ANVILFIELD Try FieldOS

Field glossary · business

Contingency

Set contingency by subtracting the base estimate from the risk-adjusted funding target. A $500,000 base funded at $540,000 carries $40,000 of contingency, or 8% of base cost. The target comes from combined risk outcomes and the selected funding confidence. Adding probability-weighted losses gives an average, which can buy less coverage than that target. Record the reserve's holder and baseline treatment because funding and earned-value frameworks use reserve labels differently.

Money in the estimate for known-unknowns: costs that will occur but are not yet defined, sized to the project's risk and design completeness. Not profit, padding, or forgotten scope.

Used across 4 Anvilfield field guides, most in Electrical.
Updated

Choose a funding percentile, not an average loss

GAO's Cost Estimating and Assessment Guide, GAO-20-195G (March 2020), calculates contingency as the difference between the point estimate and the modeled cost at management's selected confidence level. A cost percentile answers how much funding covers a stated share of modeled outcomes. An expected value answers the average of those outcomes.

A risk register recording only 'high' or 'medium' cannot generate a funding percentile. Add the amount, probability and shared cause for each event to the risk-pricing record. Identify costs already inside the base so the reserve does not fund the same exposure twice.

Two priced risks produce different reserve choices

An estimate has a $500,000 base excluding two retained risks. Its risk assessment assigns a 30% probability to $40,000 of extra excavation and a 25% probability to $20,000 of added staging. Treat the events as independent in this calculation. Their expected additional cost is 0.30 x $40,000 + 0.25 x $20,000 = $17,000.

Risk outcomeAdded costProbabilityCumulative probability by cost
Neither event$052.5%52.5%
Staging only$20,00017.5%70.0%
Excavation only$40,00022.5%92.5%
Both events$60,0007.5%100.0%

Read the coverage before approving the reserve

A $17,000 reserve covers only the zero-cost outcome, giving 52.5% coverage in this model. A $20,000 reserve reaches 70%. The smallest reserve reaching at least 80% is $40,000, producing a $540,000 funding level and 92.5% coverage. Discrete outcomes create jumps; the selected percentile need not correspond to an outcome with exactly that cumulative probability. The selected $40,000 reserve is 8% of the $500,000 base; that percentage is the result of this risk model.

GAO-20-195G identifies common causes as a reason to model positive correlation between cost elements. If the same access restriction drives both excavation and staging, the independent-event probabilities above no longer describe the job. Rebuild the joint outcomes before accepting the reserve; adding separate expected losses does not settle that dependence.

Who holds the reserve, and when does it become cost?

GAO-20-195G uses 'contingency' for government program funding and 'management reserve' for contractor-managed uncertainty within contract scope. NSF's EVM Gold Card places awardee-managed contingency outside the performance measurement baseline until authorized transfers occur. The name alone therefore does not identify who controls the money or whether it is already in the work budget.

The NSF Gold Card, updated June 5, 2026, moves contingency into the baseline through change control during execution. A transfer authorizes budget; it does not prove that a supplier invoiced or a crew performed work. Keep the reserve draw, purchasing commitment and actual charge as separate transactions.

Codified FAR 31.205-7 and its overhaul model generally disallow contingency for historical costing under paragraph (b). For future-cost estimates, (c)(1) includes reasonably measurable consequences; (c)(2) excludes less measurable exposures from individual cost items and calls for separate disclosure of the basis. Use the cost principle incorporated into the federal procurement when preparing its cost submission.

Distinctions

Confidence level
The probability of finishing at or below a modeled cost. An 80% confidence target is not an instruction to add 80% to the base estimate.
Schedule contingency
Time reserved for schedule uncertainty. Its effect on supervision, equipment hire and other duration-driven costs belongs in the cost model as well as the schedule.

Frequently asked questions

Is probability times impact enough to set contingency?

It calculates expected loss for the stated risk. To choose funding at a specified confidence level, calculate the combined outcome distribution, including shared causes, and select the corresponding cost.

Does an approved contingency draw prove the money was spent?

No. Approval releases budget. A purchase commitment and an incurred cost occur at their own stages, so the reserve ledger and the job-cost ledger need a documented connection rather than identical entries.

Sources checked

Also defined as

  • HVAC: Money priced into the bid to cover a specific job's risk and unknowns, kept separate from profit.
  • Landscaping: Money carried in the bid against site conditions that could not be seen at estimate time

Where this shows up

Next step: Calculate bid pursuit ROI

Back to the full field glossary