ANVILFIELD Try FieldOS

Electrical

Crane, rigging, and signaling safety field guide

What safe lifting is, the four killers, and how to keep the crane clear of the lines, within the chart, the rigging rated, and everyone out from under the load.

Crane SafetyRiggingOSHA Subpart CCSling AngleSignal Person

Direct answer

Safe crane lifting is a qualified team working a load within the crane's load chart, with rated rigging hooked to a balanced load and the area under and around it cleared. The crane kills by contacting power lines, tipping or overloading, dropping a load, and striking people in the swing. OSHA Subpart CC, 1926.251, and ASME B30 govern.

Key takeaways

  • OSHA Table A power-line clearance is 10 ft up to 50 kV, rising with voltage; default to 20 ft when the voltage is unknown.
  • Crane lifts kill four ways: power-line contact, tip-over or overload, dropped loads from bad rigging, and struck-by from the load or swing.
  • Sling leg tension equals 1 divided by the sine of the angle from horizontal: 1.41 at 45 degrees, 2.0 at 30 degrees, the practical floor.
  • Never exceed the load chart; capacity drops as radius grows, and many charts subtract hook, rigging, and jib weight.
  • Nobody stands under a suspended load or inside the barricaded swing radius of the counterweight.

Safe lifting, and why it is a whole-site risk

Safe crane lifting is a qualified team picking a load that stays inside the crane's rated capacity, with rigging rated for the weight and the angle, hooked to a load that hangs in balance, and the ground under and around it cleared of people. Get those pieces right and the lift is routine. Miss one and a multi-thousand-pound load is loose over a jobsite.

Cranes move the heavy gear electrical and mechanical crews cannot set by hand: rooftop units, switchgear lineups, dry-type and pad-mount transformers, generators, structural steel, long conduit racks. The weight is the point and the weight is the hazard. A 6,000 lb rooftop unit does not care that the lift looked fine on paper.

The deaths cluster in four places, and only one of them is the operator's seat. Power-line contact, tip-over or overload, a dropped load from bad rigging, and people struck by the load or the swing. Three of those four kill people on the ground more often than the person running the crane. That is the part that gets lost. Crane work is not a one-operator risk. It is a whole-site risk, and the people most exposed are often the ones who had nothing to do with planning the pick.

This guide covers the pieces that keep a lift safe. Two adjacent hazards have their own guides: working from a boom or bucket is in the aerial lift and MEWP guide, and de-energizing the gear you are setting belongs to the lockout/tagout guide.

The four ways a crane lift kills, and who it kills

Power-line contact is the one that kills most consistently. The boom or the load line touches an energized line, or comes close enough to arc, and the whole machine and its rigging go live. The operator inside the cab is often the one who survives, because the cab and the tires give a path that does not run through a body. The people on the ground touching the load, the tag line, or the crane are the ones who die. That is the cruel signature of electrocution on a crane site: the person who made the mistake walks away and the person holding the tag line does not.

Tip-over and overload are the same failure from two directions. Either the load is heavier or further out than the chart allows, or the ground under an outrigger gives way, and the crane goes over. A tipping crane throws the load and can crush the cab and anyone in the fall path.

Dropped loads come from rigging that failed: a sling cut on a sharp edge, a shackle pinned wrong, a hitch that slipped, a load that was never balanced. The load comes down on whoever is under it.

Struck-by covers the load swinging into someone, a load that spins on a single pick point, and the counterweight of a rotating crane catching a worker against a wall or a truck. The swing radius behind the crane kills people who never looked up because they were not part of the lift.

How far must a crane stay from power lines?

Treat every overhead line as energized and stay outside the clearance in OSHA's Table A. For lines up to 50 kV the minimum is 10 ft. The clearance grows with voltage: 15 ft over 50 up to 200 kV, 20 ft over 200 up to 350 kV, 25 ft over 350 up to 500 kV, 35 ft over 500 up to 750 kV, and 45 ft over 750 up to 1,000 kV. Above 1,000 kV the utility or a qualified engineer sets the distance. Those figures are in OSHA 1926.1408; confirm them against the current rule and the line's actual voltage.

