Competent person

A competent person combines hazard-recognition capability with employer-granted authority to correct the hazards covered by the assignment. A scaffold staffing plan shows the distinction: OSHA assigns its design to a qualified person and its inspection before each shift to a competent person. One worker may fill both roles, but the assignment must establish both capabilities and the authority needed for corrective action.

Someone able to identify scaffold hazards and with authority to take prompt corrective action, including tagging it out

Used across 6 Anvilfield field guides, most in Roofing.
Updated

Three OSHA roles that a staffing plan must separate

Under 29 CFR 1926.32(f), a competent person must recognize existing and predictable hazards and have authority to eliminate them promptly. A specialist who can only send an advisory report has not been given the second part of that role. The employer's assignment must make corrective action possible while the work is underway.

OSHA's definition in 1926.32(m) allows qualified-person status through a recognized degree, certificate, or professional standing, or through extensive knowledge, training, and experience demonstrating the ability to solve relevant problems. Section 1926.32(d) separately defines an authorized person by employer assignment or approval for particular duties or locations. Authorization alone establishes neither of the other roles.

Scaffolds show why design and inspection are separate

OSHA 1926.451(a)(6) assigns scaffold design to a qualified person. Under OSHA 1926.451(f)(3), a competent person checks scaffolds for visible defects before every shift and following events capable of compromising structural integrity. These duties can fall to the same individual only when that individual meets both sets of qualifications.

OSHA 1926.451(f)(7) places scaffold erection, moving, dismantling, and alteration under a competent person's supervision and direction, with that person qualified in the particular work. This is an additional duty to distinguish from the design requirement in 1926.451(a)(6). Identify the design basis and the alteration supervisor in the supported-scaffold work plan.

Make corrective authority usable at the workface

A subcontractor's inspector finds a damaged scaffold component while the general contractor controls access to the work area. The assignment needs a practical means to prevent use and obtain correction, not just a promise to discuss the finding at the next meeting. Identify who can restrict access, arrange replacement, and release the equipment after correction.

Use a designation record that identifies the standard, inspection duty, relevant experience, correction authority, and person covering an absence. Keep it beside the scaffold design and shift inspection record. Those documents answer different questions: who established the arrangement, who checked its present condition, and who could act on a defect.

Distinctions

Training certificate
A certificate can support the training part of an assignment. Add evidence of relevant hazard recognition and the actual employer grant of corrective authority; the certificate alone does not establish those two facts.
Safety manager
An organizational job title can include many duties. The competent-person role comes from the applicable rule and the person's capability and authority for that work.

Frequently asked questions

Can the competent person also be the qualified person?

Yes, when the individual satisfies both roles for the particular work. Record the design and inspection responsibilities separately so neither disappears into a general title.

Does OSHA require one universal competent-person card?

The construction definition establishes capability and authority, not a universal card. Task-specific standards determine the duties for which that person is responsible.

Sources checked

Also defined as

  • Electrical: Per OSHA 1926.32(f), someone able to identify hazards and authorized to take prompt corrective action, including removing items from service
  • Concrete: The designated person who can identify silica hazards and has authority to correct them, and who implements the written plan

Where this shows up