = min_s(U_s), including normal operation. C_s is the scenario's contractual allowance; E_s is the tightest surviving electrical allowance; H_s is cooling-supported IT load; P_s is the enforced cap. All values are tenant kW after commitment and reserve reconciliation. Mark a confirmed absent cap “not limiting.” An unknown essential limit or failed transition leaves the allocation unsupported, even if the other entries are numeric. The zero floor indicates no spare allowance and triggers correction when commitments exceed capacity.

Table 3. Required scenario worksheet
ScenarioSurviving pathQuantities requiredEvidenceAllocation decision
Normal operationA and B with current topologyContract cap, per-phase loading, cooling allowanceCurrent one-line, exports, reservation ledgerEstablish reference load and shared bottlenecks
A unavailableB through its complete upstream chainB continuous and transient limits; total transferred loadA-loss record at tenant-equivalent loadLimit allocation to B's supported allowance
B unavailableA through its complete upstream chainA continuous and transient limits; total transferred loadB-loss record at tenant-equivalent loadLimit allocation to A's supported allowance
One UPS module unavailableRemaining modules and distributionDerated module sum; bypass rating; battery runtimeModule-out results and settingsApply the tightest surviving electrical limit
Utility unavailableUPS bridge then generatorIT plus cooling/losses, transfer trace, fuel durationIntegrated outage and recovery recordHold allocation to proven load and duty envelope
One cooling train unavailableRemaining cooling pathHeat rejection, local delivery, recovery envelopeRack inlet or liquid-loop time seriesReduce allocation if thermal delivery binds
Planned maintenance plus failurePrecisely named residual topologySurviving capacities and restoration sequenceAgreed scenario evidenceInclude only where the buyer explicitly requires this service

Each row also needs duration, initial state, limiting asset, evidence ID/revision, test load, hold time, transient result, status, owner and due date. A normal limit below the surviving-path limits still controls deployment.

Reconcile signed but uninstalled reservations as well as running loads at every shared device. A customer's commitment belongs in both UPS and PDU checks when it traverses both; compare the remaining allowances rather than adding them. At each device, count each commitment once. Calculate either the buyer's total allowance excluding its own existing reservation from other commitments, or incremental headroom including it; label the result. Metered utilization alone does not reveal capacity already sold.

The sustained kW result needs passing transfer, voltage/frequency, thermal and workload conditions over the required duration. Include battery/fuel autonomy, replenishment and return transfer. Use power density planning for load placement and power capping and oversubscription for enforced allocations.

What evidence proves contracted rack failover?

Request the signed script and results, actual connected load, load placement, power factor, topology revision, as-left settings, firmware, ambient conditions, exceptions and synchronized traces. “Full load” needs a named boundary and a number. The electrical commissioning and power QA guide explains the underlying acceptance records; integrated systems testing covers scenario execution.

Trace each test to the buyer's delivery point. A generator load bank connected upstream of the UPS does not establish rack delivery downstream. A resistive load differs from a dynamic GPU workload; record load characteristic and the validation covering that difference. For single-cord equipment, retain the rack transfer device's rating, source-compatibility limits and measured transfer result at the device inlet.

Match battery runtime at the specified load and condition to the complete transfer sequence. Retain recharge state, unavailable strings, capacity evidence and time until another event can be supported. Use UPS and static transfer switch checks and generator acceptance and load-bank turnover to locate the relevant records.

A test at 60% load needs a bounded engineering basis before supporting a 100% tenant claim. Identify the uncovered path, load placement or operating envelope and require targeted verification. After a change, choose affected-scenario verification or a full integrated retest according to the documented impact, rather than treating every change as identical.

Collect recovery evidence: return transfer, restored redundancy, temperatures, alarms and defect closure. An accepted deviation needs a stated kW/scenario consequence, interim restriction and corrective action.

What sampling interval is fast enough?

Specify the event to detect and the shortest contractual acceptance interval, then match waveform sampling, bandwidth, triggers and clock accuracy to it. Logger time resolution alone does not establish interruption-detection capability. Anvilfield recommends 1-second power/temperature trends through the scenario and 1-minute operating exports for the preceding 30 days, plus event waveforms; instrumentation must still resolve faster equipment responses.

Does usable power also support cooling and GPU performance?

