CDU

A coolant distribution unit (CDU) is selected by what its coolant circuit can deliver to the racks: heat-transfer duty, supply temperature, flow and external differential pressure. Those ratings describe the pumps and heat exchanger together; the headline kW figure does not establish usable rack capacity. The XDU450 examples below concern heat rejection to facility water, while Vertiv's CoolChip CDU 70 rejects heat to room air without a facility-water connection.

Coolant distribution unit, the pumps, heat exchanger, filtration, and controls that isolate and condition the secondary loop

Used across 13 Anvilfield field guides, most in Datacenter.
Updated

Why a CDU has more than one capacity number

Vertiv's Liebert XDU450 Application and Planning Guide lists 453 kW at a 4 C approach and a maximum 975 kW at an 8 C approach. In that guide, approach is secondary supply temperature minus entering facility-water temperature. An 8 C selection therefore permits warmer rack coolant than a 4 C selection at the same facility-water temperature; its larger capacity does not describe the tighter approach.

A 500 kW row specified at a 4 C approach exceeds the published 453 kW point by 47 kW. Quoting the 975 kW maximum does not resolve that deficit. Obtain the performance selection at the actual entering temperatures, fluid composition and flow rates, then carry that duty into the CDU commissioning load test.

Resolve the published single-pump pressure conflict

Vertiv's XDU450 planning guide revision B contains conflicting single-pump data: table 4.1 pairs 450 L/min with 2.0 bar external differential pressure, while section 3.2 pairs that flow with 1.6 bar without filtration. Resolve the selection with Vertiv's pump curve for the supplied filter arrangement before assigning the one-pump duty. Neither printed pressure alone settles that selection.

Table 4.1 separately pairs 500 L/min with 3.4 bar during dual-pump operation. That point cannot establish performance after a pump loss. External differential pressure is the budget for distribution piping, hoses, connectors and rack restrictions at the stated flow; pump discharge pressure without the return-pressure measurement does not establish that budget.

What the primary flow display actually measures

Vertiv's XDU450 Operation and Maintenance Manual states that its primary inlet meter measures total primary flow through the unit, not flow through the heat exchanger alone. The control valve divides that flow between bypass and heat exchange. Read valve demand and feedback with the primary and secondary temperatures to determine whether the exchanger receives enough flow for the duty.

Vertiv places primary flows below 11 L/min outside that sensor's displayed range. A missing low-flow value is not a quantified zero-flow measurement. For the optional primary filter, the manual sets the A29 dirty-filter alarm above 0.6 bar differential pressure, approximately 9 psi, with a default 60-second delay. Preserve the pressure trend and configured delay when explaining why a brief pressure excursion did not produce an alarm.

Distinctions

Pump redundancy
An extra pump protects against a pump loss. It does not add a second heat exchanger, controller or facility-water connection. Read the redundant component and the rated pump mode separately.
Facility-water flow
On the XDU450, the primary meter includes bypass flow, so its reading cannot be assigned to a cold-plate branch. The secondary branch record needs its own measured flow and pressure difference.

Frequently asked questions

Does a 450 kW CDU always remove 450 kW?

Its published duty is tied to specified temperatures, fluids and hydraulic conditions. Use the selection point that matches the project rather than treating the model designation as a constant output.

Why are chips hot when CDU supply temperature is correct?

The XDU450's primary flow display includes bypass and cannot clear a restricted cold-plate branch. Record flow and pressure loss on the affected secondary branch, then use the loop commissioning checks to restore that branch's documented design duty.

Sources checked

Also defined as

  • Coolant distribution unit, the pumps, controls, and heat exchanger that can isolate a clean door loop from facility water
  • Coolant distribution unit, isolates the clean rack loop from facility water and sets its flow, pressure, and temperature