Field glossary · material
BUR
BUR, or built-up roofing, is a bituminous roof membrane whose reinforcing-ply count controls the sheet takeoff. A 5,000-square-foot four-ply field contains 20,000 square feet of reinforcing coverage within one roof covering. Johns Manville's GlasPly IV roll lists 500 square feet net, a sheet-area figure. Record the bitumen, felt, ply count and surfacing separately; Type IV is the felt classification, not proof of four installed plies.
Built-up roofing, the multi-ply tar-and-gravel low-slope system of alternating bitumen and reinforcement
Type IV felt is a material classification
ASTM D2178/D2178M-15a(2021) covers asphalt-impregnated glass felts for roofing and waterproofing. Johns Manville identifies GlasPly IV as a Type IV felt; that designation does not establish how many plies the contractor installed. Read the product designation and the assembly's ply schedule as separate entries on the submittal.
Johns Manville's GlasPly IV data sheet reports breaking strengths at 73.4°F of 64 lbf/in along the roll and 59 lbf/in across it, against a listed minimum of 44 lbf/in in each direction. These are sheet properties. They do not describe the bond between installed plies. The BUR installation guide explains how those sheets become a membrane.
Read roll coverage before counting finished squares
Johns Manville lists a GlasPly IV roll as 36 inches wide by 177 feet long, with 531 square feet gross and 500 square feet net coverage. Those are roll-area figures. Use the selected assembly's exposure and end-lap details to calculate finished roof coverage.
A 5,000-square-foot field with four reinforcing plies contains 20,000 square feet of ply coverage. Dividing by the published 500-square-foot net roll area gives 40 roll equivalents for an initial material allowance. The order still needs the assembly's starter strips, ends, cuts and waste, plus any separately specified base or cap sheet. This calculation converts sheet inventory into a finished-area takeoff without confusing a four-ply membrane with four successive roof coverings.
A switch to cold adhesive changes the felt selection
Johns Manville's Asphalt-Applied and Cold Application Built-Up Roofing Application Guide prohibits GlasPly IV and GlasPly Premier in its BUR Adhesive systems. Section 9.6 recommends fully coated, nonporous ply and base felts and also permits Ventsulation Felt as a base felt. Keep that base-felt allowance separate from the prohibition on the two porous ply products.
Put the proposed adhesive and each felt product on the substitution request. A change from hot asphalt to cold adhesive needs a compatible felt schedule; retaining the original roll designation because its ASTM type matches does not establish that compatibility.
Separate the gravel load from the complete roof load
At Johns Manville's gravel-surfacing rate of 400 pounds per 100 square feet, a 5,000-square-foot field requires 20,000 pounds, or 4 pounds per square foot, of gravel alone.
The calculation describes the surfacing component. Bitumen, felts, insulation, cover boards, retained water and earlier roof coverings add their own weight. For a tear-off or recover decision, record those components individually instead of assigning the gravel rate to the entire roof stack.
Distinctions
- Graveled single-ply roof
- Stone above a single-ply membrane belongs to a different assembly from aggregate embedded in BUR surfacing. Identify the membrane beneath the stone before assigning a repair material or surfacing quantity.
Frequently asked questions
Does Type IV on the felt wrapper prove a four-ply roof?
It identifies the supplied felt. Establish installed ply count from the assembly record and observed buildup; retain the wrapper information as evidence of material identity.
Sources checked
Also defined as
- Built-up roof, a multi-ply low-slope membrane of felt and bitumen with a surfacing