Cooling evidence must follow heat to the rack through failure and recovery. DOE/FEMP's July 2024 design guide summarizes the ASHRAE fifth-edition recommended inlet band of 18°C to 27°C for classes A1 to A4. That band is neither a universal GPU limit nor a chilled-water setpoint. [S8]

ASHRAE's May 31, 2022 errata correct the Class H high-density Table 2.2 allowable dry-bulb interval to 15°C to 25°C and identify incorporation into the revised 2022 fifth edition. Select the applicable equipment class and OEM envelope; the two published temperature ranges address different scopes. See data center thermal envelopes. [S17]

Measure the hottest relevant server inlets rather than substituting room averages or return air. Record heat location and air/liquid split when a load bank supports a cooling claim. Obtain evidence for hot weather, restricted water or other design-limiting conditions when the current season does not exercise them.

For liquid cooling, request installed CDU and pump duty, minimum/peak flow, supply temperature, differential pressure, water-quality requirements, residual air cooling and failover trends. Put the actual model limits into the register. CDU commissioning supplies the test context, while the capacity uncertainty worksheet addresses close thermal decisions.

Does “still running” mean full GPU performance?

The DGX H100/H200 has a specified 10.2 kW maximum system draw and six PSUs in a 4+2 arrangement. NVIDIA's October 17, 2026 DGX H100/H200 User Guide states that operation with only three powered PSUs continues at reduced performance, so powered operation alone does not establish sustained GPU performance after a feed loss. With three PSUs on each feed, losing either feed leaves three powered PSUs and invokes that reduced-performance condition. [S11]

Record server model, PSU-to-feed mapping, cold-start capability and ownership of facility, tenant and cloud power caps. Aggregate PSU nameplate watts are not server input draw. Retain workload throughput, GPU clocks, caps and throttling events beside facility traces, and specify the accepted performance or restoration obligation.

How fresh must capacity and test evidence be?

Under Anvilfield's evidence-register method, a capacity confirmation date establishes inventory freshness, while test date, configuration revision and intervening changes establish whether a failover result supports the current claim.

Colocation Scout's verification policy, reviewed July 24, 2026, removes operator-reported regional inventory rows it cannot reconfirm within 45 days. That is an inventory policy, not a failover retest standard. The buyer still needs evidence matching the reserved load, configuration and service conditions. Colocation Scout verification policy

Table 4. Freshness and change register
RecordRequest interval or triggerConsequenceAuthority
Capacity and allocation confirmationDated within 30 days of decision; reconfirm at execution and before deploymentReconcile any intervening sale or deploymentAnvilfield buyer recommendation, 2026
Operating load exportsPreceding 30 days, 1-minute trend, plus peaks/events; retain design-limiting seasonal evidenceIdentify sustained load and excursions; resolve uncovered seasonal conditionsAnvilfield buyer recommendation, 2026
Configuration attestationWithin 30 days of decision, listing changes since testMap every change to affected scenariosAnvilfield buyer recommendation; topology relevance supported by S5
Full evidence-register reviewEvery 12 months and before material expansionRefresh documents, reservations and open actionsAnvilfield buyer recommendation, not annual IST mandate
Controls, firmware, protection, routing or cooling modificationOn change, before relying on the affected claimDetermine and complete affected verification/retestAnvilfield method; S5 supports topology-change concern
Failed test or significant incidentAfter correction, before restoring the affected claimRetain successful repeat evidence and close defectsAnvilfield buyer decision rule
Claimed Tier certificationCheck exact award, phase, award validity and subsequent changes at each transactionDo not treat a design award as tenant allocation evidenceS15 and S5

The intervals above are Anvilfield buyer recommendations. A twelve-month register review is not a universal annual IST expiry; retain the site's actual maintenance, certification and change-control obligations separately. A recent test before a protection or firmware change can be less relevant than an older test of the unchanged configuration.

Connect current meter exports and configuration changes to DCIM and asset records. Reconfirm reservations before deployment: sales change shared-capacity headroom without changing equipment.

Claim-to-evidence matrix: what is supported?

Classify each material assertion separately. “Supported” means matching evidence for the stated service; “conditional” means a named dependency with a quantified consequence; “unsupported” means evidence is missing, mismatched or fails the agreed acceptance conditions. Record the lower supported kW separately from the requested but unproven allocation.

Retain document ID, issuer, issue/test date, locator, revision, delivery boundary, scenario, supported kW, duration, limiting condition and acceptance signature. Distinguish issuer records, engineering calculations and witnessed measurements. A weighted score must not let an attractive certificate offset a failed essential capacity claim.