When the voltage is unknown, the rule defaults to a 20 ft clearance for lines up to 350 kV, more above that. Do not guess the voltage low to shrink the number. If nobody can tell you what the line carries, you assume the larger distance.

The strongest control is to get the utility to de-energize and visibly ground the line at the worksite. When that is not possible, OSHA requires a planning meeting and at least one added measure: a dedicated spotter whose only job is watching clearance and who is in continuous contact with the operator, a proximity alarm, a range-control or range-limit device, or an insulating link. A spotter eyeballing a gap from a bad angle is the weak version of this, which is why de-energizing wins when you can get it.

Power-line contact is the number one crane killer. The clearance is not a target you trade against the schedule. Cross-link the lockout/tagout guide for de-energizing the line and proving it dead, and confirm the distances and the encroachment options against OSHA Subpart CC and the utility before the crane rolls.

What is a load chart?

A load chart is the manufacturer's table of how much the crane can lift at a given radius and boom configuration. It is specific to that machine, and it is the law of the lift. Radius is the horizontal distance from the crane's center of rotation to the load, and it is the input that punishes you: the further out the load sits, the less the crane can pick. A crane that lifts 30,000 lb at a short radius might be rated for a few thousand at full reach. The chart de-rates as you boom out.

The chart accounts for boom length, boom angle, whether outriggers are set and how far, the counterweight, and the direction of the pick relative to the carrier. Capacity over the rear, over the side, and over the front are not the same number. Many charts also subtract the weight of the hook block, the headache ball, the rigging, and any jib from the rated figure, so the net capacity for your actual load is less than the headline number. Read the deductions, not just the line.

Do not exceed the chart, and do not round in your favor. Working a crane past its rated capacity is how it tips, and it is a violation under OSHA Subpart CC. The chart is the manufacturer's; the radius and configuration are yours to measure honestly, and ASME B30.5 and OSHA back the rule that the chart governs. When the load and the radius put you near the chart's limit, you are in critical-lift territory, covered below.

Firm ground, outriggers, and mats

A crane is only as stable as what is under it. Outriggers or crawler tracks carry the whole weight of the machine plus the load into a small footprint, and the ground has to take that bearing pressure without giving. Set the crane on soft fill, a buried trench, a saturated subgrade, or an undocumented utility vault and the outrigger punches through. That is a tip-over in slow motion.

Extend the outriggers per the configuration the load chart assumes, usually fully, and set them on mats or cribbing sized to spread the load over enough area. The pad alone is rarely enough. The mat turns a high point load into a pressure the soil can carry. On questionable ground, the bearing pressure under the outrigger float against the allowable pressure of the soil is an engineering question, not a guess, and a critical or near-capacity lift may need that checked.

Level the crane before the pick. An out-of-level crane loses capacity and swings the load out to a larger effective radius as it rotates, which the chart did not account for. OSHA 1926.1402 requires the supporting ground to be firm, drained, and graded enough to handle the equipment, and the controlling entity has to tell the crane crew about known hazards like backfilled areas and underground structures. Confirm the setup against the load chart's outrigger configuration and the manufacturer before the load leaves the ground.

What is a qualified rigger?

A qualified rigger is a person who, by training, experience, or both, can select and inspect rigging and hook up a load safely for the lift at hand, and whom the employer has designated as qualified for that work. OSHA does not hand out a rigger card; the employer determines and documents the qualification, and ASME B30 describes the rigger's responsibilities. OSHA does require a qualified rigger specifically when workers are in the fall zone during assembly, disassembly, or hooking and unhooking a load.

The lift is a team, and OSHA Subpart CC names the roles. The operator must be trained, certified, and evaluated for the type and capacity of crane under 1926.1427. The signal person has to meet the qualification requirements of 1926.1428 for each signaling method used, shown by a documented assessment. On many lifts these are three different people, and the work does not start until each one is qualified for their part.

Do not let title creep do the qualifying. A good operator is not automatically a qualified rigger, and a rigger is not automatically a signal person. Each role has its own competency and its own way to get someone killed. Confirm the qualifications against OSHA Subpart CC and the employer's program before the lift.

