ANVILFIELD Try FieldOS

Field glossary · measurement

Connected load

Connected load is the sum of the equipment inputs served by a defined supply path before demand reductions are applied. State the boundary and the units: gas input in Btu/h or cubic feet per hour, electrical real power in watts or kilowatts, or apparent power in VA or kVA. Appliance heat output, energy use and equipment capacity are different quantities and must not be mixed into that sum.

The total CFH of all appliances the system can serve, summed for sizing

Used across 2 Anvilfield field guides, most in Plumbing.
Updated

Add appliance inputs before converting gas volume

The 2025 Fuel Gas Code of New York State, Section 402.2, starts gas sizing with simultaneous maximum inputs, allows established diversity, and requires an altitude adjustment above 2,000 feet. Preserve those as separate schedule fields: installed input, any supported demand reduction and the altitude-adjusted gas-flow basis. One appliance’s normal running rate cannot stand in for the connected maximum.

Appendix A102.1 of that code converts Btu/h to cubic feet per hour by dividing the total input by the serving supplier’s average gas heating value. At a stated 1,050 Btu per cubic foot, 315,000 Btu/h requires 300 cubic feet per hour. Dividing the same input by an assumed 1,000 instead produces 315 cubic feet per hour. Keep the actual heating-value basis beside the total.

Do not substitute useful heat for fuel input

A heater labeled 100,000 Btu/h input and 80,000 Btu/h output contributes 100,000 Btu/h to the gas input schedule. The output describes useful heating capacity after losses. The natural-gas sizing guide carries that schedule into branch and trunk sizing.

The U.S. Energy Information Administration defines 1 kWh as equivalent to 3,412 Btu. Accordingly, 10 kW of electric resistance input is about 34,120 Btu/h of energy input. That conversion does not make a heat pump’s delivered heating capacity equal to its electrical input, and it does not convert a gas appliance’s fuel requirement into its small auxiliary electrical load.

Define which equipment each segment actually serves

A shared gas main serving two 100,000 Btu/h heaters and a 115,000 Btu/h kitchen load carries 315,000 Btu/h of connected input. The kitchen branch carries 115,000 Btu/h. Totaling every appliance for every branch hides the actual distribution; omitting a branch from the main hides a real maximum.

Create one equipment schedule and trace each segment’s downstream inputs from it. An appliance served from an alternate source must be represented according to the actual transfer or interlock arrangement. “Installed in the room” and “connected to this feeder” are different boundaries.

Preserve the original sum when demand changes

Keep the connected total alongside the demand calculation and its reduction basis. That allows a later equipment addition to start from a complete inventory rather than reverse-engineering a previously reduced number. The electrical-load guide explains why the service calculation is a separate deliverable from the connected-load schedule.

Distinctions

Demand load
The load established by the applicable calculation or operating-demand basis after justified reductions. It should remain traceable to the original connected equipment.
Energy consumption
Power integrated over time, such as kWh. A monthly energy bill cannot be added to a nameplate power schedule.

Frequently asked questions

Should I add gas input or heat output?

Use maximum fuel input for the gas connected-load schedule. Output ratings describe the heat delivered by the appliance.

Is connected load the same as breaker capacity?

A breaker rating describes circuit protection. The equipment schedule describes the loads served; they are not interchangeable totals.

Sources checked

Also defined as

  • Electrical: The full sum of all load nameplates before any demand factor is applied

Where this shows up

Next step: List rooftop equipment sites

Back to the full field glossary