Field glossary · component

Isolation valve

An isolation valve creates a service boundary, but its shutoff duty must match the condition that exists during service. Normal operation between two connected pipe flanges, operation with downstream piping removed, and hot-fluid service can have different pressure limits. Select the valve against the actual boundary condition, then document how pressure trapped inside that boundary will be identified and released.

A valve placed to take a component out of a live loop for service without draining the rest of it

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

Cold working pressure and steam pressure are separate ratings

NIBCO's TM-585-70-66 ball-valve sheet specifies 600 psi non-shock cold working pressure. NIBCO's saturated-steam rating for the TM-585-70-66 is 150 psi. Read the pressure-temperature chart and service description together when the fluid is hotter than the cold-rating condition.

NIBCO's TM-585-70-66 sheet also identifies a vented ball and an actuation mounting pad. Those features do not establish a particular actuator's closing capability. Keep the valve body, seat arrangement and any fitted actuator together in the selection record, rather than carrying over a rating from a visually similar manual valve.

Removing the downstream flange changes the question

NIBCO's large-diameter LD-1100 sheet covers 30, 36, 42 and 48 inch valves with 150 psi shutoff service and 100 psi bidirectional dead-end service without a downstream flange. NIBCO's separate 14 through 24 inch LD-1100 sheet permits 150 psi dead-end service. Size is therefore part of the rating, even within one figure number.

A 120 psi boundary on the cited 30 through 48 inch valve falls below its 150 psi shutoff rating but exceeds its 100 psi dead-end rating. An estimator planning downstream spool removal therefore needs the dead-end condition in the work scope. A normal operating pressure entry alone would hide the distinction until the pipe is ready to come apart.

The valve selection record needs the maintenance arrangement alongside the fluid and pressure. State whether downstream piping remains attached during the work so the quoted valve meets the required service condition.

A closed indication does not measure seat leakage

An actuator end switch reports the position reached by its mechanism. It does not directly measure leakage through a damaged or obstructed seat. When pressure returns to a relieved section, identify whether the source is seat leakage, another connected supply or heating of trapped liquid before declaring the boundary established.

Show drains, vents, bypasses and instrument connections on the isolation sketch. A bypass left connected can defeat an otherwise sound shutoff, while a gauge on the wrong side of the valve reports the live system rather than the isolated section. Label those measurement points by which volume they represent.

Frequently asked questions

Does every lug butterfly valve have the same dead-end rating?

No. NIBCO publishes 100 psi dead-end service for its 30 through 48 inch LD-1100 valves and 150 psi for its 14 through 24 inch versions. Match the figure number, size and downstream-flange condition to the actual service boundary.

Sources checked

Also defined as

  • Plumbing: A valve built to run fully open or fully closed, such as a ball or gate

Where this shows up

Next step: Search valve replacement bids

Back to the full field glossary