Field glossary · material

PG25

PG25 is an inhibited propylene-glycol/water coolant near 25% glycol by volume; OCP's September 2026 guidance spans 24.5% to 27.5% for new fluid and 24% to 29% in use. The product's own limit can be tighter: Dow sets 25% by volume as the minimum for DOWFROST LC. Record concentration, inhibitor chemistry and pH separately, because a percentage inside OCP's general band does not establish acceptance for a particular formulation.

A roughly 25 percent propylene-glycol-and-water coolant with an inhibitor package, a common secondary-loop fluid

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

New fluid targets and product operating minimums

OCP lists a typical fresh-PG25 freeze point of -13°C to -10°C in its PG25 guidelines, Revision 2.0, Version 1.0.0, dated September 15, 2026. Table 1 describes new fluid; Table 14 covers fluid already in use. Apply the purchased product's acceptance specification to deliveries.

OCP's concentration bands describe general new-fluid properties and in-use guidance, rather than a purchase tolerance for every product. A 24.5% result fits OCP's new-fluid band but falls below Dow's 25% operating minimum for DOWFROST LC. Put the full product designation, lot and supplier limit in the direct-to-chip coolant schedule and commissioning record.

OCP's Tables 1 and 14 also distinguish pH by inhibitor technology and service condition. Organic acid technology, abbreviated OAT, has a different pH band from conventional inhibitors; applying the conventional lower limit to every PG25 sample can reject an acceptable OAT formulation. The table below summarizes OCP's guidance, with the purchased fluid's specification controlling its acceptance.

OCP pH guidanceNew fluid, Table 1In-use fluid, Table 14
Conventional inhibitor technology8.0 to 10.5, non-OAT8.0 to 10.5, IAT
Organic acid technology (OAT)7.0 to 10.56.5 to 9.5

Read the refractometer on the fluid supplier's scale

OCP's refractometer guidance uses the fluid manufacturer's published relationship because additives change refractive index. A generic glycol scale is not automatically the product's concentration scale. Record the instrument reading, temperature or compensation setting, and the fluid-specific conversion used.

Dow's 2022 DOWFROST LC Engineering and Operating Guide, Table 5, associates 25.0% glycol by weight with 24.4% by volume. Reporting either result as an unqualified '25%' loses the basis needed to interpret the sample.

What 100 L of retained flush water does to PG25

A 1,000 L final loop volume contains 100 L of retained water and receives 900 L of 25% premix. On a nominal volume balance, the premix contributes 900 × 0.25 = 225 L of glycol, so the completed charge is 225/1,000 = 22.5%. The drums were correct; dilution occurred inside the loop.

That is a 2.5 percentage-point drop from the premix concentration, or a 10% relative reduction. Dow's operating guide sets 25% by volume as the minimum for its LC coolant because lower concentrations support biological degradation. The calculated charge is below both that product's minimum and OCP's 24% lower in-use guideline. Sample the circulated blend and obtain the supplier's correction quantity using the measured concentration and final loop volume; another drum of the same premix does not supply the concentration deficit by itself.

Why a cold charge pumps differently

Dow's 2022 guide lists DOWFROST LC 25 dynamic viscosity as 2.48 mPa·s at 20°C and 1.10 mPa·s at 50°C. The colder fluid is about 2.25 times as viscous, calculated from those values. That ratio is not automatically the pump-head multiplier: pressure loss also depends on flow regime and component geometry.

A cold-start flow result and a warm operating result therefore need their fluid temperatures attached. Keep concentration and temperature with the TCS flow record, then compare the selected coolant properties with the pump and component curves. An unchanged valve position does not establish an unchanged hydraulic operating point.

Distinctions

Glycol percentage versus inhibitor condition
The glycol reading addresses mixture concentration. The inhibitor condition needs its own chemistry result; the water-treatment guide connects those measurements to the operating program.

Frequently asked questions

Is PG25 the same as 25% glycol by weight?

The designation used here is by volume. Preserve the mass or volume basis on purchase documents and laboratory reports; the Dow conversion above shows why the numbers differ.

Does a good glycol reading prove the coolant is healthy?

Dow separately identifies pH 8.0 to 10.5 as acceptable for DOWFROST LC. A sample at 25% glycol with pH 7.5 meets that product's concentration minimum while failing its pH range. Keep both results, plus appearance and inhibitor-condition findings, in the same fluid report.

Sources checked

Also defined as

  • A water-glycol coolant, roughly 75 percent water to 25 percent propylene glycol