MOP
In critical-facility work, a MOP (method of procedure) is the controlled instruction specifying a particular intervention from a defined plant state. The usable document is the approved revision linked to the equipment being worked on. Uptime Institute recommends annual review plus review after infrastructure or setpoint changes. A refrigeration MOP marking instead denotes maximum operating pressure, so a pressure value and a procedure identifier refer to entirely different things.
Method of Procedure; the approved step-by-step script, with risk and rollback, for changing a critical component's state
A procedure revision needs a review clock
Uptime Institute recommends reviewing MOPs at least annually and again after infrastructure changes, including setpoint changes. Record the review even when the technical content remains unchanged. The approval date, last review date and next review date serve different purposes; an old approval stamp cannot establish that someone reviewed the present configuration.
An annual review due November 5, 2026 cannot cover a setpoint change implemented in September unless that change was included in the review. Track the infrastructure change, the affected procedure revision and its approval as linked records. A next-review date by itself does not show that the instruction matches today's plant.
Reuse the instruction without losing the equipment boundary
Uptime describes a document arrangement in which equipment-specific SOPs invoke a shared MOP. Use that arrangement to separate the reusable task method from unit-specific references. When several air-handler procedures invoke one filter-change instruction, identify the shared document by controlled revision rather than copying its text into every parent procedure.
Maintain a list of parent procedures that invoke each shared instruction. After a revision, review those references together with the MOP, SOP and EOP library. An updated task sheet and a parent SOP still pointing to its superseded revision leave two competing instructions for the same work.
Prove usability at the point of work
Uptime Institute recommends rehearsing approved MOPs through dry runs and walk-throughs before execution. During the rehearsal, reconcile the written equipment identifier with its physical label and the referenced drawing. Note any label hidden by an access door or any identifier duplicated on an adjacent lineup; these are document usability defects that a desk review can miss.
Capture a rehearsal correction against the controlled document, then issue the corrected revision through the same review route. A handwritten improvement retained only on a training copy creates a second instruction set. The operator's completed record should identify the exact revision executed so later findings lead back to the instruction actually used.
MOP pressure on an expansion valve
Danfoss's Fitters Notes describe MOP charge as a limited bulb charge that restricts rising evaporator or suction pressure. In that description, the valve starts closing about 0.3 to 0.4 bar below the MOP point and reaches closed at that point. Those values describe the valve's pressure-limiting behavior, not the approved operating steps for servicing it.
Read the refrigerant, valve designation and MOP pressure together when interpreting a valve label. A work order containing both a procedural MOP reference and a valve MOP value needs separate fields for the document revision and pressure specification. The refrigerant metering guide explains the valve application.
Distinctions
- Review versus technical revision
- An annual review can confirm the existing instruction without changing its steps. A technical revision changes the controlled instruction; its approval must also resolve any parent procedure still referencing the earlier version.
Frequently asked questions
Must every annual review create a new technical procedure?
A review can confirm that the procedure remains valid. Preserve who reviewed it, when, and the configuration considered; issue a revision when the instruction changes.
What does an MOP number on a work order identify?
It should resolve to a particular controlled procedure and revision. A title shared by several versions leaves the executed instruction uncertain.
Sources checked
Also defined as
- HVAC: Maximum operating pressure; a gas-charged bulb that caps suction pressure to protect the compressor on pull-down
- Method of procedure, the step-by-step script for one specific planned work task