150 percent point
At the 150 percent point, a 1,500 gpm fire pump rated for 120 psi must add at least 78 psi while delivering 2,250 gpm under Xylem's A-C specification. The comparison uses discharge pressure minus suction pressure, corrected for tap elevation and velocity. That separates the pump's contribution from pressure the supply already provides; a high discharge reading alone can hide weak high-flow performance.
At 150 percent of rated flow the pump must produce at least 65 percent of its rated pressure
Calculate the target before opening the test header
Xylem's A-C Fire Pump specification requires at least 65 percent of rated head at 150 percent of rated capacity, with shutoff head no higher than 140 percent of rated head. NFPA identifies the current installation standard as NFPA 20, 2025 edition. The percentages establish a performance envelope; the manufacturer's submitted curve supplies the expected head for the particular impeller and speed.
Put the rated flow, rated head and corresponding high-flow target on the test sheet as separate fields. A pump rated 1,250 gpm reaches its 150 percent point at 1,875 gpm. Xylem's ACF021 curve sheet marks those two flow positions explicitly and identifies the test curve's 2,350 rpm speed. A different speed or impeller diameter describes a different curve.
Correct the gauge comparison for the actual test arrangement
Using the Hydraulic Institute's total-head relationship, a discharge tap 4 ft above the suction tap adds 4 ft of water head, about 1.73 psi, to the pressure-gauge difference. A larger suction pipe and smaller discharge pipe also have different velocity heads. Those corrections matter near a pass threshold.
For a separate 1,000 gpm, 100 psi pump tested at 1,500 gpm, readings of 108 psig discharge and 46 psig suction give a pressure difference of 62 psi. With negligible elevation and velocity corrections, the pump falls 3 psi short of its 65 psi minimum despite the discharge gauge showing more than the nameplate rating. Attach this calculation to the plotted point in the acceptance-test record, with the two gauge-tap elevations identified.
Separate a curve limit from the building demand
A 65 percent minimum does not say that every sprinkler or standpipe demand can be served at that pressure. Supply pressure, elevation loss and downstream friction still determine pressure at the demand point. Nor does a measured value above 65 percent erase a substantial departure from the pump's certified performance.
Label the two comparisons separately: compliance with the high-flow envelope and agreement with the submitted curve. That keeps a low curve reading from being accepted merely because it clears the broad minimum.
Distinctions
- Rated point
- The rated flow and head establish the nameplate duty. The high-flow point tests a different position on that same curve.
- Churn
- Churn is zero external flow. Its pressure ceiling protects downstream equipment and does not substitute for a capacity test.
Frequently asked questions
Is 150 percent a pressure-test setting?
No. The percentage refers to flow. A hydrostatic proof test of piping is a separate pressure test with its own specified conditions.