Field glossary · measurement
FF / FL
FF describes floor flatness from changes between successive 1 ft slopes; FL describes floor levelness from elevation differences across 10 ft spans. These statistical indices under ASTM E1155/E1155M-23 describe different scales of the profile, so a reported FF 35/FL 25 is neither a slope percentage nor a maximum gap in inches. The survey must identify its test sections, usable runs and overall versus local acceptance limits.
Floor flatness and levelness F-numbers measured under ASTM E1155, lowered by curling after placement
What do the two F-numbers actually measure?
The U.S. Access Board's dimensional-tolerance research describes FF using successive 12 in. elevation differences over a 24 in. length and FL using departures from horizontal over 10 ft. A floor can have little short-distance curvature while still changing elevation along those longer spans. Read both numbers when deciding whether the profile suits the operation.
A specification calls for overall FF 35/FL 25 and local FF 24/FL 17. The survey reports overall 38/27, with one designated local section at 22/18. The overall pair passes, but that section misses the local flatness requirement by 2 points. Its passing FL 18 does not offset its FF 22.
| Report field | What to compare |
|---|---|
| Overall result | The combined test surface against the specified overall FF and FL. |
| Local section result | Each designated section against its minimum local FF and FL. |
| Confidence interval | The uncertainty around an estimate, kept with that estimate rather than treated as a local section. |
Can the profiler fit a valid survey run?
ASCC Position Statement 25 identifies a 2 ft minimum separation between an ASTM E1155 measurement line and a penetration. Lay out the available lines on the penetration plan before the technician arrives. Sleeves and equipment projections can leave an otherwise large test section with too little usable line length.
The Allen Face D-Meter instruction manual says a run shorter than 12 ft is automatically cancelled. That is a limit of this instrument's recording routine. A short equipment pad needs an acceptance method and measurement layout suited to its dimensions.
Two penetrations bound a straight test line with 16 ft clear between their nearest edges. Stopping 2 ft from each edge leaves a 12 ft run, exactly this D-Meter's minimum. A 14 ft clear distance leaves 10 ft and cannot support that run. These are longitudinal clearances; penetrations beside the line also need the required separation.
Keep a run result separate from a section result
A profiler run, a test section and the completed floor are different reporting levels. The D-Meter manual distinguishes individual runs from session aggregates and the aggregate of all sessions. Preserve those identities when exporting data so a reviewer knows which physical area each number represents.
Label the line endpoints, direction and section assignment in the exported survey. Combining sessions from different placements would attach the aggregate to the wrong physical area. Include the acceptance schedule from the floor-flatness guide with the survey map so the overall and local comparisons remain traceable.
What does the 90% confidence interval mean?
Allen Face's D-Meter reports a 90% confidence interval for the FF or FL estimate. Retain that interval with the point estimate rather than discarding it from the exported report. It describes statistical uncertainty in the estimate; its lower endpoint is not another measured local test section.
Allen Face also requires the D-Meter's rubber contact shoes to be clean and correctly positioned on the swivel feet. Attach the instrument setup and survey date to the result; neither a neat-looking profile plot nor a narrow confidence interval demonstrates that those contact conditions were correct.
Distinctions
- Fixed-path vehicle profile
- ASTM E1155/E1155M-23 excludes using its results to enforce contract tolerances for floors primarily serving fixed-path vehicle systems. The actual wheel-path profile supplies a different acceptance basis.
Frequently asked questions
Does FF 35 mean no gap exceeds 1/4 inch under a straightedge?
FF 35 is a statistical profile result, not a point-by-point gap limit. A specified straightedge tolerance needs its own measurement and acceptance record; the FF report does not supply that observation.
Is the confidence-interval minimum the minimum local FF?
No. A confidence bound describes uncertainty around an estimate. A minimum local requirement is compared with results for the designated local test areas.
Sources checked
- ASTM International: E1155/E1155M-23, public scope and use limitations
- Allen Face: D-Meter Instruction Manual, 2022 R2
- ASCC: Position Statement 25, Floor Finishing Specifications, August 2011 update
- U.S. Access Board: Dimensional Tolerances in Construction and for Surface Accessibility, F-number measurement basis
Also defined as
- Datacenter: Floor flatness and levelness numbers measured under ASTM E1155 for the equipment and rack slab
- Floor flatness and levelness F-numbers, measured under ASTM E1155 to ACI 117 tolerances