Slings: wire rope, chain, and synthetic

Slings come in three families, and each fails differently. Wire rope is the workhorse, strong and abrasion-resistant, and it tells you it is failing through broken wires, kinks, birdcaging, and corrosion. Alloy chain is rugged and takes heat and sharp edges better than the others, and it fails at cracked, stretched, gouged, or nicked links. Synthetic web and round slings are light, easy on a finished load, and grip well, but they cut, abrade, and break down in UV and chemicals, and a cut you can hide under a thumb can drop the load.

Every sling has to be rated for the weight and for the way it is rigged. The capacity printed on the tag is not a single number that follows the sling around; it changes with the hitch and the angle, covered in the next two sections. Match the sling to the load, the edges, and the environment, not to whatever was on the truck.

Inspect rigging before every use and pull anything questionable out of service. OSHA 1926.251 requires damaged or defective slings to be removed immediately, puts a sling inspection on a competent person each shift the sling is used, and sets a periodic inspection at intervals no greater than 12 months for chain. A sling with no legible tag is out, because a sling with no rated capacity is a guess. ASME B30.9 covers sling inspection and removal criteria in detail; follow it and the manufacturer.

Why does sling angle matter?

Sling angle matters because the flatter the sling, the harder it pulls, and the tension can climb past the sling's rating while the load on the hook never changes. Measure the angle from horizontal. At 90 degrees, a straight vertical pull, each leg carries its share of the load and nothing more. As the legs spread and the angle drops, each leg has to pull harder to make the same vertical lift, because part of its force is now pulling sideways against the other leg.

The math is simple and worth carrying in your head. The tension multiplier is 1 divided by the sine of the angle. At 60 degrees the factor is about 1.15. At 45 degrees it is about 1.41. At 30 degrees it is 2.0: each leg sees double the load it would in a straight pull. Below 30 degrees the tension runs away fast, which is why rigging practice treats 30 degrees from horizontal as the practical floor and below it as not recommended.

The trap is that the load did not get heavier, so nothing warns you. A two-leg bridle that is fine at 60 degrees can overload its slings at 20 degrees on the same load. Keep the angle up with longer slings or a spreader bar, read the sling's rated capacity at the angle you are actually rigging, and confirm against the sling tag and ASME B30.9.

Sling angle from horizontalTension factor (1 / sine)What it means per leg
90 degrees (vertical)1.00Each leg carries its share, no more
60 degrees1.15About 15 percent over the share
45 degrees1.41About 41 percent over the share
30 degrees2.00Double the share, the practical floor
Below 30 degreesOver 2.0, climbing fastNot recommended

Working load limit and the sling tag

Working load limit (WLL) is the maximum load a sling, shackle, or fitting is rated to carry as marked by the manufacturer, and it already has the design factor built in. It is not the breaking strength. The breaking strength is where the part fails; the WLL is a fraction of that, with a margin commonly around 5 to 1 for slings, so do not treat the WLL as a number you can shade.

The rated capacity has to be legible on the sling and on every fitting in the assembly. OSHA 1926.251 and ASME B30.9 prohibit loading a sling past the WLL shown on its permanently affixed identification. If the tag is gone or unreadable, the sling is out of service, because nobody can prove what it is rated for.

The WLL on the tag is the starting point, not the final number. It is the vertical rating, and you de-rate it for the hitch and the sling angle. A 10,000 lb vertical-rated sling used in a choker is worth less, and used at a flat angle in a bridle it is worth less again. Calculate the actual rigging capacity from the tag, the hitch, and the angle together, and verify against the manufacturer.

Hitches and edge protection

The way a sling wraps the load, the hitch, changes its capacity. A vertical hitch, a straight pull from the hook to a single attachment, gives the sling its full rated capacity. A choker hitch, where the sling passes through its own eye and cinches on the load, de-rates the capacity, commonly to around 75 to 80 percent of the vertical rating, because the bend at the choke point concentrates stress. A basket hitch, where the sling cradles the load with both ends on the hook, can carry up to twice the vertical rating when the legs are truly vertical, but that doubling falls off as the legs angle in, by the same sine factor that governs sling angle.

The exact de-rating figures live on the sling tag and in the manufacturer's tables and ASME B30.9, and they differ between wire rope, chain, and synthetic. Use the published number for the sling in your hands, not a remembered rule.

