Minimum approach distance (MAD)
Minimum approach distance (MAD) sets an electrical separation for a specified worker and operation. OSHA's crane Table A assigns 15 ft to a confirmed 115 kV AC line, measured to the nearest part of the equipment, load, or rigging. The 20 ft planning screen determines whether crane encroachment controls are triggered for lines up to 350 kV. An unqualified person's clearance and a qualified lineworker's approach distance use separate OSHA provisions.
The required clearance from an energized line, set by voltage; assume the line is live
Which OSHA distance applies to this work?
OSHA 1910.333(c)(3)(i) requires an unqualified person in an elevated position to keep both the person and the longest conductive object at least 10 ft from unguarded overhead lines at 50 kV to ground or below. Above 50 kV to ground, that rule adds 4 in for each additional 10 kV. Its voltage-to-ground wording matters when choosing the input.
Qualified electric-power work follows a separate framework. Under OSHA 1910.269(l)(3), the employer establishes approach distances using the applicable AC or DC calculation requirements. General aerial-lift work does not acquire those qualified-worker distances merely because the platform has insulating material.
OSHA 1910.269 also distinguishes qualified employees from line-clearance tree trimmers with the training specified for their duties. A tree-removal plan needs the actual work classification, not an assumption that every arborist is qualified for electric-power work.
The crane's 20 ft screen is a planning trigger
OSHA 1926.1408(a)(2) uses a 20 ft work-zone screen for construction-crane operations near power lines up to 350 kV. Evaluate equipment, load line, load, and rigging through their maximum permitted reach. A possible encroachment triggers the rule's deenergizing-and-grounding, fixed-clearance, or voltage-based Table A options and their applicable controls.
OSHA Table A assigns 15 ft clearance above 50 kV through 200 kV nominal AC. Its voltage bands use phase-to-phase system voltage, unlike the voltage-to-ground basis in the unqualified-person rule quoted above. Confirm the utility's voltage designation before selecting a row.
OSHA 1926.1409(a) replaces the 20 ft references with 50 ft for lines above 350 kV through 1000 kV. Applying the lower-voltage planning screen to those lines would understate the required assessment distance. Under 1926.1408(e), lines remain presumed energized until the utility owner/operator confirms continuing deenergization and visible grounding at the worksite.
Include the load, not just the boom tip
For a crane operating near a confirmed 115 kV line under Table A, a hook path 16 ft from the line appears to clear the 15 ft requirement. A load projecting 3 ft toward the line reduces the closest separation to 13 ft. The planned movement fails on the load geometry even though the hook remains outside the limit.
Plot the closest part through the complete movement, including rigging and foreseeable movement of the load. The crane and signaling guide supplies the lifting context; the applicable electrical rule supplies the boundary.
Distinctions
- Arc-flash boundary
- An arc-flash boundary concerns thermal exposure from an arc event. It does not establish overhead-line clearance.
- Working radius
- The machine's reach helps define its possible exposure to a line; it is not the electrical separation itself.
Frequently asked questions
Can I measure clearance from the utility pole?
Measure separation to the energized conductor or part. Pole position does not establish conductor position, sag, or movement.
Does a spotter allow a smaller approach distance?
A spotter is an encroachment control. The required clearance still comes from the applicable rule and selected work method; using the Table A option does not by itself authorize work inside its distance.
Sources checked
Also defined as
- Landscaping: The closest a worker, tool, or conductive object may come to an energized line, set by Z133 and OSHA by voltage