W-class
An ASHRAE W-class declares liquid-cooled IT equipment performance across a facility-water supply range. W32, for example, requires full performance through 32°C under non-failure conditions. It is not a 32°C cold-plate supply guarantee: a CDU with a 5 K approach would deliver 37°C on its technology side at that rating point. Match the facility-water class, CDU approach, and equipment inlet requirement before selecting the plant temperature.
ASHRAE TC 9.9 facility water supply temperature class, W17 through W+, the number being the max supply temperature in degrees Celsius
Read the numbered ceiling and the W+ rating
ASHRAE's fifth-edition reference card, revised and expanded in 2024, uses the numbered designations W17, W27, W32, W40, and W45 for facility-water ceilings of 17°C, 27°C, 32°C, 40°C, and 45°C. All begin at 2°C. The class declaration covers full equipment performance across its range under non-failure conditions, so a favorable test point below the ceiling does not establish the whole rating.
ASHRAE designates W+ for operation above 45°C without supplying a single numbered upper endpoint. Obtain that endpoint from the equipment's declared rating and carry it into the facility-water schedule. Writing W+ alone leaves the plant designer without the upper supply temperature needed to select heat-rejection equipment.
Budget the CDU approach before choosing the water class
ASHRAE's Water-Cooled Servers white paper distinguishes facility water from the technology cooling system and describes the CDU heat exchanger separating their water-quality domains. Those are separate rating locations. State the class at the facility-water interface and the cold-plate supply requirement at the technology-loop interface.
For a cold-plate circuit requiring no more than 35°C supply and a CDU selected for a 5 K approach at the design load and flows, the facility-water ceiling is 35 - 5 = 30°C. Supplying 32°C facility water at that same approach produces 37°C technology-loop supply, exceeding the 35°C requirement by 2°C.
Attach the CDU rating point, heat load, and flows on both sides to the temperature budget. A proposal offering a 3 K approach at that same load would allow 32°C facility water for the 35°C technology-loop limit. Compare those rating points in the direct-to-chip equipment schedule, rather than comparing W32 labels alone.
A class minimum is not a condensation-control setpoint
ASHRAE's 2019 Water-Cooled Servers white paper describes a CDU maintaining technology-loop supply at least 2°C above room dew point to prevent condensation while allowing for sensor uncertainty. At an 18°C room dew point, that margin sets a 20°C technology-loop supply floor. The water class's 2°C facility-side minimum cannot serve as the exposed rack tubing's condensation-control setpoint.
Record dew point, technology-loop supply, and facility-water supply as separate trend points during loop commissioning. In the 35°C maximum-supply example, a 20°C condensation floor leaves a 20°C to 35°C technology-loop operating window. Recalculate the floor when room moisture changes; the W-class name stays the same.
Separate temperature capability from failure performance
The non-failure condition in the class definition matters at turnover. A W-class declaration does not establish what happens after a CDU pump stops, facility flow disappears, or a control valve loses power. Put the required response to those events in the equipment sequence and acceptance record, with the actual cooling load identified.
Likewise, specify heat removal at the declared inlet conditions. A temperature label supplies a boundary for rating equipment; the capacity selection still needs heat load and flow. Keep those quantities visible when comparing CDU proposals that advertise the same W-class.
Distinctions
- Coolant specification
- Water quality, glycol concentration, material compatibility, and filtration belong to the coolant requirements. A temperature class does not establish them.
- Heat-rejection design temperature
- Outdoor design conditions and plant selection establish the attainable facility-water supply. The equipment class states the range that supply must support.
Frequently asked questions
Does W-class refer to supply or return water?
The designation uses facility-water supply temperature. Identify the physical rating connection so it is not confused with CDU technology-loop supply or a return measurement.
Does W+ mean there is no upper water-temperature limit?
The class name leaves the upper endpoint unstated. The equipment's declared maximum remains a required selection input.
Sources checked
Also defined as
- ASHRAE TC 9.9 facility water temperature class (W17 to W+), naming the maximum supply fluid temperature in C
- ASHRAE liquid-cooling water classes describing supply temperature ranges