GFCI / GFI
GFI is jobsite shorthand for GFCI, ground-fault circuit interrupter; it does not name a different protection class. For construction work, OSHA's cited provision addresses 120 V single-phase 15 A and 20 A receptacles outside the permanent wiring, including extension-cord outlets supplied from permanent receptacles. Identify the employer's GFCI or assured-grounding-program method and the outlets covered. A note saying GFI checked does not record that scope.
Ground-fault circuit interrupter, the protection that trips on fault leakage current to protect personnel
Construction extensions fed by permanent receptacles
OSHA's October 29, 2008 Federal Register clarification states that an extension cord set plugged into a permanent 120 V, 15 A or 20 A receptacle during construction requires GFCI protection unless the employer uses an assured equipment grounding conductor program. The permanent wall outlet does not make the extension's receptacle part of the building wiring.
Trace the source, extension, and point of use on the protection record. Identify the approved upstream or portable device that covers that path. The temporary power guide covers the distribution layout and equipment selection.
Read all conditions in the small-generator exception
OSHA 29 CFR 1926.404(b)(1)(ii) exempts the receptacles of a portable or vehicle-mounted generator rated no more than 5 kW only when its output is two-wire, single-phase and the circuit conductors are insulated from the frame and all other grounded surfaces. Generator size alone does not satisfy that exception.
A 5 kW nameplate paired with a frame-bonded circuit conductor does not meet the stated insulation condition. Record the generator wiring configuration and product instructions together with its rating. The exception is narrower than the familiar phrase small portable generator, and it does not establish compliance with separate installation or grounding requirements.
Construction work and construction-like maintenance differ
OSHA's 2008 notice distinguishes Part 1926 construction from construction-like maintenance under Part 1910. For general-industry temporary wiring, one extension cord from a permanent receptacle is ordinarily part of the utilization equipment. The construction rule uses different language.
The notice treats multiple extensions from one permanent outlet, or multiple equipment loads temporarily supplied from an extension, as temporary wiring in its general-industry discussion. Classify the work before applying that distinction.
Record the device or grounding program actually used
A jobsite note saying GFI checked should identify the actual device or protected outlet and the result. With a portable unit, include the source outlet and the cord section it protects. With an employer grounding program, identify that program explicitly so the record leads to the procedures, responsible person, and current test records.
The AEGCP guide supplies the program requirements. OSHA 1926.404(b)(1)(i) states that the GFCI-or-program requirement is additional to equipment-grounding-conductor requirements. A protection method therefore does not authorize removing grounding contacts or leaving equipment that requires grounding without its grounding path.
Distinctions
- GFI versus GFCI
- GFI is shorthand used in conversation and site notes. It does not designate a separate OSHA protection class, trip setting, or alternative to an approved GFCI.
- GFCI test versus assured grounding test
- An operating trip device and an electrically continuous equipment-grounding conductor answer different acceptance questions. The written grounding program must establish its own required conductor tests.
Frequently asked questions
Can a portable GFCI supply jobsite protection?
Yes, when the approved portable product is used for its intended purpose and protects the outlets in use. Identify its source, protected cord segment, and rated conditions rather than recording only its presence.
Does a 30 A receptacle fall under OSHA's 15 A and 20 A wording?
The construction provision at 1926.404(b)(1)(ii) expressly names 120 V, single-phase, 15 A and 20 A receptacles. Other applicable rules and the adopted NEC can impose additional protection requirements; keep each requirement tied to its own source.
Sources checked
Also defined as
- Ground-fault circuit interrupter, protects a person by tripping at 4 to 6 mA of leakage to ground