Field glossary · property
TDP
TDP means thermal design power: the component rating a cooling designer uses before the server's operating demand has been measured. It is expressed in watts, with the product's workload and power-control conditions attached. CPU base power, turbo limits and a GPU's configurable maximum TDP are different inputs. Preserve those labels when estimating a server heat budget; adding chip ratings still leaves memory, fans, storage and conversion losses to account for.
Thermal design power, the watts a chip is rated to dissipate, which the cooling has to remove
Intel base power and turbo power describe different duties
Intel's 12th Generation Core processor datasheet, Revision 011 dated May 2025, defines Processor Base Power as a time-averaged dissipation validated at base frequency under an Intel workload and specified junction-temperature conditions. Intel identifies that quantity with TDP in this processor family. The workload and temperature conditions are part of the definition, so the number is not a direct reading of an installed server.
The same Intel datasheet permits short-duration operation above Processor Base Power during Turbo Boost, subject to platform power and thermal controls. A heatsink selected around sustained dissipation and an electrical supply selected around the platform's power requirements therefore need different information. Do not replace either specification with an average workload reading.
The H100 model name alone does not identify its watts
NVIDIA lists configurable maximum TDP up to 700 W for H100 SXM and 350 to 400 W for H100 NVL. These are different form factors and product configurations. A worksheet that says only H100 loses a difference large enough to change a server cooling allocation.
Eight H100 SXM GPUs at a 700 W design allowance contribute 5.6 kW of GPU thermal budget. Eight H100 NVL GPUs at 400 W contribute 3.2 kW. Both subtotals exclude CPU, memory, networking, storage, fans and power-conversion losses. Keep the GPU subtotal labeled before carrying the completed server requirement into the AI rack-readiness calculation.
Reconcile configured limits with measured board power
NVIDIA's nvidia-smi documentation defines average board power over the preceding second and instantaneous board power as the latest measured reading. Its one-second board average is supported on Ampere devices except GA100, and on newer devices. Record the GPU model and the returned field name with the watts so different monitoring exports remain comparable.
NVIDIA also distinguishes the power limit requested by software from the limit currently enforced by power management. Keep both when investigating an unexpected cooling or performance result: changing a requested ceiling is not evidence that the board drew that power. Board readings and module readings have different boundaries; NVIDIA's module reading includes the GPU, a supported CPU and other module components.
Carry the measurement boundary into the direct-to-chip cooling worksheet. A GPU-board power reading and a whole-module reading cannot be substituted for each other when allocating heat to cooling circuits. Use the server manufacturer's component-to-circuit allocation with the measured power fields, and retain the residual air-cooling requirement alongside the liquid-cooling duty.
Distinctions
- Power supply nameplate
- The supply rating describes output capability. It is not the server's input draw, and redundant supply nameplates are not additive estimates of server consumption.
- GPU utilization
- GPU utilization describes activity over a sampling period. It is not a percentage multiplier that converts maximum TDP directly into measured power or heat.
Frequently asked questions
Does a 700 W GPU continuously release 700 W?
That figure is a product design rating. Actual power depends on workload and active limits. Keep rated allowance, configured ceiling and measured consumption in separate columns so the cooling design and operating trend retain their meaning.