Tabulated data

Tabulated data is the engineering basis for selecting an excavation protective system, including the conditions that make its ratings usable. OSHA 29 CFR 1926.650 requires approval by a registered professional engineer. The term includes data for sloping and benching as well as manufactured shields and shoring. At equipment handoff, match the model, components, soil assumptions, and loading notes to the complete document before accepting a depth rating.

The manufacturer's depth ratings and limits for a shield or shoring system

Used across 2 Anvilfield field guides, most in Plumbing.
Updated

What belongs with a trench shield rating?

Under OSHA 29 CFR 1926.652(c)(3), other tabulated data must identify selection parameters, limits of use, and the explanatory information needed to choose the protective system. A chart with only a model name and a maximum depth omits part of that decision. Soil classification, shield dimensions, spreaders, surcharge assumptions, and configuration notes belong together in the selection record.

Efficiency Production's trench-shield assembly notes exclude surcharge loads from the published depth and psf ratings. A truck beside the cut therefore introduces a loading question that the printed depth alone does not answer. Put the equipment position and imposed load on the excavation sketch reviewed with the trench safety guide.

Who can approve a change to the manufacturer's data?

OSHA 29 CFR 1926.652(c)(2)(ii) permits deviation from manufacturer specifications, recommendations, or limitations only after the manufacturer supplies specific written approval. A rental counter conversation does not provide that written approval. Keep the approved change with the exact document and equipment configuration it modifies.

The separate design route in Section 1926.652(c)(4) requires a registered professional engineer's written design identifying the materials, configuration, and approving engineer. Record which route governs the installation. A project design and an approved deviation from a manufacturer's system carry different document trails.

Spreader width is only one pulling-eye trigger

Efficiency Production requires pulling eyes when spreaders exceed 72 inches wide or when soil pressure is severe enough to deflect a spreader. An 8 ft spreader measures 96 inches, exceeding the width trigger by 24 inches. A narrower spreader still needs pulling eyes when the deflection condition exists.

Read those movement instructions with the manufacturer's other conditions on the same sheet:

  • Use Efficiency spreaders and pins or their equal; the sheet makes its tabulated-data validity conditional on that hardware.
  • Have the competent person inspect the shield, spreaders, and pins before each use.
  • Visible shield damage or repairs without registered-professional-engineer documentation and certification invalidate the stated psf rating.

Where the written information must be kept

OSHA 29 CFR 1926.652(c)(2)(iii) requires the manufacturer's instructions and any written deviation approval at the site while the protective system is being constructed. The other-tabulated-data route, Section 1926.652(c)(3)(iii), also requires a copy naming its approving registered professional engineer during construction. Afterward, either set of records can be held offsite but must remain available to OSHA on request.

A scaffold chart has a different design basis: OSHA 1926.451(a)(6) requires a qualified person to design the scaffold, with construction and loading following that design. Attach the chart to the actual bay, platform, and bracing arrangement in the supported scaffold review. An excavation engineer's approval does not establish a scaffold configuration's capacity.

Distinctions

Sales specification
A product brochure describes a family of equipment; tabulated data establishes the approved selection and use conditions for the protective system.

Frequently asked questions

Does a phone call authorize a different spreader arrangement?

The manufacturer-deviation route requires specific written approval. Keep that approval with the arrangement and tabulated data it covers.

Is the depth rating enough to allow equipment beside the trench?

Read the surcharge assumptions. The cited Efficiency Production sheet excludes surcharge from its depth and pressure ratings.

Sources checked