SPD means surge protective device. Compare its installation Type, voltage ratings and tested discharge current separately: a Type 1 rating concerns placement, while a 20 kA nominal discharge-current rating concerns repeated surge exposure. Mersen describes that nominal-current evaluation as 15 test impulses, not a 15-event service life. A large advertised peak-current number cannot replace those application details or establish protection of a particular connected load.

Surge protection device, which clamps the transient on building wiring that the LPS itself does not address

Used across 3 Anvilfield field guides, most in Electrical.
Updated

Which SPD Type fits the proposed connection?

UL 1449, fifth edition published January 8, 2021 and revised October 21, 2025, distinguishes Type 1 service-side applications from Type 2 load-side applications. Type is an installation category, not a descending quality grade. Identify whether a submittal describes a complete listed device or a component assembly before approving the connection arrangement.

UL's public scope reaches 1,000 V on 50 or 60 Hz circuits and 1,500 V DC in PV applications. Select the actual product's system voltage and circuit configuration within that scope. A catalog reference to UL 1449 does not make an AC device suitable for a PV circuit.

UL 1449 categoryProcurement distinction
Type 1Application on the service overcurrent device's line side or load side; includes specified PV applications
Type 2Permanent application downstream of the service overcurrent device
Type 5Suppressor component, such as an MOV, requiring evaluation in its end-use assembly

Nominal discharge current describes a repeatable test

Mersen's Surge Protection Note 6 explains nominal discharge current using 15 impulses in three groups of five, with an 8/20-microsecond current waveform. The note discusses UL 1449's fourth edition; UL's publisher page identifies the fifth edition as current. The test description makes the meaning of a nominal-current claim concrete: repeated impulses at a stated level, under a defined sequence.

That sequence is not a promise that a field device has exactly 15 surges of remaining life. Actual exposure is not a counter of identical laboratory events. Likewise, a peak-current marketing figure cannot substitute for a stated nominal discharge-current rating. Put the test designation beside the number when comparing submittals, rather than sorting products by the largest kA value printed on the cover.

Put the rating name beside every voltage or kA number

UL's surge-device guide distinguishes VPR, a voltage-protection rating, from MCOV, the continuous voltage permitted across the rated terminals. Neither is the device's short-circuit current rating. Compare the protection mode as well as the value: a line-to-neutral number does not describe an unrelated line-to-ground connection.

Keep a submittal row for system voltage and configuration, Type, protection modes, VPR, MCOV, nominal discharge current and SCCR. The SPD ratings guide connects those fields to selection. An estimate containing only 'panel SPD, 100 kA' leaves both the meaning of that current and the application ratings unresolved.

A product evaluation does not certify an entire protective chain

UL 1449's public scope excludes the interconnection of multiple field-installed SPDs from its coverage. Listing individual devices therefore does not, by itself, establish the performance of their installed combination. A service device and a downstream device still need application information for the arrangement being proposed.

UL 1449 also leaves adequacy for a particular connected load outside its product evaluation. Pair the chosen device's ratings with the equipment's protection objective and retain the proposed service-to-panel arrangement. Use the installation guide for the connection record rather than treating individual product listings as evidence for the complete chain.

Distinctions

Type 5 component versus replacement module
A Type 5 suppressor is a discrete component category. A replacement cartridge belongs to its specified complete SPD assembly; similarity in shape does not establish interchangeability.

Frequently asked questions

Is the largest kA number the best way to compare two SPDs?

Start by identifying what each kA number rates. Nominal discharge current, a peak surge claim and SCCR describe different conditions. Compare devices for the same system, protection modes and rating definitions before ranking their current values.

Sources checked

Also defined as

  • Datacenter: Surge protective device, which clamps transient overvoltage and diverts surge current to ground
  • Surge protective device, the unit that clamps voltage transients and diverts the surge to ground