Quality assurance (QA)
Quality assurance, or QA, is the planned system that makes conformity with project requirements dependable: qualified suppliers, controlled procedures, competent reviewers and traceable evidence. Auditing an inspection record is one way to test that system. QA asks whether the right acceptance criterion, instrument and authority supported the result; quality control checks the work itself. A witnessed test does not transfer the contractor's quality responsibilities to the owner.
The planning, procedures, roles, and standards that make quality happen, set before the work starts
Audit the evidence behind a passed inspection
Start with one completed record and follow its references backward. Identify the inspected item, governing drawing revision, acceptance criterion, instrument identification, test result and release authority. Then follow the record forward into any covering work or subsequent test that depended on the release. This reveals a broken approval chain that a stack of signed forms can conceal.
In an audit of twelve pressure-test records, two missing instrument certificates create two evidence gaps; they do not establish that two installed systems failed. Record the affected test IDs, instrument serial numbers and test dates, then locate the calibration evidence valid on those dates. Resolving a missing file and repeating an invalid test are different dispositions.
Keep contractor control in place during owner surveillance
FAR 46.105 assigns the contractor responsibility for controlling quality and for retaining required evidence of conformity. Owner access to the records does not shift that work to the owner. The contractor still needs an operating inspection system that covers subcontracted and supplied work.
FAR 52.246-12, August 1996, requires complete contractor inspection records available to the Government. Its paragraph (c) preserves contractor quality-control responsibility and says Government inspection does not constitute or imply acceptance. A witness signature should identify the action witnessed rather than imply transfer of responsibility.
Close the process defect as well as the individual record
ISO's public quality-assurance guidance describes QA as extending from planning and production through testing and delivery. It is a continuing management activity, not a document completed only before mobilization. Review changes in suppliers, procedures and acceptance evidence as the work progresses.
When several records omit the same certificate, repairing the files closes the immediate evidence gap. Preventing recurrence requires a change to the release process, such as a required instrument-reference field and a verification step before the record is accepted. Test that change on the next completed records and retain the result. The construction quality-program guide places that corrective action within the project organization.
Distinctions
- Quality control
- QC checks the work against its acceptance criteria. QA also examines whether those checks and their supporting system remain dependable.
- Acceptance
- Acceptance is an authorized decision under the governing contract. Witnessing or reviewing a test has only the authority assigned to that action.
Frequently asked questions
Can QA find a problem when the installed work passes its tests?
Yes. A test result can pass while its revision, instrument evidence or release authority is incomplete. Resolve the evidence defect and determine its effect on the acceptance decision separately.
Sources checked
Also defined as
- Concrete: The planning and process that prevents defects: the quality plan, procedures, training, and approved submittals set before work starts