Field-cured

Field-cured specimens estimate a concrete member's strength under its construction curing conditions. For a release governed by ACI CODE-318-25, a 3,220 psi cylinder cannot be hidden inside a 3,300 psi average when the required stage strength is 3,250 psi. Each cylinder tested for that release must meet the minimum unless the licensed design professional approves otherwise. The project must identify the governing edition, specimens to test and retesting criteria.

Cylinders cured with the structure to judge in-place strength for stripping or loading

Used across 2 Anvilfield field guides, most in Concrete.
Updated

The 2025 construction-stage criterion uses every cylinder

For prestressing and removal of shoring or formwork supporting beams and slabs, ACI CODE-318-25 Section 26.12.4.1 makes the lowest cylinder strength decisive unless the licensed design professional approves another basis. ACI's January 2026 Concrete Q&A explains that the professional must also specify how many field-cured specimens to test and how later tests supersede earlier low results. The rule does not establish a complete testing schedule by itself.

With a 3,250 psi stage requirement, results of 3,220 and 3,380 psi average 3,300 psi. The minimum misses by 30 psi even though the average clears the requirement by 50 psi. Record the individual breaks, test time and approved disposition. Test the next designated specimens at the agreed interval; an old low break should not be silently dropped or treated as an indefinite prohibition on a later release.

Cylinders made on site are not automatically field-cured

ASTM C31/C31M-26b, the current field-specimen practice, assigns standard-cured specimens to acceptance and mixture quality control, while field-cured specimens serve in-place strength and construction decisions. The place where the mold was filled does not determine its curing designation. A standard-cured specimen can spend its initial curing period on the jobsite.

Label the intended use when the specimen is made. Record its storage location, protection and temperature history, especially after any move. Separate standard-cured acceptance specimens from stage-release specimens in the laboratory export; a shared sample number alone cannot distinguish their purposes on a slab project.

Temperature-match curing is a separately identified method

NRMCA's March 2026 specification guide identifies temperature-match curing as a way to reproduce the temperature measured inside a concrete member more closely. A controlled curing enclosure responds to the member's measured history. ACI's January 2026 discussion treats this as an alternative procedure whose acceptance criteria must be set by the licensed design professional, separate from ordinary field curing.

ACI's January 2026 discussion explains that cylinders and members can dissipate hydration heat differently even under similar protection. Pair the specimen history with the member location the decision concerns. A warm center, a thin edge and an exposed anchorage zone need identifiable evidence; one ambient weather reading cannot establish that all three followed the specimen's history. Use a separate method identifier for any maturity estimate included in the same release record.

Distinctions

Standard-cured acceptance test
This uses the specified average of qualifying standard-cured cylinders. Applying that average to field-cured stage-release results would omit the 2025 individual-cylinder criterion.

Frequently asked questions

Does the 2025 criterion automatically replace the rule on an older project?

Identify the edition and requirements governing the contract. ACI's January 2026 Q&A notes that the 2024 IBC references ACI 318-19; publication of ACI 318-25 alone does not rewrite the project's adopted code or specifications.

Sources checked

Also defined as

  • Datacenter: Cylinders cured alongside the structure to measure in-place strength for stripping, shoring, post-tensioning, and loading decisions

Where this shows up