Markup

Markup is the amount charged above a stated cost base: adding 15 percent to $2,300 of eligible delivered material produces a $2,645 price. State which charges the $2,300 includes and whether overhead and profit use that same base or are applied in sequence. On reimbursable work, the contract controls both the eligible costs and the permitted additions.

A percentage added to cost; a 50 percent markup is about a 33 percent margin

Used across 3 Anvilfield field guides, most in Landscaping.
Updated

Which costs receive the percentage?

Using Penn State Extension's cost-based markup calculation, the material line below is $2,300 times 1.15, or $2,645. Label the base in the landscape estimate: invoice material, delivered material, burdened labor and subcontracted work are different pricing lines.

A material purchase of $2,000 plus $180 freight and $120 eligible handling has a $2,300 delivered-cost base. Applying 15 percent to that base adds $345. Applying it only to the purchase invoice adds $300. The $45 difference comes entirely from the base definition. Put freight and handling on visible lines so the reviewer can reproduce the amount.

Distinguish a commercial pricing base from a contract reimbursement base. A cost incurred by the business does not automatically belong in every reimbursable category. The change takeoff should identify both the amount and the provision governing its treatment.

When two 10 percent additions become 21 percent

On contracts containing GSAR 552.243-71, Equitable Adjustments, March 2019, profit applies to a firm's own direct costs plus its allowed overhead. Paragraph (h) requires negotiated rates and limits profit to 10 percent unless entitlement to a higher rate is demonstrated. A stated ceiling does not establish the negotiated rate.

For $8,000 of a firm's own direct work with negotiated rates of 10 percent overhead and 10 percent profit, overhead is $800 and profit is $880. The resulting amount is $9,680, an effective 21 percent addition to direct cost. Two additive 10 percent amounts calculated on the original $8,000 would instead total $9,600. The rate labels match; the application order does not.

GSAR 552.243-71 also generally prohibits adding overhead or profit to a subcontractor's overhead or profit, subject to its stated lower-tier cost treatment. For subcontractor work within two tiers, it allows half the claiming firm's negotiated overhead and profit rates, capped at 10 percent combined, on the subcontractor's direct costs. Preserve the subcontractor's cost breakdown instead of applying the self-performed-work calculation to an undivided subcontract total.

Agency force-account additions already cover multiple costs

WSDOT's 2027 Standard Specifications, Section 1-09.6, add 29 percent to eligible labor reimbursement and 21 percent to material and equipment costs for force-account work. These additions cover project overhead, company overhead, profit and other specified expenses. They are contract payment factors for that work, rather than targets for the contractor's net earnings.

WSDOT's 2027 labor list includes sick leave required by law in the labor reimbursement base. Its 2026 edition instead provided a separate 2 percent sick-leave addition. Identify the edition incorporated into the contract before carrying forward a previous project's worksheet.

For $4,000 of approved labor costs including required sick leave under the 2027 provisions, $3,000 materials and $2,000 equipment, the additions are $1,160, $630 and $420. Total reimbursement is $11,210 on the $9,000 base before any separately applicable provisions. The effective combined addition is about 24.6 percent because the categories have different rates.

Keep each category beside its authorized rate when assembling a change-order proposal. A second general overhead-and-profit percentage on the same total would duplicate costs already included in the specified factors. Name the edition and any project amendments with the calculation.

Distinctions

Fee
An agreed fee can be a fixed amount or follow its own contractual basis. Do not infer a cost percentage merely because a proposal labels the result a fee.
Drawing markup
A redline records an annotation or field change on a drawing. It contributes evidence of changed scope but does not itself establish the pricing addition.

Frequently asked questions

Does a material markup include freight?

WSDOT's 2027 force-account material basis includes freight, handling and applicable taxes before the 21 percent addition. Agency-furnished material receives no addition for its material value; eligible labor and equipment used to handle and place it are reimbursed separately.

Can the same markup apply to labor and materials?

A company pricing policy can use a common rate. A reimbursable proposal must follow the contract's categories and bases, which can assign different factors to labor, material, equipment and subcontracted work.

Sources checked

Also defined as

  • HVAC: The amount added on top of cost, as a percentage of cost. A 25 percent markup adds a quarter of the cost to the price.
  • Concrete: The percentage added to cost; not the same as margin