Protect the sling at every edge. A synthetic sling laid over a sharp steel corner can be cut through under tension with no warning, and even wire rope and chain lose strength bending tight over an edge. Use softeners, corner protectors, or wear pads anywhere the sling crosses an edge. Skip the edge protection on a sharp-cornered load and you are rigging a dropped load.

Center of gravity, balance, and tag lines

Rig the load so the hook sits over its center of gravity. A load picked off-center tips the moment it leaves the ground, slides in the slings, and can shock-load one leg as the load swings to find its balance. Estimate where the weight actually is, not where the geometric middle looks like it is. A piece of switchgear or a transformer carries its mass low and to one side, and the lugs or lift points are placed for that. Use the rigging points the manufacturer provided, because they were located for the real center of gravity.

A balanced load lifts level and hangs still. If the load cocks or drifts as it comes off the ground, set it back down and re-rig. Do not try to fix balance in the air.

Control the load's rotation and drift with tag lines. A tag line is a rope on the load handled by a worker who stands clear of the load and outside the fall zone, used to keep the load from spinning and to guide it without anyone putting hands on a suspended load. On a tall or wind-catching load like a rooftop unit, two tag lines give real control. They let the crew steer the load while staying out from under it, which is the whole point.

Who gives the crane signals?

One designated signal person directs the crane, and the operator follows only that person. The exception is the stop signal, which the operator obeys from anyone. That pairing is the rule: a single voice running the lift so signals do not conflict, and a universal brake any worker can pull when they see something the signal person cannot.

Standard hand signals are spelled out by ASME and posted on the job. OSHA Subpart CC requires hand signals to follow the standard method, with a chart of the signals posted at the site. Hand signals work when the signal person and operator can see each other clearly. When they cannot, or the lift is complex, switch to radio with a clear protocol: the signal person names the crane, gives the command, and the operator acknowledges, with continuous transmission on a blind pick so a dropped signal means stop.

A signal is required whenever the load or any part of the crane is out of the operator's full view, or when the operator is moving the load near a hazard. The signal person stands where they can see the load and the landing zone and where the operator can see them, and they have no other job during the lift. Confirm the signaling method and the qualifications against OSHA Subpart CC.

Who can stand under a suspended load?

Nobody stands under a suspended load. That is the bluntest rule on the site and the most broken. A load can drop from a rigging failure, a hydraulic failure, or a two-block, and the only reliable protection is that no person is in the space it would fall into. Keep the area under the load and along its travel path clear, and keep workers from passing under it.

The swing radius is the second zone people forget. As the crane rotates, the counterweight and the rear of the machine swing through an arc, and a worker between the counterweight and a wall, a truck, or a stack of material gets crushed. OSHA requires the swing radius to be barricaded so workers cannot enter the area where they could be struck or pinned by the rotating superstructure.

Barricade the zones, do not just brief them. Tape, cones, and a person watching are how you keep the load path and the swing radius clear, because the worker walking through with their head down was never in the lift meeting. Hoisting people on the crane, instead of keeping people clear of it, is a separate and tightly restricted operation with its own OSHA requirements, and it is not a shortcut around access. Clear the zone and keep it clear for the whole lift.

The lift plan

A lift plan is the pick worked out on paper before the crane shows up. At a minimum it states the load weight, the lift radius and the boom configuration, the crane's rated capacity at that radius from the load chart, the rigging selected with its capacity at the planned hitch and angle, the ground and outrigger setup, the power lines and other hazards in reach, and the signaling method. When the planned load and rigging are inside the chart with margin and the hazards are addressed, you have a plan. When any line is a guess, you have a hope.

The weight is where plans fail. Use the actual weight from the equipment submittal or the nameplate, add the rigging and the spreader, and do not eyeball a transformer. A wrong weight feeds every other number, and it feeds them in the dangerous direction, because the load is heavier than you planned, not lighter.

Walk the plan with the crew before the lift: the operator, the rigger, the signal person, and the landing crew. The brief is where the signal person learns the path, the landing crew learns where the load lands, and someone catches the power line nobody put on the plan. A lift plan filed and never read is paperwork. A lift plan walked on site is a safer lift.

