SPF

SPF is spray polyurethane foam; a roofing submittal identifies the closed-cell formulation and the coating that completes its weather-exposed system. The two roofing products compared here publish densities of 2.8 and 3.04 lb/ft³ and aged one-inch R-values of 5.7 and 6.93. Those differences affect insulation and weight calculations. Select the named product before setting pass thickness, cooling time between passes, or the deadline for coating.

Spray polyurethane foam, a sprayed monolithic low-slope roof that insulates and waterproofs, protected by a coating

Used across 2 Anvilfield field guides, most in Roofing.
Updated

Compare the formulation behind the density label

SWD's August 2023 QUIK-SHIELD 155-3.0 data sheet lists nominal core density of 2.8 lb/ft³, compressive strength of 50 psi, and aged R-value of 5.7 at one inch. The product's '3.0' name and its published nominal core density therefore serve different purposes on a receiving or inspection record.

Elastochem's Insulthane 300R data sheet, revision 2, lists core density of 3.04 lb/ft³, compressive strength of 53 psi, and 90-day-aged R-value of 6.93 at one inch. Compare the stated aging basis as well as the number when selecting a product for the SPF roof assembly.

ASTM C1029-25 covers spray-applied rigid cellular polyurethane thermal insulation, classifies four material types, and addresses properties including thermal resistance, strength, moisture behavior, aging, and closed-cell content. A material specification provides the property framework; the selected roof system supplies the application details.

Cooling between passes and coating within 24 hours

Elastochem's Insulthane 300R revision 2 sets a normal pass range of 0.5 to 1.5 inches and requires the foam core to cool below 100°F before another pass. It expressly permits passes below 0.5 inch for drainage tapering and an acceptable surface finish. Complete the specified foam thickness in an area the same day, then apply protective coating that day or within 24 hours of foam application.

Elastochem also specifies relative humidity below 85 percent and a substrate more than 5°F above the dew point for Insulthane 300R. With a 55°F dew point, a 60°F substrate is exactly at that difference and does not meet the instruction to be above it. Record substrate temperature and dew point together, along with the pass and coating times.

SWD's QUIK-SHIELD instructions also give a 0.5-to-1.5-inch pass range, with exceptions at pass lines, penetrations, and tapering. A total depth reading alone cannot establish whether the foam was built within its processing limits. The installation record needs the product and pass information behind the final thickness.

Use the roofing system overview for system selection and the coating thickness guide for the separate coating quantity. Keeping the foam and coating records connected makes the permitted exposure interval visible.

Calculate foam weight from cured density

Using Elastochem's published 3.04 lb/ft³ core density, a uniform 3-inch layer weighs 3.04 × 3/12 = 0.76 lb/ft² before coating and other system materials. Across 20,000 square feet, that foam volume is 5,000 cubic feet and its calculated weight is 15,200 pounds.

A tapered installation needs its measured or designed average foam volume for the weight calculation. Retain minimum thickness separately for insulation and coverage requirements. The deepest core does not establish the average installed volume, and the product's compressive-strength value does not establish the supporting roof's load capacity.

Frequently asked questions

Does a higher density automatically give a higher R-value?

Read the named product's aged thermal data. Density describes cured mass per volume, while the insulation value also depends on formulation and aging. Use both properties as separate entries in the submittal comparison.

Which document revision should the crew record?

Keep the application instructions and technical data sheet supplied for the installed formulation with its batch identification. The Insulthane comparison above uses revision 2; its published properties differ from older product literature.

Sources checked

Also defined as

  • Spray polyurethane foam, the closed-cell foam body of the roof, sprayed from two components

Where this shows up

Related guides

Next step: Plan foam roof outreach