Field glossary · data center
TCS
A TCS (technology cooling system) sample represents rack-side coolant; at a CDU heat exchanger, a bottle drawn from the facility-water side cannot establish its glycol concentration. OCP's September 2026 glycol guideline lists 24.5% to 27.5% propylene glycol by volume as typical for fresh PG25 formulations. That concentration does not identify the inhibitor package or approved materials. Interpret TCS results against the named fluid: inhibited glycol can meet its product requirements at conductivities far above a deionized flush-water target.
Technology cooling system, the clean conditioned secondary loop from the CDU to the cold plates, held to the strict chemistry
Locate the sample valve before assigning a TCS result
Mark the sample valve on the piping drawing and list the rack manifolds it represents. At a liquid-to-liquid CDU, label the two heat-exchanger sides with their loop IDs and fluid products before collecting samples. The laboratory report should identify the side sampled, not merely the skid number; different water-quality specifications can meet at the same cabinet.
What does PG25 identify, and what is missing?
PG25 describes nominal propylene-glycol concentration, not a complete chemical specification. The purchasing record also needs the coolant product, inhibitor formulation, approved wetted materials and batch identification. Put those identifiers on each laboratory request and cross-reference the treatment record maintained under the liquid-cooling chemistry guide.
OCP's September 15, 2026 glycol guideline, Revision 2.0, lists 24.5% to 27.5% propylene glycol by volume as the typical range for fresh PG25 formulations. It also directs refractometer interpretation to the fluid manufacturer's correlation because additives change the relationship between refractive index and concentration. A generic glycol scale can therefore disagree with the product-specific result.
Dow's 2022 DOWFROST LC Engineering and Operating Guide lists a typical freezing point of -10°C for LC 25, equal to 14°F. That property belongs to the formulated product. A freeze-point reading alone does not establish that the inhibitor package or materials compatibility is acceptable.
Why a low conductivity target can be wrong
Dow's 2022 DOWFROST LC Engineering and Operating Guide describes typical electrical conductivity above 2,500 µS/cm because the fluid contains corrosion inhibitors, buffers and other additives. This is electrical conductivity, distinct from thermal conductivity, which describes heat conduction. Comparing that circulating coolant with a deionized flush-water limit would misclassify the product.
Separate the incoming-water sample, the unused premix sample and the circulating-fluid sample in the laboratory request. Include temperature and the fluid name with conductivity results. A change after a service visit is evidence to reconcile with the added fluid and its analysis; it is not a reason to strip out useful additives to chase the lowest number.
Calculate dilution from retained flush water
An 800 L circuit retaining 80 L of flush water and receiving 720 L of 25% premix contains 180 L of propylene glycol. On that volume basis, the final concentration is 180 / 800 = 22.5%. The delivery container was correctly labeled PG25, but the filled system is below the fresh-fluid range in OCP's 2026 guidance.
Use the fluid remaining inside hoses, manifolds and equipment in the fill balance. Verify the mixed result at representative circulating sample points after filling. OCP's 2026 guideline specifically identifies residual commissioning water as a cause of over-dilution and recommends retaining a sample from each delivered batch for at least six months. A retained sample helps distinguish an incoming-fluid issue from dilution introduced on site.
Use the coolant's heat capacity when measuring TCS duty
Dow's DOWFROST LC guide gives LC 25 a specific heat of 3.94 kJ/(kg·K) at 50°C. For mass flow of 2.5 kg/s and a 10 K coolant rise, the calculated heat transport is 2.5 × 3.94 × 10 = 98.5 kW, using that fluid property at the mean operating temperature. Log the supply and return temperatures with the flow reading.
A volume-flow meter requires the matching fluid density to convert its reading into mass flow. Keep the fluid-property basis in the calculation sheet so a later concentration change does not leave the displayed thermal duty using the old properties. Compare this measured liquid duty with the equipment's required liquid heat removal, rather than assuming it equals all electrical input to the rack.
Distinctions
- FWS sample
- A facility-water sample at a CDU characterizes the building supply on that side of the heat exchanger. It cannot establish the glycol concentration or inhibitor condition in the separate TCS circuit. Record the loop and sample-valve identifiers even when both bottles come from the same skid.
Frequently asked questions
Does a clear coolant sample prove the TCS is clean?
Visual clarity cannot establish glycol concentration, inhibitor condition or dissolved contamination. Keep the appearance observation with the formulation-specific analytical results, rather than using it as the release criterion by itself.
Sources checked
Also defined as
- Technology cooling system, the clean secondary coolant loop that feeds the cold plates
- Technology cooling system; the coolant circuit serving the IT equipment.