Table 5. Claim evidence matrix: buyer decisions
ClaimMinimum matching evidenceSupported caseConditional or unsupported caseSupplier / next action
“10 kW contracted”Executed schedule, demarcation, delivery date and service conditionsEntitlement clear at named rack boundaryEntitlement supported but 10 kW failure delivery unproven: classify those claims separatelyOperator commercial and engineering: reconcile purchased service with deliverable allowance
“A/B protected”One-line plus both directional loss recordsEach surviving feed supports required rack loadOnly A-loss tested: B-loss claim unsupported; a common UPS also leaves the UPS-loss claim unprovenEngineering/Cx provider: identify failure domain and missing scenario
“Capacity available now”Energized path, dated unallocated-capacity ledger, reservationBuyer block allocated with no duplicate claimFuture utility milestone or unreserved inventory: conditionalOperator: identify dependency and allocation date
“N+1 UPS”Installed module count, site derates, settings and module-loss traceRemaining modules carry required load within limitsParts count alone: unsupported capacity claimEngineering: reconcile real surviving output
“Cooling holds on failure”Rack/loop trace through outage and recovery at required loadThermal conditions stay within specified equipment envelopeElectrical trace only: unsupported thermal claimMechanical/Cx provider: supply thermal scenario
“GPU performance protected”Facility event plus workload and throttling recordsAgreed throughput persists or agreed recovery is metMeasured throttling outside agreed performance: unsupported performance claim; expansion conditional on correctionCloud operator: define and demonstrate performance
“Tier III certified”Correct award type, site/phase identity and change historyExact claimed certification is verifiedMarketing label or different campus phase: unsupportedOperator: provide exact award evidence
“Passed IST”Script, traces, configuration and defect closureRecords match tenant-relevant scenario and current configurationSummary certificate with no load/trace mapping: unsupported for allocationCx provider: release bounded evidence pack

Operator engineering owns topology and allocation reconciliation; the commissioning provider supplies test records. The buyer's technical reviewer reconciles the claim, and procurement carries the agreed deliverables into the commercial schedule. These acceptance roles do not grant switching authority.

When confidentiality prevents unrestricted disclosure, request redacted records preserving load, boundary, scenario and result, a controlled data-room review or a scoped independent witness statement. If essential evidence remains unavailable, leave that claim unsupported and reduce or defer the affected purchase.

Worked example: two 30 A feeds are not 9.48 kW of protected load

The worked rack has two independent 208 V, 30 A single-phase feeds, a fully transferable 4.20 kW IT load and 0.95 power factor. Anvilfield estimates the following limits using Schneider Electric FAQ FA104355, revised October 14, 2024. [S1]

Multiply voltage by allowable current and power factor to obtain real watts, then divide by 1,000: kW = V × A × PF / 1,000. Compare that feed result with every upstream and downstream limit on its surviving path. For balanced three-phase input, multiply line-to-line voltage by line current, power factor and the square root of three, then divide by 1,000. Check every phase and neutral loading separately.

Table 6. Worked inputs, results and sensitivity
ItemInput or calculationResultProvenance
ConfigurationTwo independent single-phase feeds; load fully transferable to eitherA and B evaluated separatelyAnvilfield design inputs, 2026
Voltage and breaker208 V; 30 A each, conventional continuous application24 A continuous per feedSelected inputs; S1 application factor
Power factor0.95 at design conditionUse real kW, not kVAAnvilfield calculation input; verify on installation
Surviving feed ceiling208 × 24 × 0.95 / 1,0004.74 kWAnvilfield estimates
Sum of both feed ceilingsTwice the unrounded feed result9.48 kW normal aggregate electrical capacity, without either-feed protection at that loadAnvilfield estimates
Planned total IT load4.20 kW2.10 kW per feed with equal sharingAnvilfield design input
Normal current, equal sharing2,100 / (208 × 0.95)10.63 A per feedAnvilfield estimates
Current after either feed loss4,200 / (208 × 0.95)21.26 A on survivorAnvilfield estimates
Remaining electrical marginUnrounded feed result minus 4.20 kW0.54 kW; 2.74 AAnvilfield estimates
Power-factor sensitivitySame 208 V and 24 A, PF = 1.00 / 0.904.99 / 4.49 kWAnvilfield estimates; hold kVA/current limit fixed
Voltage sensitivity200 V, 24 A, PF = 0.954.56 kWAnvilfield estimates; actual voltage is an input
Unequal surviving pathB limited to 20 A breaker × 0.80, 208 V, PF = 0.953.16 kW after A loss; 4.20 kW deployment exceeds it by 1.04 kWAnvilfield estimates; S1
Known cooling allowanceBuyer worksheet input: 4.00 kW at same rack boundary in required scenarioCombined allocation at most 4.00 kW; reduce planned load by 0.20 kWAnvilfield selected input, requiring site evidence

The smaller surviving path controls either-feed service. The 20 A sensitivity therefore rejects the 4.20 kW deployment even though the other feed retains its original rating. Lower voltage or power factor also reduces real-power allowance at a fixed current ceiling; use installation measurements when completing the site worksheet.