Critical lifts

A critical lift is a pick that carries more consequence or less margin than a routine one, and it gets extra planning and usually an engineered plan and a higher sign-off. OSHA Subpart CC does not define the term with one bright line, so the employer's program and the crane manufacturer set the trigger, but the common ones are a load near the crane's rated capacity, a lift using more than one crane, hoisting personnel, a load that cannot be replaced or that would be catastrophic if dropped, and lifts over occupied space or live equipment.

Near-capacity is the most common trigger. As the load approaches the chart, every error that was survivable on a light pick becomes the tip-over, so many programs flag a lift at a set percentage of the chart, often around 75 percent, for critical-lift planning.

A multi-crane lift adds the problem that the load shares between cranes and shifts as they move, so one crane can become overloaded while the other unloads. Those lifts need an engineered plan, defined load shares, and tight coordination. Treat the trigger and the planning level as set by your program, the manufacturer, and the applicable standard, and when in doubt, plan it as critical.

Inspecting the crane and the rigging

Cranes get inspected on a schedule and rigging gets inspected every time it is used. A competent person inspects the crane before each shift for the items that fail between days: the wire rope, hooks and latches, hydraulics and leaks, tires or tracks, the outriggers, controls, and safety devices. OSHA 1926.1412 lays out the shift inspection, a monthly documented inspection, and an annual inspection by a qualified person, with the annual records kept.

Rigging is the per-use inspection. Before each lift the rigger looks over every sling, shackle, hook, and fitting for the damage that family of rigging shows, and pulls anything questionable. OSHA 1926.251 puts the each-shift sling inspection on a competent person and requires defective rigging removed from service on the spot. There is no fixing a damaged sling in the field. It comes off the job.

The crane's safety devices and operational aids are part of the inspection, not optional extras. The load moment indicator, anti-two-block, level indicator, and boom-angle indicator are there to keep the lift inside the chart, and a lift with a defeated or broken safety device is a different and worse lift. Follow the manufacturer and OSHA Subpart CC for what gets checked and how often.

Wind, weather, and the load's sail area

Wind is a crane hazard that scales with the load, not just the crane. A flat-sided load like a rooftop unit, a panel, or a section of ductwork is a sail, and a wind speed that is nothing to a compact steel beam can push that load out of control and add side force the chart never assumed. The manufacturer's load chart and operation manual set the maximum wind speed for the crane and often de-rate capacity as wind rises, and large or high-sail loads have their own lower limits.

Know the wind speed, do not feel it. An anemometer at the boom tip or on the site, plus the day's forecast, tells you when to stop, because wind aloft at the boom tip is stronger than the breeze at grade. When the wind crosses the limit for the crane or the load, the lift waits.

Lightning stops crane work outright. A boom in the air is a target, and the safe move is to land the load, get clear, and wait out the standard delay after the last strike before resuming. Treat the wind limits as set by the manufacturer for that crane and that load, and the lightning policy as set by the site safety plan.

Lifting an RTU or switchgear to a roof

Setting a rooftop unit or a piece of switchgear on a roof stacks several of the hazards in this guide into one pick. The radius is long, because the crane has to reach over the building to land the load past the parapet, and a long radius is where the chart de-rates hardest. Check the capacity at the radius over the roof, not at the crane, and remember the load travels out to that radius as it swings into place.

The load is usually a sail. Rooftop units and switchgear are big flat boxes, so wind control and tag lines matter more here than on a compact load. Run two tag lines on anything tall, and keep the landing crew on the roof clear until the load is over the opening and coming down slow.

The landing crew is exposed in a way ground crews are not. They work near a roof edge under a suspended load, so they need fall protection suited to the edge, a clean hand-off of the signal, and a rule that nobody reaches for the load until it is low and under control. Plan the rooftop pick as its own lift plan, cross-check that the roof structure can take the load and the crew, and confirm the setup against the crane chart and the building documents.

Crane assembly and disassembly

Assembling and disassembling a crane is one of the most dangerous parts of the whole operation, and OSHA Subpart CC puts it under a qualified assembly/disassembly director. The A/D director understands the manufacturer's procedures, knows the hazards of the work, and is responsible for the crew doing the build or teardown safely. Booms have dropped during assembly and killed the people pinning them, so this is not a step to run by feel.

