Estimate class
AACE estimate class describes the information supporting an estimate, using the practice for that industry. For repeatable building work, RP 56R-08 associates Class 3 with roughly 10% to 40% project definition. Its typical accuracy limits are 5% to 15% below and 10% to 20% above the estimate after contingency. Those limits depend on project risk; a Class 3 label alone promises neither a fixed tolerance nor an 80% chance of staying within budget.
AACE's classification of an estimate by design maturity, Class 5 conceptual to Class 1 definitive, which sets the expected accuracy range.
Which AACE practice fits the facility?
AACE's Professional Guidance Document 01, revised August 29, 2022, directs building and general construction work to RP 56R-08 and process-industry work to RP 18R-97. Put the selected practice in the estimate basis so a reviewer knows which deliverables the class describes.
RP 56R-08's August 7, 2020 revision covers repeatable building and site/civil work, while excluding one-of-a-kind facilities such as research buildings and high-tech manufacturing. Classifying an office addition does not establish the basis for its adjacent specialized production plant. Separate the packages and select the practice for each scope.
Can one unfinished package hold back the class?
AACE PGD 01 makes key deliverables a gate: the target class is not reached until all key defining deliverables have the required maturity. It permits a class declaration with identified exceptions when lagging deliverables are non-critical. It does not average packages into a fractional class.
For a building budget, test the utility connection separately from the equipment takeoff. A complete switchboard count cannot settle an unresolved service route, connection point or civil scope. List the missing input, its pricing treatment and its effect on the class declaration in the preconstruction estimate basis.
Class 3 accuracy limits and the 80% interval
AACE RP 56R-08 gives Class 3 a typical low-side limit selected from 5% to 15% below the estimate and a high-side limit selected from 10% to 20% above it. It associates this class with 10% to 40% project definition and budget authorization or design development. The percentages describe deliverable maturity broadly, not engineering hours spent.
RP 56R-08 expresses accuracy at an 80% interval after appropriate contingency, typically around a funding position with equal chances of overrun and underrun. An 80% interval describes the spread of outcomes; an 80th-percentile budget is a funding amount covering 80% of outcomes. These are different statistical statements.
Turn the percentages into a budget discussion
A $2,400,000 estimate containing contingency has a risk-analysis interval from $2,160,000 to $2,760,000. Those endpoints are -10% and +15% relative to the estimate. They do not establish its class, and the upper outcome is not an instruction to add another 15% reserve. Record the interval's probability coverage and the estimate's funding percentile separately.
PGD 01 assigns project-specific accuracy to quantitative risk analysis. Different ground conditions, execution complexity and price exposure change the interval even when the defining documents support the same class. Carry those assumptions with the cost date and location basis so the next revision explains what changed.
Specify the estimating service beyond its class
PGD 01 says a class label alone does not specify the quality of an estimating process. A request for estimating services should also name input revisions, scope boundaries, quotation requirements, reconciliation format and the required risk-analysis output. Ask for the priced quantities and assumptions needed to repeat the calculation, rather than accepting a cover sheet marked 'Class 3'.
Distinctions
- Estimate accuracy
- The expected spread of outcomes for the defined project. Classification communicates the information available; risk analysis quantifies the uncertainty in the resulting cost.
- Design milestone
- A contractual issue such as schematic design or design development. Its label alone does not prove that every defining deliverable has reached the maturity required for a particular estimate class.
Frequently asked questions
Is a Class 3 estimate the same as a 30% design estimate?
No. AACE RP 56R-08 associates Class 3 with a broad 10% to 40% definition range, and PGD 01 uses maturity of the defining deliverables to establish the class. A drawing issue labeled 30% does not show whether a critical site or utility input is settled.
Is the upper accuracy percentage the contingency percentage?
No. RP 56R-08's accuracy interval already includes appropriate contingency. Record the project's modeled interval and funding percentile separately; the upper endpoint is not a second reserve to add.
Sources checked
Also defined as
- The AACE measure of how defined the design was when the estimate was made, Class 5 conceptual through Class 1 on complete documents.