Demand load
Demand load is the load assigned to a feeder or service after applying the calculation method and demand treatment permitted for that installation. It is distinct from both the sum of connected equipment ratings and a utility meter’s recorded demand. State whether a figure is calculated or measured, its units, and the code edition or measurement interval behind it.
The diversified load after Article 220 demand factors, what the feeder really carries
The 2026 NEC moves the calculation address
Minnesota’s official 2026 NEC adoption review identifies Article 120 as the new location for branch-circuit, feeder, and service load calculations formerly organized in Article 220. A worksheet citing Article 220 can therefore be using an earlier edition rather than a different engineering concept.
The same Minnesota review identifies 120.7 as addressing listed power control systems used in determining service or feeder size. A promised operating schedule is different from a listed system that enforces a load limit. Record the actual control arrangement when a calculation depends on that limit.
Keep the selected method and its assumptions with the electrical load calculation. A single demand percentage copied from another occupancy cannot show why the reduction is permitted for this installation.
A utility peak is an interval average
Kentucky’s state energy guide describes utility demand measurement as average kilowatts over 15-minute or 30-minute intervals. A brief peak can therefore differ from the demand recorded for a full billing interval. With a 15-minute interval, 100 kW for five minutes and 40 kW for ten minutes averages 60 kW.
The Kentucky guide also identifies demand ratchets that base billing demand on a percentage of an earlier peak. A billed demand value can consequently differ from the highest interval measured this month. Keep the meter interval data separate from the tariff’s billing calculation when evaluating an existing service.
Keep real power and apparent power apart
The Kentucky energy guide defines power factor as real power divided by apparent power. A 90 kW load at 0.90 power factor represents 100 kVA. Treating the 90 kW reading as 90 kVA understates the apparent-power basis used to relate voltage and current. For a balanced 480 V three-phase load, 100 kVA corresponds to about 120 A: 100,000 VA ÷ (√3 × 480 V). Once the kW reading has been converted to kVA using power factor, do not apply that power-factor adjustment a second time in the current calculation.
For existing-load work, retain the measurement dates, operating conditions, interval, and any load absent during monitoring. A quiet-season record does not establish that a seasonal load vanished from the design. Apply the governing method for using measured data rather than treating a favorable bill as a completed load calculation.
Distinctions
- Connected load
- Connected load totals the relevant installed ratings before permitted demand treatment. It supplies an input to the chosen method, not automatically the final service requirement.
Frequently asked questions
Does a lower demand load reduce every branch-circuit requirement?
No. A service or feeder demand calculation does not automatically change the individual equipment, branch-circuit, motor, or continuous-load requirements. Preserve those checks at their respective circuit levels.
Sources checked
Also defined as
- The load remaining after demand factors, which sizes the service or feeder