Special inspection
Special inspection adds permit-required verification for designated work, including systems beyond the structural frame. Under 2024 IBC Section 1705.18, a Group R fire area's occupant load greater than 250 can trigger firestop and joint inspections even in a Risk Category II building. Price the agency visits from the approved scope, installation sequence and concealment dates. The latest published IBC is 2027, but a project's adopted edition and amendments determine its inspection obligations.
A code-required inspection of specific structural work by a qualified, independent inspector, reported to the building official under IBC Chapter 17
The current IBC and the permit edition
ICC offers the 2027 International Building Code in digital form. Identify the code edition and local amendments used for the permit separately from that latest publication. The firestop and EIFS examples below use the 2024 IBC, so their section references stay tied to that edition.
The 2024 IBC Section 1704.2 assigns engagement of the approved inspection agencies to the owner or authorized agent other than the contractor, subject to its exceptions. Identify that contracting party alongside each inspection scope. Combine the structural inspection program with separate rows for the required enclosure and fire-protection work.
Firestop inspection can be triggered by occupant load
The 2024 IBC Section 1705.18 requires special inspection of the specified fire-resistant penetrations and joints in Group R fire areas with an occupant load greater than 250, as well as in high-rise and Risk Category III or IV buildings. The occupant threshold applies to the fire area, rather than a count of penetrations.
A Group R fire area assigned 260 occupants crosses that 250-person trigger even when the building is Risk Category II. An occupant load of exactly 250 does not cross that particular threshold; the other listed triggers still require their own review. Preserve the occupancy and fire-area calculation with the inspection requirement so the reason for that scope remains clear when the tenant layout changes.
Separate EIFS assembly exceptions from barrier inspection
Georgia's SI GL 01-2024 guidelines identify EIFS assembly exceptions for installation over masonry or concrete and over a water-resistive barrier with drainage to the exterior. Their schedule separately calls for inspection of the water-resistive barrier coating over sheathing. Carry that coating as its own scope item when the assembly qualifies for the drainage exception.
ICC-ES evaluation report ESR-2186, Section 4.7, provides a product-level example: its IBC recognition requires special inspection of the water-resistive barrier coating under Section 1705.17.1. Match the selected system's evaluation report and substrate to the ITP inspection rows. An assembly exception and a coating inspection can therefore appear on the same wall schedule.
Close a missed inspection through the approved resolution
Georgia's SI GL 01-2024 guidelines direct the inspection agency to notify the responsible design professional and building official about required inspections missed before concealment. They describe a replacement plan involving exposure or additional tests and inspections, with its acceptability discussed with the building official before implementation. Record the approved method and its findings against each concealed location.
The Georgia guidelines require the final special-inspection report before issuance of the certificate of occupancy. Carry missed-inspection resolutions into that report along with completed inspection and test records. Closing a schedule row without the agreed replacement evidence leaves its underlying inspection gap unresolved.
Distinctions
- Structural observation
- A design professional's observation visit cannot be substituted for a missing agency report. Track the observation findings and the scheduled special-inspection results separately, including the locations and work each actually covered.
Frequently asked questions
Are all data centers automatically Risk Category IV?
Assign risk category from the adopted code and the building's function. The data center label alone does not establish the category or every special-inspection trigger.
Can concealed work be accepted after an inspection was missed?
Use the documented resolution accepted through the design professional and building official. Record the exposure, testing or other approved verification and its result.
Sources checked
- ICC: 2027 International Building Code, current publication
- ICC: 2024 IBC Code and Commentary, public sample including Section 1704.2
- ICC: 2024 IBC transition training, Section 1705.18 firestop inspection in Group R
- City of Rome: Georgia Special Inspections Guidelines, ACEC/SEAOG SI GL 01-2024
- ICC-ES: ESR-2186, Section 4.7, EIFS water-resistive barrier special inspection
Also defined as
- Code-required independent inspection of specific structural and life-safety work, commonly under IBC Chapter 17