Flash gas
Unwanted flash gas at a TXV inlet signals that the liquid feed has lost its local subcooling margin. Danfoss calls for checking subcooling at both the condenser outlet and valve inlet before adding charge. Its TU/TC valve data describe 2 to 5 K at the condenser outlet as adequate in most cases, depending on system design. That selection guidance does not replace the equipment's charging target or prove that the margin survives the liquid-line run.
Liquid that boils to vapor in the liquid line when pressure drops below its saturation point, starving the metering device
Follow the subcooling margin to the valve inlet
Subcooling at the condenser outlet is a starting margin. Pressure loss lowers the local saturation temperature, and heat gain raises the liquid temperature. Both consume the difference that keeps refrigerant liquid before it reaches the metering device. A single outlet reading cannot show how much margin survives the entire run.
Danfoss's TXV troubleshooting guidance calls for checking subcooling at both the condenser outlet and TXV inlet before adding refrigerant when upstream flashing is suspected. Pair each temperature with pressure at the relevant location; using condenser pressure with a distant liquid-line temperature conceals the intervening pressure loss.
For a refrigerant blend, determine liquid subcooling from the bubble-point data for that refrigerant. Record that bubble-point basis with the pressure and temperature at the metering-device inlet, especially when another technician will repeat the test.
A five-degree margin can disappear along the run
Start with a 40°C local saturation temperature and 35°C liquid temperature: 5 K of subcooling. If pressure loss lowers saturation temperature by 3 K while the liquid gains 2 K from its surroundings, both temperatures reach 37°C. The subcooling margin has reached zero; further pressure reduction or heat gain causes flashing.
Danfoss's March 2025 TU/TC expansion-valve data sheet describes 2 to 5 K of condenser-outlet subcooling as adequate in most cases, with the required amount dependent on system design. That valve-selection guidance is not a replacement for an equipment manufacturer's charging target. A long rise or a hot liquid-line route consumes a different margin from a short, cool run.
Calculate the expected pressure loss and elevation effect for the installed line, then compare local measurements with that expectation. Increasing charge does not remove an undersized passage or restore a crushed tube's area.
A restriction can mimic a shortage of refrigerant
Danfoss identifies a clogged filter drier or damaged liquid-line tubing as a cause of flash gas even when refrigerant charge is correct. Finding vapor upstream of the valve therefore establishes a feed-condition problem, not its root cause.
Compare the condition before and after the suspected restriction while the system is operating steadily. A loss concentrated across one component directs attention there; a margin consumed progressively along the run directs attention to line sizing, elevation and heat exposure. Preserve those locations with the readings so the diagnosis can be checked after the repair.
Distinctions
- Cavitation
- Vapor formation and collapse associated with a liquid-pressure reduction and recovery, commonly discussed at pumps. Flash gas feeding an expansion valve is a refrigerant supply condition.
Frequently asked questions
Are sight-glass bubbles enough reason to add charge?
No. Establish the operating condition and compare subcooling along the liquid line. Restrictions and pressure losses can produce bubbles with the correct refrigerant inventory.
Will a larger TXV cure upstream flashing?
A larger valve does not restore the liquid subcooling lost upstream. Correct the feed condition before selecting a different valve capacity.
Sources checked
Also defined as
- Vapor formed when liquid drops in pressure or picks up heat before the device, which starves the device of liquid
- Vapor flashing in the liquid line, seen as bubbles in the sight glass