The A/D director addresses the specific hazards of the process: the assembly area ground conditions, the danger zones around the boom and the suspended boom sections, the pin and connection points, and the line of sight and signals for the crew. The work follows the crane manufacturer's procedures, and where those are not available, procedures from a qualified engineer or another reliable source.

This is also where power lines bite during setup, not just during the lift. The clearance rules apply to assembly and disassembly under their own section of Subpart CC, so the same Table A thinking covers raising the boom near a line. Run the build and the teardown under the A/D director, by the manufacturer's procedures, and confirm against OSHA Subpart CC.

Records: certs, inspections, and the lift plan

The crane lift generates a paper trail, and the paper is what shows the lift was planned and the equipment was fit. Keep the operator's certification for the type and capacity of crane, the signal person's documented qualification, and the employer's designation of the qualified rigger. Keep the crane's annual and monthly inspection records and the shift inspection log. Keep the rigging inspection records and the sling capacity tags. Keep the lift plan, and for a critical lift the engineered plan and the sign-offs.

This is where a field tool earns its place. Capturing the pre-lift inspection, the lift plan, the load weight and chart check, the rigging selected, and the sign-off in something like FieldOS, with photos of the rigging and the setup, puts the record where it can be found instead of in a truck cab. When an incident or an inspection asks whether the lift was done right, the answer is the record, and a record nobody can produce is the same as no record.

Tie the documentation to the lift it covers. An inspection log that cannot be matched to the crane on site, or a lift plan with no weight on it, is paperwork that fails the moment it is tested.

ElementRequirementNote
Operator certificationCertified for crane type and capacityOSHA 1926.1427
Signal person qualificationDocumented for each signaling methodOSHA 1926.1428
Qualified rigger designationEmployer designates and documentsRequired in the fall zone
Crane inspectionsShift, monthly, annual on fileOSHA 1926.1412
Rigging inspection and tagsEach use, defective removedOSHA 1926.251, ASME B30.9
Lift planWeight, radius, chart, rigging, hazardsEngineered for critical lifts
Load weight basisSubmittal or nameplate, plus riggingWrong weight drives every error

Common mistakes

  • Contacting an overhead power line, or shrinking the clearance because the schedule is tight.
  • Overloading the crane past the load chart, or reading the chart at the crane instead of at the load radius.
  • Setting up on soft or undocumented ground, or running outriggers short and without mats.
  • Rigging with a damaged sling, the wrong sling for the load, or a sling tag that cannot be read.
  • Pulling the sling angle too flat so leg tension climbs past the rating while the load looks unchanged.
  • Letting people stand under the load or inside the swing radius of the counterweight.
  • Running the lift with no lift plan, no single signal person, or no posted signal protocol.
  • Picking a load off its center of gravity, or trying to fix the balance in the air.

Field checklist

0 of 10 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

Standards and references

OSHA 1926 Subpart CC is the construction crane standard, and it carries the rules that get people killed when they are ignored. Operator certification and evaluation are at 1926.1427, signal person qualifications at 1926.1428, and the qualified rigger requirement appears for assembly, disassembly, and work in the fall zone. Power-line clearance and Table A live at 1926.1408 for lines up to 350 kV, with 1926.1407 for assembly and disassembly near lines and 1926.1409 for lines over 350 kV. Ground conditions are at 1926.1402, inspections at 1926.1412, keeping clear of the load and the swing radius in the work-area-control sections, and assembly and disassembly under the A/D director.

Rigging is governed by OSHA 1926.251, which sets working-load-limit, marking, inspection, and removal-from-service rules for wire rope, alloy chain, and synthetic slings. The ASME B30 family is the consensus standard underneath much of this: B30.5 for mobile and locomotive cranes, B30.9 for slings, B30.10 for hooks, B30.20 and B30.26 for below-the-hook devices and rigging hardware, and the standard crane hand signals. The crane manufacturer's load chart and operation manual control the machine's capacity, wind limits, and setup, and they govern where they are stricter.

Section numbers and clearance figures shift between code cycles and editions, so confirm them against the current OSHA Subpart CC, the cited ASME B30 volume, the manufacturer's documents, and the authority having jurisdiction before you rely on them on a lift plan. When two sources disagree, the more stringent one and the manufacturer's instructions control.

Units, terms, and conversions

Crane and rigging work runs on a small vocabulary that carries real weight, so the terms are worth pinning down.

