Field glossary · process

Underpinning

Underpinning establishes permanent support beneath an existing foundation, with acceptance following the load through the new bearing and connections after temporary jacks are released. The critical measurements are applied force, movement by support location, and the final bearing condition. A pump reading supplies pressure only; the cylinder's effective area is needed to calculate force, and that force alone does not establish permanent foundation capacity.

Carrying an existing settled foundation down to firm soil on new piers, connected by brackets under the footing, to stop or reverse settlement.

Used across 2 Anvilfield field guides, most in Concrete.
Updated

What must the permanent support detail carry?

A pier beneath a footing must transmit more than an axial reaction when adjacent excavation exposes it to soil or water pressure. The 2022 NYC Building Code, Chapter 18, as amended, Section 1817.4.1, includes vertical loads and overturning from lateral earth and water pressures in the underpinning bearing calculation. Its resulting bearing pressure must stay within the bearing stratum's allowable pressure.

Identify the footing-to-support connection and lateral restraint on the same detail as the new bearing. A helical-pier bracket, a drilled-pile connection, and a pit-pier contact joint need different evidence of load transfer. The excavation-stage load case also needs review when surrounding ground that previously provided restraint is removed.

NYC pit-pier limits that affect the takeoff

The 2022 NYC Building Code, Section 1817.7, limits pit-pier width to 4 feet unless calculations justify a wider pier. The same section limits nonshrink dry-pack at the foundation-to-pier interface to 3 inches thick and requires the pier bottom at least 1 foot below the future adjacent excavation bottom. These are NYC pit-pier criteria, so identify that method and jurisdiction on the estimate.

NYC Section 1817.7.1.2 requires at least 12 feet clear between open pits, with the evaluation report determining the spacing. For 4-foot-wide pits along a straight wall, 12 feet clear means 16 feet between pit centers. An estimate that treats those numbers as the same spacing misstates how many work fronts can be open together.

NYC Section 1817.7 requires pit-pier preloading by the engineer's designed means. Include the contact material, preload arrangement, staged excavation, and monitoring in the scope rather than pricing only excavated soil and placed concrete.

Jack pressure is not foundation load

Enerpac's basic hydraulics guidance defines cylinder force as hydraulic pressure multiplied by the cylinder's effective area. A pressure reading without the cylinder identity and effective area cannot establish the applied force. Keep the calibration and the working stroke with the load-transfer record.

Enerpac lists 2.24 square inches as the effective area in its RC-106 cylinder calculation. At 5,000 psi, the corresponding nominal force is 11,200 pounds. Changing to a cylinder with a different effective area changes that force even when the pressure gauge reads the same number.

Record that calculated force against the specific support and loading stage. It is a nominal cylinder force; allowable bearing, bracket resistance, connection eccentricity, and retained load after lock-off are separate checks in the permanent support design.

Measure movement through loading and lock-off

Enerpac explains that equal-capacity cylinders connected to one pressure source begin moving at the least-loaded point. Compare pressure and elevation at each support during every designed loading stage; one shared gauge cannot demonstrate synchronized movement.

NYC's 2022 Building Code, Section 1817.9, requires an engineer's monitoring plan defining instruments, reading and reporting frequency, movement and vibration limits, and actions for exceedances, including notification of the commissioner. For a building being underpinned, that section assigns the monitoring plan to the engineer designing the underpinning work.

At underpinning closeout, record elevation before loading, at preload, and after transfer to permanent bearing. Distinguish intentionally achieved lift from movement that continues after the temporary jacks are unloaded. The latter needs resolution against the monitoring plan even when the installation pressure reached its target.

Distinctions

Shoring
Shoring provides support during construction or excavation. Underpinning modifies the existing foundation support; temporary shoring can be part of that operation.
Lifting
Lifting deliberately changes elevation. An underpinning design can accept stabilization without restoring the building to its original elevation.

Underpinning firms following public building alterations use PorchRocket Bid Control to track agency bids and early capital plans before organizing an engineered repair proposal.

Frequently asked questions

Does reaching the specified jack pressure prove the repair is complete?

Completion also depends on the designed permanent connection, load transfer, and movement record. The same pressure can represent different forces with different cylinders.

Can a single pump make all underpinning points rise evenly?

A shared pump does not ensure synchronized movement. Enerpac identifies the need for appropriate flow control or a synchronous system where uniform movement is required.

Sources checked

Also defined as

  • Strengthening or deepening an existing foundation by transferring its load to deeper, stronger soil or to piers

Where this shows up

Related guides

Next step: Define a foundation territory

Back to the full field glossary