62 percent rule
The 62 percent rule is a shortcut within a fall-of-potential grounding test: for a 200 ft span to the current stake, it puts the potential probe about 124 ft from the electrode being tested. Its validity depends on a simple electrode geometry, reasonably uniform soil and adequate separation. Compare neighboring probe positions before accepting the resistance; neither the percentage nor a single low reading establishes a passing ground.
The potential pin position, about 62 percent of the way to the current pin, where the reading is valid
Where the 61.8 percent position comes from
Metrel derives the 61.8 percent position using equal test current through the tested electrode and auxiliary current electrode, uniform soil, and electrodes represented as hemispheres. Separation must be sufficient for that simplified geometry to represent the real arrangement. In this model, the position fraction is (sqrt(5) - 1) / 2, approximately 0.618. Rounding that fraction gives the familiar name.
A 200 ft current-stake distance puts the calculated potential position at 123.6 ft. Rounding to 62 percent moves it to 124 ft, a 0.4 ft difference. The origin matters more than that rounding: an incorrect electrical center or a traverse crossing different soil conditions changes the calculation's assumptions. The grounding test guide covers the complete test arrangement.
Measure from the electrode's electrical center
AEMC's Understanding Ground Resistance Testing workbook limits its simple 62 percent method to a single electrode unit with all three electrodes in a straight line. A rod, pipe, or plate has a much simpler reference geometry than a ring connected to building steel and remote electrodes. Measuring from the nearest test well does not establish the electrical center of that entire network.
Draw the electrode, potential stake, and current stake on the test sketch, then identify the origin used for both distances. If the tested system extends beyond that origin, retain its dimensions and connected paths. AEMC bases multiple-electrode stake spacing on the maximum grid dimension, such as the diagonal of a square, rather than applying a single-rod spacing unchanged.
How close must the three readings agree?
AEMC plots neighboring checks at 52, 62 and 72 percent of the electrode-to-current-stake span. For the 200 ft layout, mark 104, 124 and 144 ft from the same origin and leave the current stake fixed while comparing those readings. Moving both stakes between checks would change two inputs at once.
AEMC describes comparison bands such as ±2, ±5, or ±10 percent as tolerances selected by the user, rather than a single automatic acceptance limit. Set the applicable comparison band in the test plan. A 2.00 ohm center reading with a specified ±5 percent band sets adjacent comparison limits of 1.90 and 2.10 ohms. Preserve each reading and the chosen band so agreement has a defined meaning.
That band assesses the stability of the test geometry. The project's maximum electrode resistance answers a different question. Three readings within the comparison band can still exceed the specified resistance target, while a low center reading with large adjacent changes leaves the measurement unsupported.
When 62 percent loses its meaning
Layered soil, buried metallic paths, an extended electrode network, or inadequate current-stake distance require more information than a percentage supplies. A fall-of-potential traverse preserves the changing resistance across the span and exposes a slope hidden by the center reading. Moving a stake until a preferred number appears defeats the geometry check.
IEEE 81-2025 is the current measurement reference. A report naming the 62 percent method should establish why its electrode geometry and soil assumptions fit the tested system. A percentage written beside a resistance value supplies neither of those facts.
Distinctions
- Resistance target
- A required maximum resistance evaluates the grounding system. The 62 percent position and adjacent reading comparison evaluate how that resistance was measured.
Frequently asked questions
Is 62 percent measured from the current stake?
Measure from the tested electrode's reference center toward the current stake. Reversing the origin places the potential stake at 38 percent of the intended span.
Sources checked
Also defined as
- Datacenter: Potential probe at 61.8 percent of the electrode-to-current-probe distance, for a valid reading in uniform soil