Table 7. Completed buyer allocation by scenario, all values in tenant IT kW
ScenarioContract C_sElectrical E_sCooling H_sControl P_sCalculated U_s / limiting item
Normal, both feeds4.509.484.604.304.30 / control cap
A unavailable, B survives4.504.744.004.304.00 / cooling
B unavailable, A survives4.504.744.404.304.30 / control cap
Required either-feed serviceSame selected entitlementEach feed checked separatelyScenario-specific coolingCap remains enforced4.00 / lowest failure row

A-loss cooling sets the 4.00 kW allocation, below the 4.20 kW design load. Reduce deployment by 0.20 kW or resolve the cooling constraint and close the scenario evidence.

Normal aggregate capacity assumes both complete upstream paths support the sum. The contract, cooling and cap entries are Anvilfield planning inputs. Attach matching site records, duration and passing transition results before accepting the allocation.

Method note: Anvilfield estimates use the November 5, 2026 source check, Schneider's continuous-application rule and the declared voltage, current, power factor and load inputs. Calculate with unrounded values and display two decimals. The evidence pack supplies measured values, applicable ratings and contractual allowances.

What does a UPS temperature rule do to unit-loss capacity?

Select three compatible complete 100 kW Galaxy VS UPS units in parallel at 45°C, with installed parallel support and controls confirmed. Under revision 990-91141L-001's temperature rule, each retains 87.5 kW; Anvilfield estimates 175 kW after one unit is lost, compared with 200 kW from unadjusted ratings. [S13]

For a shared-bus continuation, select 5 kW of non-IT load and downstream loss, leaving 170 kW at the tenant boundary. Deduct 110 kW of other commitments and 10 kW of separate reserve: Anvilfield estimates 50 kW remaining. A downstream PDU with 40 kW remaining limits the electrical allowance to 40 kW; with a 60 kW contract, 48 kW cooling allowance and 45 kW cap, the buyer allocation is 40 kW.

Now commit another 20 kW on the UPS through a different PDU. UPS headroom falls to 30 kW, so the buyer allowance falls to 30 kW even though its local PDU still has 40 kW free. Reconcile each shared device independently and take the tightest allowance; do not add overlapping headroom.

How much time and money does buyer evidence review take?

Anvilfield estimates 44 professional hours and $8,300 for the desktop review below, using selected billing allowances. With one reviewer and eight productive hours per day, that is 5.5 working days after the complete pack arrives. Operator response time, site access and retesting are separate schedule items.

Table 8. Review allowance, Anvilfield estimates, 2026. These are selected estimating inputs, not surveyed fees
Work itemHoursSelected hourly allowanceExtended allowance
Document inventory, meter map and allocation reconciliation24$175$4,200
Electrical and mechanical scenario review12$225$2,700
Provider questions and final evidence register8$175$1,400
Total desktop scope44Mixed rates$8,300
Additional review day sensitivity8$175Add $1,400

The deliverables are a meter map, completed registers, scenario gap list and technical schedule for procurement. Quote site witness work separately by scenario, test window, travel, instrumentation, vendor attendance, load banks and repeat mobilizations. An incomplete pack adds question cycles; define who must answer and when before fixing the delivery schedule.

Estimating method: Multiply the selected hours by each rate and sum once. The $8,300 allowance excludes contingency, tax, travel, live switching, load-bank or instrument rental and test crews.

Compare provider charges over the same term and delivery boundary using the same included recurring charges divided by evidence-supported contracted IT kW. Show energy, reservation, setup, cross-connect and overage terms separately. A physical capacity shortfall does not create an assumed contractual refund.

Past awards and winning amounts in PorchRocket Bid Control let estimators compare agency power-upgrade scopes with the metering, testing and turnover deliverables in the current bid.

Buyer evidence request checklist

Send this pack to the operator with the proposed rack schedule and service envelope. Assign each unresolved item an owner, due date and effect on the named kW claim. The operator's approved process governs testing; the request pack identifies required evidence and does not prescribe a switching sequence.