Capacity and weights are in pounds or tons in US practice and kilograms or tonnes in metric documents, and a US ton is 2,000 lb. Sling and fitting ratings show as working load limit (WLL), also called rated capacity. Radius is in feet or meters from the center of rotation. Sling angle is measured from horizontal in degrees. Wind speed is in miles per hour or meters per second.

WLL (working load limit)
The maximum load a sling or fitting is rated to carry, marked by the manufacturer, with the design factor already included
Radius
The horizontal distance from the crane's center of rotation to the load; rated capacity drops as the radius grows
Sling angle
The angle of a sling leg from horizontal; lower angles raise leg tension by 1 divided by the sine of the angle
Hitch
How the sling attaches to the load (vertical, choker, or basket), each with a different rated capacity
Swing radius
The arc the crane's counterweight and rear sweep as it rotates, a struck-by and crushing zone
Two-block
When the hook block runs up into the boom tip, which can part the line and drop the load
Critical lift
A lift with extra consequence or less margin, near capacity, multi-crane, or over occupied space, needing added planning
A/D director
The qualified person who directs crane assembly and disassembly under OSHA Subpart CC

Related tools

Calculators and readiness checks for this work

Compare your options

FAQ

What is a qualified rigger?

A qualified rigger is a person the employer has designated who can select, inspect, and hook up rigging safely through training or experience. OSHA does not issue a rigger card; the employer determines and documents it, and ASME B30 describes the role. OSHA requires one when workers are in the fall zone during hooking or assembly.

How far must a crane stay from power lines?

Stay outside OSHA's Table A clearance: 10 ft up to 50 kV, growing with voltage to 20 ft over 200 up to 350 kV and more above that. When the voltage is unknown, default to 20 ft for lines up to 350 kV. The strongest control is to de-energize and visibly ground the line.

What is a load chart?

A load chart is the crane manufacturer's table of how much that specific machine can lift at a given radius and boom setup. Capacity drops as the load moves out to a larger radius, and the chart often subtracts the hook, rigging, and jib weight. Never exceed it. Read the deductions, not just the headline.

Why does sling angle matter?

Sling angle, measured from horizontal, sets how hard each leg pulls. The tension multiplier is 1 divided by the sine of the angle: about 1.4 at 45 degrees and 2.0 at 30 degrees, where each leg sees double. The load never got heavier, so nothing warns you. Keep the angle above 30 degrees.

How much does a choker hitch reduce sling capacity?

A choker hitch commonly de-rates a sling to around 75 to 80 percent of its vertical rated capacity, because the bend at the choke concentrates stress. A vertical hitch gives full capacity, and a basket hitch can reach twice it when the legs are vertical. Use the exact figure on the sling tag and in ASME B30.9.

What is a critical lift?

A critical lift carries more consequence or less margin than a routine pick: a load near the crane's rated capacity, a multi-crane lift, hoisting personnel, or a lift over occupied space. OSHA does not set one bright line, so the employer's program and the manufacturer define the trigger and the extra planning, often an engineered plan.

Who can stand under a suspended load?

Nobody. A suspended load can drop from a rigging or hydraulic failure, and the only reliable protection is keeping every person out of the space it would fall into. Keep the load path and the swing radius of the counterweight barricaded and clear, and never route workers under a raised load.

How often must crane rigging be inspected?

Rigging gets a visual inspection by a competent person before every use, with damaged or defective slings removed from service on the spot under OSHA 1926.251. Chain slings also get a periodic inspection at intervals no greater than 12 months. A sling with no legible capacity tag is out of service.

Do you need a lift plan for every crane lift?

A lift plan should cover any lift that is not trivially routine, and it states the load weight, the radius and boom setup, the chart capacity, the rigging and its capacity at the hitch and angle, the ground setup, the hazards, and the signals. Critical lifts need an engineered plan and a higher sign-off.

What wind speed is too high for a crane lift?

The crane manufacturer's load chart and manual set the maximum wind speed, and they often de-rate capacity as wind rises. Large flat loads like rooftop units act as sails and have lower limits. Measure wind at the boom tip, not at grade, and stop for lightning. Treat the limits as the manufacturer sets them.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.