Load transfer
Load transfer is the passage of force from one supporting element to another through a defined connection or interface. In underpinning, it is the engagement of new support beneath an existing structure; across a slab joint, it is the sharing of wheel-induced force between panels. The evidence must match the mechanism: sustained support force and movement for a pier, joint response for pavement.
Moving the structure's weight from the old failing path onto the new piers or pit through a bracket or dry-pack
Underpinning: proof load and held load differ
A proof test demonstrates response under a temporary test load. Lock-off establishes the force retained when temporary jacking equipment is removed. Record test load, displacement, preload and the final connection separately; a test peak is not a measurement of the force remaining in the completed support.
For Atlas Resistance Modified Piers in its combined underpinning and tieback procedure, the CHANCE Technical Design Manual specifies testing to 150% of design load. CHANCE's combined underpinning and tieback procedure calls for preloading each Atlas Resistance Modified Pier to at least 95% of design load before lock-off. Those percentages belong to that specified system and sequence.
Pavement: read the response on both sides
FHWA-RD-02-088 defines its commonly used deflection load-transfer efficiency as LTE = 100 × unloaded-side deflection / loaded-side deflection. Both readings come from corresponding positions beside the joint under the same loading event. Equal deflections give 100%; a nearly stationary unloaded edge gives a result near zero.
FHWA also reports that stress-based and deflection-based efficiency do not have a one-to-one relationship. Identify which metric a test report uses before comparing it with another report or an acceptance value. Record the load position and sensor locations so the comparison represents the same joint condition.
For example, 400 micrometers on the unloaded side and 500 micrometers on the loaded side give 80% deflection LTE and a 100 micrometer differential movement. Those readings do not demonstrate that 80% of the applied wheel force crossed the joint. FHWA treats the deflection ratio and stress reduction as different quantities.
Close the force path before closing the record
An underpinning connection needs a record of engaged bearing surfaces, shims or packing, lock-off hardware and measured structural response. An installed pile without an engaged connection has not demonstrated the intended handoff.
Across a slab joint, the useful evidence includes differential deflection, joint opening and support condition under the wheel-load case being investigated. A surface seal does not establish mechanical load transfer beneath it.
Distinctions
- Hydraulic pressure
- A jack-gauge reading in pressure units. Converting it to force requires the effective hydraulic area and the calibrated equipment relationship.
- Electrical load transfer
- Switching power demand between supplies. It does not use structural bearing, pier preload or pavement-efficiency criteria.
Field example
In the CHANCE procedure described above, a modified pier with a 20 kip design load has a 30 kip proof-test target and at least a 19 kip preload before lock-off. The record carries all three values. Recording only '30 kip achieved' leaves the sustained transfer after jack removal unresolved.
Frequently asked questions
Does a successful proof test establish the final transferred load?
It demonstrates behavior during the test. The retained load and structural response depend on the subsequent preload, connection engagement and lock-off record.