  • Name site, hall, suite, racks, deployment date, continuous protected IT kW, required duration and accepted interruption.
  • Attach the contract schedule and identify its meter boundary and billing units.
  • Provide the current one-line with both rack feeds traced through shared dependencies.
  • Provide installed ratings, breaker settings and applicable OEM derating revisions.
  • Reconcile current load, reserved load and this buyer's allocation independently at every shared bottleneck, then take the tightest remaining allowance.
  • Fill normal, A-loss and B-loss rows; add module, utility and cooling scenarios required by the service.
  • Attach electrical and thermal test traces, load distribution, hold time, instrumentation, uncertainty/acceptance rule and clock information.
  • Confirm battery condition, transfer timing, generator duty, fuel plan and recovery sequence.
  • Identify single-cord equipment, transfer devices and any unprotected controls or cooling loads.
  • For GPU service, attach power-cap settings, workload performance and throttling records.
  • Attach defect closures and repeat-test records for affected scenarios.
  • List configuration changes since testing and the evidence that closes their effects.
  • Date the availability confirmation and identify who reserves the capacity.
  • Record exact certification type and facility phase for each certification claim.
  • Assign unresolved claims, permitted interim load and evidence delivery dates; record evidence IDs, configuration revision and acceptance owner.
  • Obtain buyer technical acceptance and carry the agreed evidence duties into the commercial schedule.

Accept the allocation when the required scenarios, limits and evidence match. For a conditional claim, record the permitted interim load and the dependency that must close before expansion. Carry ongoing evidence delivery, configuration-change notice and reservation duties into the agreed commercial schedule so the register remains useful after handover.

Sources, methodology and how to cite this page

Anvilfield checked the following eleven primary documents on November 5, 2026. Public manufacturer and agency explanations support the stated applications; the registers, allocation method, review intervals and estimating allowances are Anvilfield's buyer evidence pack.

Use stable links to the meter demarcation register, derating register, failure-capacity worksheet, test freshness register and claim evidence matrix when citing individual evidence units.

Update log: 2026-11-05: Final article review completed; source applications, allocation rules and buyer evidence pack checked.

How to cite this page: Anvilfield, How much colocation power is usable after a failure?, 2026, https://anvilfield.com/field-guides/datacenter/colocation-power-capacity-evidence-register/

Related tools

Next step: Find public capital bids

FAQ

How much colocation power is usable after a failure?

Anvilfield estimates 4.74 kW of surviving electrical capacity for the two-feed 208 V, 30 A, 0.95 PF worked case; the selected cooling constraint reduces the buyer allocation to 4.00 kW. Apply the lowest supported limit and the agreed interruption and duration conditions.

How do I verify usable colocation power?

Match metered load, installed ratings, site derates and allocation records to the same tenant delivery boundary.

What proves contracted rack power will fail over?

Require directional A-loss and B-loss evidence at the relevant load and configuration, with thermal results and defect closure.

What should GPU cloud facility diligence include?

Include facility capacity, cooling and workload performance through the event, including enforced caps and throttling.

Can I add the capacity of A and B feeds?

Add their readings to measure normal consumption, but use the surviving path's limit when calculating either-feed protection.

Does Tier III mean the rack survives every failure?

Uptime Institute’s April 2021 explanation defines Tier III by concurrent maintainability. Tenant allocation and required failure scenarios still need matching evidence.

Does every circuit have to stop at 80%?

Schneider FAQ FA104355, revised October 2024, distinguishes standard-rated continuous applications from qualifying 100% rated applications. Apply the installed assembly’s conditions rather than treating 80% as a global rule.

Does a low PUE prove spare power?

No. The Green Grid defines PUE as an energy-efficiency ratio; it does not state spare rack current or surviving cooling capacity.

Does an IST report expire after one year?

This pack recommends annual evidence review and change-triggered verification, not a universal annual IST expiry.

What if the provider will not share raw test files?

Request scoped redaction, controlled review or independent verification; an essential claim without matching evidence remains unsupported.

For how long must the contracted power survive?

State the purchased outage duration and initial battery/fuel condition; check transfer, sustained operation, replenishment and return transfer against that service. A sustained kW ceiling and an autonomy duration answer separate parts of the service claim.

How do I avoid counting shared power capacity twice?

Reconcile commitments at every shared device, then use the lowest remaining path allowance; never add overlapping UPS and PDU headroom. In the shared-bus example, 50 kW remaining at the UPS and 40 kW at the PDU leave 40 kW for the buyer.