ANVILFIELD Try FieldOS

Field glossary · component

Lap splice

A lap splice consumes reinforcing steel twice over the overlap while extending the member only once. Force passes through the surrounding concrete between the overlapped bars, so acceptance needs both the specified lap and space for sound concrete around the doubled steel. Keep the design schedule, measured overlap and tightest cover or clearance together in the inspection record.

Two bars overlapped to transfer force, length set by the class and the development length

Used across 2 Anvilfield field guides, most in Concrete.
Updated

Lap schedules belong to a specific design basis

Record the contract's bar grade, coating, size and splice class before selecting a lap from a schedule. ACI publishes CODE-318-25 for building design, while the Caltrans dimensions below come from its June 2025 bridge-construction manual. The publication year identifies the reference; the project documents identify which schedule governs the placed bars.

Caltrans' June 2025 Reinforced Concrete Construction Manual gives a minimum 45-bar-diameter lap for uncoated ASTM A615 Grade 60 bars No. 8 and smaller under its cited contract specification. Caltrans specifies a minimum 60-bar-diameter lap for uncoated ASTM A615 Grade 60 bars No. 9, No. 10 and No. 11 under the same contract specification. These are Caltrans bridge requirements, not a generic replacement for a building's designed tension-lap schedule.

Inspect the whole doubled-bar zone

The Caltrans manual requires its lapped bars to be in contact and securely tied, with at least 2 inches clear to adjacent reinforcement or splices. Measure the clear space from the outside of the spliced pair, not from the original single-bar centerline.

At a corner, a bundle or a crossing with transverse steel, draw the actual bar envelopes. Moving one splice sideways to regain cover can consume the neighboring placement passage. Inspect the tightest location in the whole overlap, including ties and hooks, rather than taking one generous measurement at its open end.

The designed lap length must survive assembly: record the shortest cover and tightest adjacent-bar clearance along that overlap. A placing sketch that shows the correct lap but omits the doubled-bar envelope leaves the congestion unresolved.

Overlaps consume stock without extending the run

Separate installed bar length from the continuous distance it covers. Each splice counts twice within the overlapped zone but only once along the member. A takeoff based solely on the finished wall or footing length omits the extra stock that every lap consumes.

Keep splice stations in the takeoff rather than adding an unexplained percentage. Stock lengths, corners and changes in bar size determine the number of overlaps. That record lets the estimator distinguish a design change in lap length from a field decision to use shorter stock.

For a straight run of n equal stock bars of length S joined by equal laps L, covered length = nS - (n - 1)L. Use matching units and count corner returns separately. Solving against the required run length exposes whether another stock bar is needed when a lap dimension increases.

Distinctions

Development length
Anchors the force in a bar into concrete. A lap-splice schedule accounts for transferring force between overlapped bars in the specified splice condition.
Mechanical splice
Transfers force through a qualified coupling assembly. Its installation and acceptance criteria differ from measuring a conventional overlap.

Field example

Four 20 foot bars joined with three specified 30 inch laps cover 80 - 7.5 = 72.5 feet of continuous run. They consume 80 feet of purchased bar. Counting only the 72.5 foot run understates installed steel by 7.5 feet before bends or cutting losses are considered.

Frequently asked questions

Should a 45-diameter calculation be rounded down?

No. A No. 5 bar's 0.625 inch diameter gives 28.125 inches at 45 diameters, and Caltrans Table 4-2 reports 28.13 inches. A practical 28.25 inch placing dimension exceeds that particular minimum; 28 inches falls short. Use the actual scheduled class, coating and grade before applying the arithmetic.

Sources checked

Also defined as

  • Two bars overlapped so force transfers between them through the surrounding concrete

Where this shows up

Related guides

Next step: Find reinforcing work

Back to the full field glossary