Field glossary · process
Inspection and test plan (ITP)
An inspection and test plan (ITP) connects each work lot to its acceptance rule, required tests and release evidence. Lot boundaries matter numerically: test counts rounded up within each lot can exceed counts calculated from the combined area. Queensland MRTS50 also makes reduced testing conditional on four consecutive conforming lots, a controlled process and a reduced level already stated in the relevant specification. A useful ITP carries those frequency rules through production changes.
The document listing, per activity, what is inspected or tested, when, to what criteria, by whom, the record, and the hold or witness point
Choose the lot before calculating test coverage
Queensland's MRTS50, March 2025, requires compliance assessment, inspection, sampling and testing to be based on lots. The lot gives the result its boundary. A density result without its layer, location and lot identification cannot establish which portion of the work was offered for acceptance.
For an ITP row requiring one test per 500 square metres or part thereof in each lot, calculate the test count by dividing each lot's area by 500 and rounding up before adding the counts. The project row establishes the frequency; MRTS50 supplies the requirement to assess compliance by lot.
Define lots from the controlling specification and actual production conditions before calculating coverage. Combining test areas on a spreadsheet cannot turn separately accepted work into one lot.
| Lot arrangement | Calculation for each lot | Total tests |
|---|---|---|
| One 1,200 square metre lot | 1,200 / 500 = 2.4, rounded up to 3 | 3 |
| Two separate 600 square metre lots | 600 / 500 = 1.2, rounded up to 2 in each | 4 |
Write the rule that increases or reduces testing
MRTS50 requires a contractor-proposed testing frequency to reach the Administrator at least 14 days before testing when the contract states no minimum frequency or count. An empty frequency cell therefore needs resolution before production, rather than an inspector choosing a convenient number during the test.
MRTS50 permits a specified reduced testing level after four consecutive lots without nonconformances and evidence that the process remains controlled and consistent. It does not create a reduced rate where the relevant specification supplies none. Write both the qualifying conditions and the specified reduced frequency into the ITP.
MRTS50 requires an immediate return from reduced to normal testing for all standards and requirements when any requirement for a lot becomes nonconforming. Flag that transition in the lot register. Leaving an old reduced-frequency instruction on an open field sheet lets the testing program continue at the wrong intensity.
Track the test and the report as separate events
The commissioning provisions of NAVFAC UFGS 01 45 00, August 2023 with Change 4 of August 2026, require the Testing Plan and Log to show both the test date and the date results were forwarded to the Contracting Officer. Carry both dates when those provisions are included in the project specification; a completed test can still have an outstanding report.
Add a report identifier and the applicable requirement revision to each completed row in the construction ITP matrix. Define which lots use a revised instruction and retain earlier instructions with earlier results. That history distinguishes a changed acceptance requirement from a changed test outcome.
Distinctions
- Test procedure
- A pressure-test procedure can be reused across several pipe lots. Each ITP row still needs its own location, test frequency and release record; sharing the procedure does not combine the lots.
- Testing log
- A log entry saying tested establishes an event. The linked ITP row must still identify the criterion and report needed to accept that particular lot.
Frequently asked questions
Can a good run justify fewer tests?
Use the reduction mechanism in the controlling specification. MRTS50 combines four consecutive conforming lots with process-control evidence and an available specified reduced level.
Should a revised ITP replace the old file?
Issue the new revision for the work it governs and retain the old revision with the lots inspected under it. The inspection history needs both.
Sources checked
Also defined as
- Concrete: The matrix listing each activity, its standard, acceptance criteria, method, frequency, responsibility, hold or witness point, and record