ANVILFIELD Try FieldOS

Field glossary · business

Allowance

An allowance reserves a stated amount in the contract for a selection or scope detail whose final cost is still open. The allowance’s cost boundary matters as much as its amount: a material-only allowance and an installed-work allowance reconcile differently. Identify what the allowance includes, what is already carried elsewhere in the contract, and how the final difference changes the contract sum.

A placeholder dollar amount for a specific, identified item not yet priced, such as fixtures still to be selected, reconciled to actual cost later.

Used across 3 Anvilfield field guides, most in Electrical.
Updated

What an AIA material allowance pays for

AIA A201-2017 §3.8 places delivered material and equipment cost, required taxes, and applicable trade discounts inside an allowance unless the contract documents provide otherwise. Freight and sales tax therefore belong in a delivered-cost comparison rather than appearing later as unexplained extras.

AIA A201-2017 §3.8 places unloading, handling, installation labor, overhead, and profit outside the allowance itself but inside the contract sum. The distinction prevents an estimator from carrying installation twice or omitting it because the owner has not selected the product. A project-specific allowance schedule can set a different boundary; its wording controls the estimate.

Reconciling an $8,000 selection

A finish-material allowance is $8,000. The selected material costs $8,750 delivered with tax after discounts, and the selection adds $500 to installation cost already carried in the contract. The adjustment is $1,250: $750 for the material difference plus $500 for the changed installation requirement.

AIA A201-2017 §3.8 requires an allowance change order to reflect both the actual allowance-cost difference and resulting changes to the contractor’s other costs. A supplier invoice proves the material purchase; it does not by itself prove the labor adjustment. Attach the selection, invoice basis, and installation difference to the reconciliation.

Run a credit through the same calculation. Material selected for $7,500 against the $8,000 allowance creates a $500 material credit; an accepted $200 installation increase reduces the net credit to $300. Showing both lines prevents a lower invoice from hiding a genuine installation change.

Keep selection deadlines attached to the money

An allowance does not reserve factory capacity or establish a delivery date. Give each selection a needed-by date tied to procurement and installation, plus an owner decision date that allows the stated lead time. The preconstruction planning guide supplies the wider decision schedule; the allowance log connects the unresolved selection to its specific cost boundary.

AIA A201-2017 also calls for owner selection of allowance materials and equipment with reasonable promptness. A late choice that changes the product and delivery sequence should leave separate records of the selection difference and its scheduling consequence. Otherwise a single allowance balance hides two different commercial questions.

Distinctions

Contingency
Contingency covers identified estimating uncertainty or risk under its stated rules. An allowance attaches an amount to a particular unresolved item; spending one does not automatically authorize spending the other.

Frequently asked questions

Is an unused allowance automatically contractor profit?

Under the A201 allowance mechanism, the contract sum is adjusted to the actual cost basis and associated changes. A lower selection cost produces a credit through that reconciliation rather than silently becoming margin.

Sources checked

Also defined as

  • Landscaping: A stated budget or quantity for defined work, with authorization and payment rules agreed in the contract.
  • A placeholder dollar amount carried for scope that is real but not yet defined enough to price.

Where this shows up

Next step: Review electrical bid scopes

Back to the full field glossary