Deterioration curve

A deterioration curve turns dated condition observations into a forecast of when pavement will reach a treatment threshold. Specify the condition measure and pavement family before reading the crossing date. For PCI, the local linear forecast is years remaining = (current PCI - threshold PCI) / annual PCI loss. A curve calibrated to visual distress does not predict load capacity.

The accelerating drop in pavement condition over time, flat at the top and steep at the bottom, that sets treatment timing

Used across 2 Anvilfield field guides, most in Paving.
Updated

Name the condition variable before fitting age

ASTM D6433-24 uses repeated PCI observations to establish the rate of pavement deterioration. A useful dataset therefore retains inspection dates and consistent section boundaries, not just the most recent index value.

ASTM D6433-24 states that PCI does not measure structural capacity and does not directly measure friction or roughness. A PCI curve predicts that visual condition index. It cannot establish an axle-load capacity or replace an IRI series simply because all three describe pavement performance.

Match the decline rate as well as the starting level

FHWA-HRT-17-104 found that bias and standard error alone were inadequate for comprehensively evaluating pavement performance predictions; the study also examined measured and predicted deterioration trends. That distinction matters when two models reproduce an inspection score but forecast different changes after it.

A section scored PCI 84 in 2022 and PCI 72 in 2026 loses 12 / 4 = 3 points per year over that interval. Continuing that rate reaches a planning threshold of 60 in (72 - 60) / 3 = four years, in 2030. A forecast using 6 points per year reaches the same threshold in 2028. These are competing slope assumptions, not two different observations of today’s pavement.

Keep treatment effects visible in the history

A resurfacing event can create a jump in the observed score. Fitting one smooth decline through observations from before and after that intervention can make the apparent age effect misleading. Retain the treatment date, affected limits and new surface age alongside the original pavement age.

Group sections by construction, loading and treatment history, then retain later inspections to test the prediction. An apparent good fit to the original points does not establish a reliable future slope. In the preservation plan, carry the threshold date with the survey date and assumed annual loss so the next inspection can update the work year.

Distinctions

Condition survey
A survey records the pavement at an observation date. A deterioration curve adds assumptions to predict unobserved dates.
Treatment benefit curve
A treatment model describes how an intervention changes expected condition or life. Its gain and subsequent decline need separate support from the untreated history.

Frequently asked questions

Can one inspection establish a deterioration rate?

One observation establishes a condition point. A rate requires comparison over time or an explicitly borrowed model. Identify the borrowed pavement family and retain the first repeat survey as a check on that assumption.