Hold point
A hold-point release authorizes a specific next operation on an identified area or assembly. List the required inspection result, release authority, and any expiry conditions before scheduling that operation. NRC Criterion X makes designated mandatory holds subject to the designated representative's consent. A notice period manages attendance; permission to cross the hold comes from the governing release process.
A step the affected work cannot pass until the designated authority releases it on the required evidence
Write a release that identifies the permitted next operation
NRC quality rules in 10 CFR 50 Appendix B, Criterion X, require designated mandatory inspection hold points to appear in the relevant documents and prohibit proceeding without the designated representative's consent. That requirement applies to the nuclear quality scope; construction contracts use their own ITP and specification to establish comparable release authority.
Write the release against a location and operation: 'Tank T-2, floor zone C, surface preparation accepted for primer under the specified conditions.' A general 'inspection complete' entry leaves the applicator unable to tell which surface, coating stage, or outstanding correction the signature covers. The tank coating scope guide shows where to put those boundaries in the bid.
Attendance does not change the contract
FAR 52.246-12(c) states that Government inspections do not constitute or imply acceptance of federal construction work. Paragraph (d) also prevents an inspector from changing specification terms without the Contracting Officer's written authorization. A witnessed test therefore needs its result and applicable acceptance record, not just the visitor's signature.
If a witness observes a failed test, the hold remains unresolved unless the authorized process establishes another disposition. Record the failure and the required repeat or repair. A photograph of the witness beside the equipment proves attendance; it does not prove that the equipment met the specified criterion.
Schedule the notice window and the readiness check separately
For an ITP requiring 48 hours' notice, a request issued Monday at 10:00 supports a Wednesday 10:00 inspection slot under that stated elapsed-time rule. Confirm whether the contract instead counts working hours or business days. The notice rule belongs to the project, and the release still depends on readiness and the inspection outcome.
FAR 52.246-12(e) allows the Government to charge additional inspection costs when work is not ready at the contractor's specified time or rejection makes retesting necessary. Use an internal readiness review before calling the witness: approved documents available, work accessible, instruments ready, and prerequisite tests complete. Releasing only the inspected area lets unaffected work proceed without silently extending the approval.
Distinctions
- Hold point versus witness point
- A witness point reserves an attendance opportunity under the ITP notice rules. A mandatory hold retains the release requirement when the inspector is absent. Read the project-specific waiver and notice provisions before scheduling the next operation.
- Partial release
- A partial release permits the named operation in the accepted area. Uninspected locations and unresolved defects stay outside its scope.
Frequently asked questions
Does the end of the notice window release a mandatory hold?
Only if the governing hold-point procedure provides an authorized release or waiver. Expiration of the notice period alone is not permission to cross a mandatory hold.
Sources checked
Also defined as
- Paving: A step in the build where the next layer buries the last, so it is inspected and signed off before work continues
- Concrete: A defined stage where the specified inspection and release must occur before the next work proceeds.